Time Management Flashcards
What is the process of time
management?
Plan Schedule Management
Define Activities
Sequence Activities
Estimate Activities Resources
Estimate Activities Durations
Develop Schedule
Control Schedule
What is the key output of the Plan
Schedule Management process?
Schedule management plan
What are the key outputs of the Define
Activities process?
Activity list
Activity attributes
Milestone list
What are the key outputs of the
Sequence Activity process?
Network diagrams
Updates to project documents
What are some the key outputs of the
Estimate Activity Resources process?
Activity resource requirements
Resource breakdown structure
What are the key outputs of the Estimate
Activity Duration process?
Activity duration estimate
Updates to projects documents
What does the Develop Schedule process
involve?
What are some of its key outputs?
Creating a project schedule that is
bought into, approved, realistic, and
formal
Project schedule
Schedule baseline
Updates to the project management plan
and project documents
What are the key outputs of the Control
Schedule process?
Work performance information
Schedule forecasts
Change requests
What are the 4 types of logical
relationships between activities in the
precedence diagramming method?
Finish-to-Start (FS): An activity must
finish before the successor can start
Start-to-start (SS): An activity must start
before the successor can start
Finish-to-finish (FF): An activity must
finish before the successor can finish
Start-to-finish (SF): An activity must
start before the successor can finish
What are mandatory dependencies?
What are discretionary dependencies?
Mandatory: The order in which
activities MUST be done, due to the
inherent nature of the work; also called
“hard logic”
Discretionary: The order in which the
organization has CHOSEN that activities
be performed; also called “preferred”,
“preferential”, or “soft logic”
What are external dependencies?
What are internal dependencies?
External:Dependencies based on the
needs of a party OUTSIDE the project
Internal: Dependencies based on the
needs of the project; may be under the
control of the project team
What is a lag?
What is a lead?
Lag: Waiting time inserted between
activies
Lead: How soon an activity can start
before its predecessor activity is
completed
What is a resource breakdown structure?
An organizational chart or table showing
identified resources, organized by
category and type
How does a schedule model differ from
a schedule?
The schedule model consists of all the
project data that will be used to calculate
the schedule, such as the activities,
dependencies, leads and lags, etc.
The project schedule is the output of the
schedule model - this refers to the final,
printed dates that makes up the schedule
that becomes the baseline and part of the
project management plan
What is the critical path?
What is the near-critical path?
Critical: the longest path through the
network diagram
Near-critical: The path closest in lenght
to the critical path