Time Management Flashcards

1
Q

What is the process of time

management?

A

Plan Schedule Management

Define Activities

Sequence Activities

Estimate Activities Resources

Estimate Activities Durations

Develop Schedule

Control Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the key output of the Plan

Schedule Management process?

A

Schedule management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key outputs of the Define

Activities process?

A

Activity list

Activity attributes

Milestone list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the key outputs of the

Sequence Activity process?

A

Network diagrams

Updates to project documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are some the key outputs of the

Estimate Activity Resources process?

A

Activity resource requirements

Resource breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the key outputs of the Estimate

Activity Duration process?

A

Activity duration estimate

Updates to projects documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does the Develop Schedule process
involve?

What are some of its key outputs?

A

Creating a project schedule that is
bought into, approved, realistic, and
formal

Project schedule

Schedule baseline

Updates to the project management plan
and project documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the key outputs of the Control

Schedule process?

A

Work performance information

Schedule forecasts

Change requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the 4 types of logical
relationships between activities in the
precedence diagramming method?

A

Finish-to-Start (FS): An activity must
finish before the successor can start

Start-to-start (SS): An activity must start
before the successor can start

Finish-to-finish (FF): An activity must
finish before the successor can finish

Start-to-finish (SF): An activity must
start before the successor can finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are mandatory dependencies?

What are discretionary dependencies?

A

Mandatory: The order in which
activities MUST be done, due to the
inherent nature of the work; also called
“hard logic”

Discretionary: The order in which the
organization has CHOSEN that activities
be performed; also called “preferred”,
“preferential”, or “soft logic”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are external dependencies?

What are internal dependencies?

A

External:Dependencies based on the
needs of a party OUTSIDE the project

Internal: Dependencies based on the
needs of the project; may be under the
control of the project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a lag?

What is a lead?

A

Lag: Waiting time inserted between
activies

Lead: How soon an activity can start
before its predecessor activity is
completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a resource breakdown structure?

A

An organizational chart or table showing
identified resources, organized by
category and type

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How does a schedule model differ from

a schedule?

A

The schedule model consists of all the
project data that will be used to calculate
the schedule, such as the activities,
dependencies, leads and lags, etc.

The project schedule is the output of the
schedule model - this refers to the final,
printed dates that makes up the schedule
that becomes the baseline and part of the
project management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the critical path?

What is the near-critical path?

A

Critical: the longest path through the
network diagram

Near-critical: The path closest in lenght
to the critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How does the critical path help us

manage the project?

A

it shows the project manager the
shortest time in which the project can be
completed

It shows the project manager where to
focus his or her time

It is used in compressing or adjusting the
schedule

17
Q

Define total float, free float, and project

float.

A

Total float: the amount of time an
activity can be delayed without delaying
the project en date or an intermediary
milestone

Free float: The amount of time an
activity can be delayed with delaying
the early start date of its successor(s)

Project float: The amount of time the
project can be delayed without affecting
the project’s required end date

18
Q

What are the two formulas for

calculating float?

A

Late start - Early start

OR

Late finish - Early finish

19
Q

What are the methods that can be used

to compress a schedule?

A

Crashing

Fast tracking

20
Q

What is crashing?

A

Adding or adjusting resources in
order to compress the schedule while
maintaining the original project scope

21
Q

What is fast tracking?

A

Compressing the schedule by doing

more critical path activities in parallel

22
Q

What is the critical chain method?

A

A schedule network analysis tool that

builds in buffers at critical milestones

23
Q

What is reestimating?

A

Estimating the project again after
planning to make sure you can still meet
the end date, budget, or other objectives,
and adjusting the project if you cannot

24
Q

What is the resources optimization?

A

Finding ways to adjust the use of

resources

25
Q

What is resource leveling?

A
A resource optimization technique that
keeps the amount of resources used for
each time period constant, resulting in 
a more stable level of resources and a
longer project duration
26
Q

What is resources smoothing?

A

A modified form of resource leveling,
where resources are leveled only within
the limits of the float of their activities,
so the completion dates of activities are
not delayed

27
Q

What is the schedule baseline

A

The approved version of the schedule
model, along with any approved
changes, used to measure project
schedule performance

28
Q

What are the main presentation formats

for a schedule?

A

Network diagrams

Bar charts

Milestone charts

29
Q

What do network diagrams show

A

Dependencies (logical relationships)
between activities

How project activities will flow from
beginning to end

Network diagrams may also be used to
determine the critical path

30
Q

What do simple bar charts show?

A

Project schedule or project status

31
Q

What do milestone charts show?

A

High-level project status

32
Q

What is Monte Carlo analysis?

A
A schedule network analysis technique
used to simulate the project to determine
the likelihood that the project will be
completed by a specific date or for a
specific cost

Also used in Perform Quantitative Risk
Analysis to determine the overall level of
risk on the project