Cost Management Flashcards

1
Q

What is the process of cost management?

A

Plan Cost Management

Estimate Costs

Determine Budget

Control Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the key outputs of the Plan Cost

Management process?

A

Cost management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key inputs to the Estimate

Cost process?

A

Cost management plan

Scope baseline

Project schedule

Human resource management plan

Risk register

Enterprise environmental factors

Organizational process assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the key outputs of the Estimate

Cost process?

A

Activity cost estimates

Basis of estimates

Updates to project documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the key outputs of the

Determine Budget process?

A

Cost baseline

Project funding requirements

Updates to project documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the key outputs of the Control

Costs process?

A

Work performance information

Cost forecasts

Change requests

Updates to project management plan
and project documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the main approaches to cost or

schedule estimating?

A

One-point estimating

Analogous estimating

Bottom-up estimating

Parametric estimating

Three-point estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is analogous estimating?

A
Top-down estimating that use expert
judgement and historical information to
predict the future (for example,"The last
three projects cost $25,000, or took six
months, and so should this one")
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is bottom-up estimating?

A

Creating estimates based on the details
of the project (e.g., from the bottom of
the work breakdown structure), which
are then rolled up into the project estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are parametric estimating?

A
Calculating estimates by looking at the
relationships between variables on an
activity (e.g., cost per line of code, hours
per installation), based on historical
information, industry requirement,
standard metrics, or other sources
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is earned value management, and

how is it used?

A
A method of measuring project
performance that looks at the value
earned for work, accomplished, by
reviewing project performance against
the scope, schedule, and cost baselines

It can be used to predict future cost
performance and project completion
dates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the typical range for a rough

order of magnitude (ROM) estimate?

A

-25 to +75 percent from actual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the typical range for a budget

estimate?

A

-10 percent to +25 percent from actual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the typical range for a definitive

estimate?

A

+/-10 percent from actual

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the difference between a cost

budget and a cost baseline?

A

The cost budget adds management

reserves to the cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the formula for cost variance?

A

CV = EV - AC

17
Q

What is the formula for schedule

variance?

A

SV = EV - PV

18
Q

What is the formula for cost

performance index?

A

CPI = EV / AC

19
Q

What is the formula for schedule

performance index?

A

SPI = EV / PV

20
Q

What are the formulas for estimate at

completion?

A

EAC = AC + bottom-up ETC

EAC = BAC/CPI

EAC = AC + (BAC -EV)

EAC = AC + (BAC-EV)/ (CPI x SPI)

comment: to update

21
Q

What is the formula for estimate to complete?

A

ETC = EAC - AC

22
Q

What is the formula for variance at completion?

A

VAC = BAC - EAC

23
Q

What is the formula for to-complete performance index?

A

TCPI = (BAC -EV) / (BAC - AC)

24
Q

How do variable costs differ from fixed costs?

A

Variable costs vary with the amount of
production or work done on the project.

Fixed costs do not vary with the amount
of production or work done on the project.

25
Q

What is a direct cost?

What is an indirect cost?

A

Direct cost: A cost that is directly attributable to the project.

Indirect cost: Overhead costs or costs incurred for more
than one project.

26
Q

What does life cycle costing mean?

A

Considering cost over the entire life of the product,

not just the cost of the project to create the product

27
Q

What is value analysis?

A

Finding a less costly way of doing essentially the same

work (also know as value engineering)