Socrative Occupational Skills Test Flashcards

1
Q

1.When a ladder is placed against a 22’ (6.7m) high working platform, how far out from the
bottom should the ladder be placed?

A

The range in Ontario is 1:3-1:4, but 1:4 is more common across Canada

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

2.
What safety device is used to hold long stock against the
fence while ripping on the table saw?

A

Feather board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. To assure that a rectangular building is square, what is the diagonal measurement of the
    building if its dimensions are 34’ 6” x 46’
A

57’ 6” (17.525m)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

4.

What is the name given to wood frames to which string lines are secured to layout the building?

A

Batter boards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

5.

What are the three types of grade rods used for suveying and layout?

A

Architects’, Engineers’, and Metric

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

6.If the elevation at the curb is 100.34’ (30.582m) and a 125’ (38.098m) driveway has a 5%
grade, what would the elevation be at the house?

A

106.59’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

7.

What is the distance between from the propety line and the building known as?

A

Set back

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

8.

What should be installed on all open sides of scaffolds over 8’ 2.4m) high?

A

Guardrails

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

9.

What is the main difference between a transit level and a builder’s level?

A

The transit can be used to measure vetical angles.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

10.What is the difference between 100 linear feet of 2 x 12 and 100 board feet?

A

100 Board feet

Board feet o Thickness(in inches)X Depth(in inches)X Length(in linear feet)]÷ 12
= 2” X 12” X 100 linear feet)÷ 12 = 200 Board Feet
Difference = 200 Board Feet - 100 Board Feet = 100 Board Feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. What is the crane operators reaction to the following hand signal?

Thumbs up

A

Boom up

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. What is the missing angle?
A

20° 21’ 16”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

13.

What knot creates a non slip loop in the end of the rope?

A

Bowline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

14.
When the Hypotenuse of a ight angle tiangle is 40, and its height is
32’, what is the length of the base?

A

24’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. A heavy machine requires a circular concrete base that is 13’ in
    diameter. What is the surface area of the base?
A

132.73 ft2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

16.

What is the purpose of a snatch block?

A

to change direction of pull

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

17.

What is the crane operators reaction to the following hand signal?

A

Stop

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

18.

What is the maximum size boulder that can be used in backfill for an excavation?

A

250mnm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

19.
How deep should a trench be before you need to provide a ladder to enter or have the sides
sloped?

A

4’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

20.

What does the following WHMIS symbol represent?

A

Compressed gas

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

21.

How far beyond the face of the chimney wall must a chimney cap project?

A

25mm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

22.
On a builders level with four thumb levelling screws, which direction would you tun the thumb
screws to move the bubble in the vial to the left?

A

turn the screws outward

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

23.

What must castors for steel frame scaffolding have?

A

Working Brakes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

24.

What is the minimum depth below grade for a foundation on clay soil?

A

1.2m

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
25. What would be the minimum length of ladder that could safely be used when the height of the building is 23'?
30'
26
26. When corbelling for masonry veneer, what is the maximum distance beyond the support that a 4" thick brick can project?
25mm
27
27. | Ladders are required to extend how far above working platforms or landings?
0.9M
28
28. Any worker in danger of falling ____m must wear fall protection
3M
29
29. What is the chemical process through which cement hardens when water is added to mixed concrete?
Hydration
30
30. What would the wire rope have to be rated for in order to lift the following? Worker = 210 lbs. Tools = 175 lbs. Material = 225 lbs.
6100 lbs. SF OHSA Cables, Slings, Rigging Strength 169. A cable used by a crane or similar hoisting device shall be capable of suppoting at least, (d) Ten times the maximum load to which it is likely to be subjected if the crane or similar hoisting device is used for supporting persons. O. Reg. 213/91, s. 169. 210lbs + 175lbs + 225lbs = 610lbs ×(10) = 6100 lbs. SF 12'6 1/2" Referring to the highlighted area, we can see that the two spans for our W8X20 beam are 13'7" and 11'6" (wall thicknesses can be ignored): according to the footnotes from the beam tables in the Building code: "3 Supported length means half the sum of the joists spans on both sides of the beam" Therefore: Supported joist length = =(13' - 7" + 11' 6") / 2 =(13.5833333'+11.5') / 2 = 12.5416666 = 12' 6.5"
31
31. | How is a hidden line shown on a set of plans?
Series of short dashes
32
32. In laying out a 24 x 35 rectangle, what are the largest measurements of 345 you could have without going outside your working area?
24-32-40
33
33. | Where is the "D" ring supposed to be located on your full body harness?
In between your shoulder blades
34
34. A tube & clamp scaffold has had one of it’s 2” X 10” mudsills undemined by heavy rain. How should the scaffold be stabilized?
Remove loosened ground and excavate to level, extend scaffold down to new elevation
35
35. Three mirrors are mounted on a wall as shown. What is distance eq.?
1' - 10"
36
36. | Carpenters utilize a circular saw and a _______ cut to remove material from the center of a form.
Plunge
37
37. | Who shall supervise the erection, alteration, and dismantling of a scaffold?
Competent worker
38
Which of the following is recommended for joining two ropes of similar diameter?
Square knot
39
A carpenter is asked to raise a form 2% higher than its existing elevation of 35.25' (10.74 m). What would the new elevation of the form be?
35.955' (10.96m)
40
40. What is the minimum clearance required above the fireplace for a projecting 50mm X 250mm X 1500mm oak mantle?
300mm
41
41. What simple tool is used to layout bevel siding?
Story pole
42
42. The B.M. is 106.42', the H.I. is 111.89' and the F.S. is 3.89'. What is the new elevation?
108.00' New elevation= Height of instrument (H.I.) - Foresight (F.S.) = 111.89' - 3.89' = 108.00'
43
43. | What are the horizontal load bearing members on a tube and clamp scaffold known as?
Transoms
44
44. | A footing form will require 6.5 cubic yards of concrete. How many cubic feet is this?
175.5 ft3
45
45. | What is the maximum moisture content allowed for construction grade lumber by code?
19%
46
46. | When using a forklift, what must you know about the load before picking it?
Weight, dimensions, center of gravity
47
47. | What does the following WHMIS symbol represent?
C. Corrosive materials
48
48. An excavation for a 12” deep footing has been flooded by 6” of water for several days. What needs to be done in order to place concrete?
Pump out the water, excavate mud to undisturbed soil. The footings and foundation walls were designed based on the bearing capacity of the undisturbed soil at the bottom of the excavation. As soon as the soil was saturated with water it's bearing capacity was reduced. Unless the mud is removed after pumping out the water, the building will sink/ shift unpredictably and possibly fail structurally.
49
49. | What is the minimum distance a treatment unit (septic tank) may be located from the building?
1.5m
50
50 .When passing a board through a thickness planer a bun mark appears in a straight line across the width of the board. What would cause this?
The material hesitated and the cutter head is tuning in one spot.
51
51. Which of the following is NOT a proper procedure when cutting with a bandsaw?
Adjust the guides while operating the saw.
52
52. To prevent excessive checking, scaffold planks should:.
Have their ends banded with steel.
53
53. When applying laminate to a countertop:
Apply the side edges first.
54
54. Adjust the guides while operating the saw.
3.354'
55
55. | Convert 6.875' to feet, inches and fractions of an inch.
6' 10 ½"
56
56. Which of the following knots is best for safely shortening a rope?
sheepshank
57
57. What diagonal dimension would you need to use to verify that a building measuring 45' X 27' is square?
52' 5 3/4"
58
58. The main floor of a house has 13 interior doors and 2 exterior doors. Allowing 7' for side casings and 3' for head casings, how many linear feet of material would you need to tim these doors?
476' For inteior doors, we will need to multiply our total by 2, because we will be timming both sides. For exteior doors we only install the casing on the inside: First calculate your total number of sets of casing: 13 inteior doors X 2 sets per door) + exteior doors(inside only)= 26 + 2 = 28 sets Next, calculate how many linear feet you will require for each set: 3' + 7' + 7'= 17' per set Finally, multiply the number of sets by the linear feet per set to determine your total linear feet: 28sets X 17feet/set= 476'
59
59. How many cubic yards of concrete is needed to build a silo with the following specifications? Inner radius= 72'7" Outer radius= 74'3" Height= 125'
3,5589 yd³ First, convent your measurements into decimal feet: inner radius= 72'7" = 72.58333333' outer radius= 74.25' Next, add your outer radius to your inner radius and divide your answer by 2 to determine the measurement from center of silo to the center line of the curved wall: 72.58333334q74.25' = 146.8333334' t2 = 73.41666667 Next, take your new measurement and use it to find the circumference of the silo(the length of the wall in linear feet): Co 2pr = 23.141673.41666667')= 461.2916' Next, determine your wall thickness, and multiply it by your length and height to determine your volume in cubic feet: Length = 461.2916' Thickness = 74'372'7 = 20" ÷ 12 inches/foot = 1.666667' Height = 125' Volume = 461.2916' X 1.666667' X 125' = 96,102.41666667 ft³ Finally, divide your cubic foot total by 27 to convert it into cubic yards: Volume = 96,102.41666667 ft³ ÷ 27 = 3,559.348765 yd³
60
60. | Cove moulding can be shaped on a table saw by feeding the stock:
At approximately 45° to the blade
61
61. | Add 1.125" and 3.375", and convet into inches and fractions of an inch.
4 1/2"
62
62. A building is 35 yards tall, how many feet tall is it?
To convent from yards to feet, take your quantity in yards and multiply it by 3 35 yd. X 3 ft./yd. = 105'
63
63. Referring to "Wall Section A", what is the distance from finished grade to the top of the concrete slab?
6'10" If you refer to the drawing, you can find three key measurements: Distance from top of footing to top of foundation wall= 7'4" Distance from finished grade to top of foundation wall = 2" Thickness of basement slab= 4" Because the slab sits on top of the footing and the measurement in question doesn't include the amount that the wall stick out above grade, both measurements need to be deducted from the overall dimension: Distance from finished grade to top of concrete slab = 7'4" - 2" - 4" = 6'10"
64
Referring to "Wall Section A", how many nails (and at what length) would you need to use at the connection between the 2X6's and 2X8's?
3 nails, 76mm long
65
Referring to "Wall Section A", what is the height from sub-floor to finished ceiling in the second storey if you are using 5/8" drywall?
7' - 6 5/8"
66
66. Referring to "Wall Section A", what is the actual distance of the cantilevered floor frame?
24"
67
68. Referring to "Wall Section A", to what elevation would you excavate for your basement if finished grade elevation is 729' - 3 5/8"
721' - 9 5/8" To determine the depth of our excavation, we must take the total height of our wall (7'4"), deduct the distance the wall projects above finished grade (2"), and add the additional depth required for the layer of gravel that is laid below the slab: Depth of excavation = 7'4" - 2" + 4" = 7'6" = 7.5' Next, you can either keep your measurements in feet and inches and subtract them from your total: 729'3 5/8" - 7'6" = 728'15 5/8" - 7'6" = 721'9 5/8" Or, you can also convent to decimal feet, subtract your distance and convent back to feet, inches and fractions of an inch: 5t8 = 0.625" + 3" = 3.625" ÷ 12 inches/foot = 0.3020833' + 729' = 729.30208333' 729.30208333' - 7.5' = 721.80208333' 721.80208333 - 721 = 0.80208333 X 12 = 9.625 - 9 = 0.625" X 16 = 10/16 = 5/8 = 721' - 9 5/8"
68
Referring to "Wall Section A", what type of material could be used for building paper according to the building code?
No. 15 asphalt-saturated felt laid in two plies lapped 480 mm and cemented together with lap cement.
69
70. Referring to "Wall Section A", the 10" thick drops are included for:
Aesthetics Looking at the section, we can see that the cantilevered section of the floor gets its stuctural support from being incorporated into the second floor framing. The support is provided by the full floor system and diagonal bracing is not required. We can also rule out the possibility of it being a tie in for the bricks, as it sits above the bricks and is tied into the wood sheathing that overlaps the bricks slightly. If you look at the brick section you can see that ties un from the sheathing behind the bricks through the veneer every 5th course.
70
71. Referrring to "Wall Section A", what additional measures must be taken to provide adequate foundation drainage to the structure?
Cover the top and sides of the 4" perforated plastic pipe with at least 150mm of crushed stone.
71
72. | Referring to "Wall Section A", what is the R-value of the attic insulation?
R - 22
72
73. Referring to "Wall Section A", what is the metic equivalent of your ceiling joist dimension?
38mm X 184mm
73
74. Referring to "Wall Section A", what would the minimum thickness be for your subfloor material if you used grade O2 oriented strand board?
15.5mm
74
75. | Referring to "Plan B", what size door is used for the linen closets?
1'6" X 6'8"
75
76. Referring to "Plan B", at least one window in PATRICIA'S BR must provide an unobstructed opening of not less than:
0.35 m² Key words: Bedrooms, egress from 9.9.10. Egress from Bedrooms 9.9.10.1. Egress Windows or Doors for Bedrooms (1)Except where a door on the same floor level as the bedroom provides direct access to the exteior, every floor level containing a bedroom in a suite shall be provided with at least one outside window that, (a) is openable from the inside without the use of tools, (b) provides an individual, unobstructed open potion having a minimum area of 0.35 m² with no dimension less than 380 mm, and...
76
77. Referring to "Plan B", the length of the STUDY is:
14' - 9" The total room length is given, but there aren't dimension lines to full identify it. However, if you take the four dimensions listed in line from one wall to the other and add them, you should come to the same dimension: 3' 5"+ 3'5" + 4'6" + 3'5"= 14' - 9"
77
78. Referring to "Plan B", you need to reduce the hallway leading to RICKY'S BR. What is the minimum unobstructed width you can reduce the hallway to?
860 mm Key words: Hallways, hallway width 9.5.10. Hallways 9.5.10.1. Hallway Width (1)The unobstructed width of a hallway within a dwelling unit shall be not less than 860 mm, except that the hallway width is permitted to be 710 mm, where, (a) there are only bedrooms and bathrooms at the end of the hallway furthest from the living area, and (b) a second exit is provided, Note: No second exit provided.
78
79. Referring to "Plan B", what type of plan is this?
2nd floor plan Only the structure is shown, so it can't be a site plan. No foundation is shown and the garage roof is shown, so it can't be the basement plan. There aren't any exterior doors, so it isn't our first floor plan. Therefore, it must be our 2nd floor plan.
79
80. Referring to "Plan B", how much clearance is required between the STUDY wall wood framing and the masonry chimney?
50 mm Key words: Framing, materials, clearance from masonry or concrete chimneys Section 9.21. Masonry and Concrete Chimneys and Flues 9.21.5.1. Clearance from Combustible Materials (1) The clearance between masonry or concrete chimneys and combustible framing material shall be not less than, (a) 50 mm for interior chimneys, and (b) 12 mm for exterior chimneys.
80
81. Referring to "Plan C", how many cubic feet of concrete would you need for your column footings?
20 ft.³ Referring to the note next to the column in the RECREATION, we can see that our footings have the following dimensions: Width= 2' Length= 2' Depth= 1' First, determine the volume of a single footing: Volume = Width X Length X Depth = 2' X 2' X 1' = 4 ft³ Next, multiply the volume of a single footing by the total number of footings: 4 ft³/footing X 5 footings = 20 ft³
81
82. Referring to "Plan C", if you used unreinforced 10" concrete block in place of the poured concrete for your foundation wall, what would the maximum allowable height of finished ground above basement floor be (foundation wall is laterally supported at the top)?
1.8 m Foundation walls 9.15.4.2. Foundation Wall Thickness and Required Lateral Support (1) Except as required in Sentence (2), the thickness of foundation walls made of unreinforced concrete block or solid concrete and subject to lateral earth pressure shall conform to Table 9.15.4.2.A. for walls not exceeding 3.0m in unsupported height.
82
83. Referring to "Plan C", what room is the floor drain in?
Shop
83
84. Referring to "Plan C", what is the dimension of distance "Z"?
48' - 9" Looking at the highlighted area that is inside the building footprint, we can see that dimension "Z" goes from the center of one 10" common wall to the center of another 10" exterior wall at the top of the drawing. We can also see from the other highlighted area that the overall length of the building is 62'7". To determine distance "Z", we can do the following: First, we take the width of our excavated area (12' - 2") and add two wall thicknesses (1 thickness on either side of the excavated area): 12' 2 + (10" X 2) = 12' - 2" + 20" = 13' -10" Next, we can subtract our new dimension from the overall length of our building to determine our distance from the outside face of the common wall to the outside face of the exterior wall: Z = (62' - 7") - (13'-10") = 61'19" - 13'10" = 48'9" Although this measurement represents the distance from the inside face of our common wall to the outside face of our exterior wall, the measurement of "Z" will be the same value because both walls are the same thickness and offset one another.
84
85. Referring to "Plan C", what is the supported joist length for the W8X20 beam in the GAME ROOM?
12' - 6 1/2"
85
86. Referring to "Plan C", how many pilasters are there?
5
86
87. What is the minimum clearance required above a fireplace for a projecting 50 mm X 250 mm X 1,500 mm oak mantle shelf?
300 Section 9.22. Fireplaces 9.22.9. Clearance of Combustible Material 9.22.9.1. Clearance to the Fireplace Opening (1)Combustible material shall not be placed on or near the face of a fireplace within 150 mm of the fireplace opening, except that where the combustible material projects more than 38 mm out from the face of the fireplace above the opening, such material shall be at least 300 mm above the top of the opening.
87
88.What are the three parts of a knot?
Standing part, bight, and running end.
88
89.What is the minimum safe distance you must maintain from a 125,000 volt powerline while working?
3 m OHSA: Proximity to electrical conductors 188. (1) This section applies unless the conditions set out in the clauses 189 (a) and (b) are satisfied. O.Reg. 627/05,s.7.
89
90.At what height does a system scaffold need to have an engineered drawing?
10 m OHSA: Scaffold design, installation 130. (1) A scaffold shall be designed by a professional engineer and shall be erected in accordance with the design if the scaffold exceeds, (a) fifteen meters in height above its base support; or (b) ten meters in height above its base support if the scaffold is constructed of a tube and clamp system. O.Reg. 213/91, s. 130 (1) Note: (a) applies to system scaffolds and (b) applies to tube and clamp scaffolds.
90
91. An angle greater than 90° but less than 180° is called:
Obtuse
91
92. A sheet of plywood has 5 equal layers (ply's). What is the thickness of each layer if the overall thickness is 0.019 m?
0.0038 m To find the thickness of each layer, take your overall thickness and divide it by the number of layers: 0.019 m ÷ 5 layers = 0.0038 m/layer
92
93. An apprentice cuts a piece of stock into 4 pieces. The lengths are 3 3/8", 2 7/6", 4 1/2", and 1 1/4". If 1/8" is used up for each saw kerf, what is the original length of the board?
11 15/16" To create four pieces, we will need to make three saw cuts (see drawing). Therefore, to determine the overall piece of material we stated with we need to convent our four lengths of material into decimal inches, and add them to the decimal inch equivalent of three saw kerfs ( 3cuts X 1/8 inch/cut = 3/8"): ``` Original length of material = 3 3/8 + 2 7/16"+ 4 1/2" + 1 1/4"+ 3/8" = 3.375" + 2.4375" + 4.5" + 1.25" + 0.375" = 11.9375" = 11 15/16" ```
93
94. How many square yards of drywall would you need to cover a wall measuring 22'0" X 9'0"?
22 yd² First, calculate your wall area in square feet: 22' X 9' = 198 ft² Then, divide your area by the number of square feet in a square yard: 1 yd² = 3' X 3' = 9 ft² area in square yards = 198 ft² ÷ 9 ft²/yd² = 22 yd²
94
95. | How much weight is a heavy duty scaffold rated for?
75 lbs./ft²
95
96. How many cubic inches of wood chips are there in a tank containing 15 cubic feet of them?
25,920 in³ First, we must determine the number of cubic inches in a cubic foot: looking at the drawing, we can see that a cubic foot is 12" long, 12" wide, and 12" high: volume in cubic inches in a cubic foot = 12" X 12" X 12" = 1,728 in³/ft³ Next, we need to multiply our total in cubic feet by the number of cubic inches in a cubic foot: 15 ft³ X 1,728 in³/ft³ = 25,920 in³
96
97. What is the purpose of dimple board membrane?
Answer: To provide a drainage later for foundation walls below grade.
97
98. What is the main purpose of installing coarse gravel under concrete slabs?
To mitigate the effects of capillary action
98
99. What is the maximum size of structure that can be built under pat 9 of the building code?
A 3 storeys and A 600 m² per floor. Key words: Pat 9 Section 9.1. General 9.1.1. Application 9.1.1.1. Scope 1 The scope of this Pat shall be as described in Subsection 1.1.2. of Division A. 1.1.2.4. Application of Pat 9 1 Subject to Aticles 1.1.2.6. and 1.3.1.2., Pat 9 of Division B applies to all buildings, (a) of three or fewer storeys in building height, (b) having a building area not exceeding 600 m2 , and (c) used for major occupancies classified as, (i) Group C, residential occupancies, (ii) Group D, business and personal services occupancies, (iii) Group E, mercantile occupancies, or (iv) Group F, Divisions 2 and 3, medium hazard industrial occupancies and low hazard industrial occupancies
99
100. Who typically prepares shop drawings?
Suppliers for the architect