- 0PGP03-ZA-0090 Work Process Program*
- *
What is a medium risk work activity?
Cause / Would Cause:
Power reduction < 20%
Unplanned LCO entry
Emergent single point failure configuration
Reactivity management work level of R1, R2, or R3 when no compensatory/contigency actions are covered by procedure
Atypical plant configuration
ESF actuation
Loss of switchyard North or South Bus
- 0PGP03-ZA-0090 Work Process Program*
- *
What events present an operational challenge?
Unplanned power change
Unplanned LCO entry
Unplanned duration that exceeds 75% of LCO action statement
Unplanned increase in CDF or BOP trip risk
Failure to identify medium/high risk activity
Several others but these are the important ones
- 0PGP03-ZA-0090 Work Process Program*
- *
What is a high risk work activity?
Cause / Would Cause:
Unit loses all power generation capability
Reduce power ≥ 20%
Entry into LCO that requires S/D in ≤ 24 hrs
- 0PGP03-ZA-0090 Work Process Program*
- *
Whose permission is required to start emergent work without an approved work package?
Shift Manager
Emergency Director