SEPS Flashcards
1
Q
State assumption for SEPS
A
No seismic events or safeguards actuation
2
Q
State SEPS auto start signal
A
After a 30 second TD from a LOP as sensed from:
- MCC-152
AND
- US-63
3
Q
State how SEPS can extend EDG LCO action
A
The requirement for restoration of the diesel generator to OPERABLE status within 72 hours may be extended to 14** days if (SEPS) is available, as specified in the Bases,
and
(b) If at any time the SEPS availability cannot be met, either restore the SEPS to available status within 72 hours (not to exceed 14 days from the time the diesel generator originally became inoperable), or be in at least HOT STANDBY within the next 6 hours and in COLD SHUTDOWN within the following 30 hours.