Schedule Flashcards
The two most notable trends currently impacting scheduling are
- Iterative scheduling with a backlog
2. On-demand scheduling
Iterative scheduling with a backlog
a type of rolling wave planning used in adaptive project management (such as Agile) to deliver incremental value to the customer during an iteration.
back log
The backlog is the list of features that have yet to be developed during the current increment.
user story
A brief description of deliverable value for a specific user.
The schedule is based on project requirements that are documented with user stories. User stories are prioritized and clarified to define the requirements for
product features that are developed within a defined work period (a time-boxed period).
On-demand scheduling
an approach typically used in a Kanban system to limit the team’s work in progress in order to balance demand against throughput.
The schedule is subject to the availability of resources:
Plan Schedule Management
the process of establishing the policies, procedures and documentation for planning, managing and controlling the project schedule.
Plan Schedule Management
benefit
guidance and direction of how schedule will be managed throughout the project
Plan Schedule Management
inputs
- project charter (milestone sturcuture)
- pmp: scp mt plan & development approach
- EEF (scheduling software & commercial database)
- OPA (monitoring and reporting tools)
Plan Schedule Management
TT
EDM
Plan Schedule Management
outputs
Schedule Management Plan
schedule management plan establishes
- project schedule model development maintenance practices
- level of accuracy that will be required for activity duration estimates
- units of measure (time and quantity) that will be used for each resource
- Organizational procedures links based on the WBS
- Control thresholds for monitoring schedule performance
- rules of perf measurement
Define Activities
determining and listing the activities required to create the deliverables of the project
Note: list is created without regard to necessary resources, start dates, or completion dates
Define Activities
benefit
it decompose the work packages into schedule activities that provides a basis for..
Define Activities
inputs
- schedule mt plan
- scope baseline
Define Activities
TT
E+M
Decomposition
RWP (rolling wave planning)
Define Activities
outputs
- activity list
- activity attributes
- milestone list
Activity List
The activity list enumerates each schedule activity
stipulated for the project, including its IDENTIFIER and
SCOPE DESCRIPTION sufficiently DETAILED to ensure an understanding of the work by each team member.
NOT a component of the WBS.
break down the activity list to the point where the activities are 4-80 hours in duration.
Activity Attributes
clarify an activity by identifying multiple components related to the activity.
The components evolve during the project. When completed:
a description of the activity, predecessor and successor activities, logical relationships, leads and
lags, resource needs, constraints, assumptions, and exact dates.
Rolling Wave Planning
TT of define activities
concept that utilizes the progressive elaboration concept in planning.
work to be done in the near term is planning in detail, work further in the future is planned at higher level
Control Accounts
specific points in the WBS where the project scope,
budget, actual cost, and schedule are combined
Planning Package
a piece of the WBS above the work package. It is used
to plan work that has been scoped but lacks sufficient
work package level details.
Sequence Activities
identifying and documenting relationships among project activities
Sequence Activities
benefit
defines the logical sequence of the work to obtain the greatest efficiency giving all the constrains.
Sequence Activities
inputs
- schedule mt plan
- scope baseline
- activity list
- milestone list
Sequence Activities
TT
- PDM (Precedence Diagramming Method)
- Dependency Determination and Integration
- Leads and Lags
Sequence Activities
outputs
- PSDM (Project Schedule Network Diagrams)
2. activity attributes
four types of dependency attributes
- mandatory (legally or contractually required)
- discretionary (preferred, based on best practices)
- external (usually out of the project team’s control)
- internal (relationship between project activities)
FS
successor cannot start until predecessor finishes
most common
FF
successor cannot finish until predecessor finishes