Definition Flashcards
Plan schedule
management
provides guidance for creating an appropriately detailed schedule,
establishing control thresholds, and updating/modifying the schedule
as necessary.
Define Activities
determining and listing the
activities required to create the deliverables of the project.
Note that the list is created without regard to necessary
resources, start dates, or completion dates.
Sequence Activities
the arrangement of activities in the most efficient and
effective order.
Estimate Activity Durations
the number of
workdays (or hours) to complete each activity is estimated.
Develop Schedule
Note: planning
the creation of activity lists, the sequencing of activities, and the estimation of activity durations
all come together to create the project schedule (and schedule baseline)
Control Schedule
changes to the schedule
are managed and controlled
(forecasts)