Schedule Flashcards
A key document is schedule management plan what is this from
Plan schedule management
A key document is scheduled baseline what is this from
Develop schedule
A key document is a project schedule what is this from
Develop schedule
This provides a how-to direction to the team regarding a schedule management and produces the schedule management plan
Plan schedule management
This decomposes the scope of the project into a project schedule activities
Define activities
This sequence is the activities to optimize the schedule
Sequence activities
This estimates the time frames required to complete the schedule activities
Estimate activity durations
This creates the project schedule and the schedule baseline
Develop schedule
This maintains and controls the schedule baseline
Control schedule
Project schedule model development, level of accuracy, units of measure, organizational procedures, and project schedule maintenance are all components of what
Schedule management plan
Steps for developing the schedule
Decompose the work packages of the WBS into activities
And milestones
Sequence the activities in order to optimize the schedule
Estimate resource and durations of the activities
Determine the critical path of the project
A proven baseline the schedule
The critical path is the
Longest path with no floats
What is resource leveling
Spreading it out and no one works overtime
What is resource smoothing
Protects the critical path and find someone else to do it
What is fast track
Bringing an items and doing it parallel to get back on track