Q
Ev=
A
Bac * percent complete
2
Q
Cv=
A
Ev-ac
3
Q
Cpi=
A
Ev/ac
4
Q
Eac=
A
Bac/cpi
5
Q
Etc=
A
Eac-ac
6
Q
Tcpi =
A
Bac - ev
/
Bac-ac
7
Q
Sv=
A
Ev-pv
8
Q
Spi=
A
Ev/pv
9
Q
What is earned value?
A
The value of the completed work
10
Q
What is planned value
A
The budget assigned to the work (known as of planning)
11
Q
What is actual cost
A
The realize cost assigned to the work completed
12
Q
What is npv
A
Net present value
13
Q
How do you get pv (present value)
A
Fv or future value / (1 + I or interest rate) x n or number of years
14
Q
Nps
A
Net promoter score
15
Q
Pert
A
Optimistic plus four times most likely plus pessimistic divided by 6