Formulas Flashcards

1
Q

Ev=

A

Bac * percent complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Cv=

A

Ev-ac

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cpi=

A

Ev/ac

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Eac=

A

Bac/cpi

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Etc=

A

Eac-ac

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Tcpi =

A

Bac - ev
/
Bac-ac

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Sv=

A

Ev-pv

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Spi=

A

Ev/pv

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is earned value?

A

The value of the completed work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is planned value

A

The budget assigned to the work (known as of planning)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is actual cost

A

The realize cost assigned to the work completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is npv

A

Net present value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How do you get pv (present value)

A

Fv or future value / (1 + I or interest rate) x n or number of years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Nps

A

Net promoter score

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Pert

A

Optimistic plus four times most likely plus pessimistic divided by 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly