Acronyms Flashcards
CV
Cost variance
EV
Earned value
CPI
Cost performance index
CPI values > 1.0 indicate a project is under planned cost
CPI values = 1.0 indicate a project is on planned cost
CPI values < 1.0 indicate a project is over planned cost
BAC
Budget at completion
AC
Actual cost
SV
Schedule value
PV
Planned value
TCPI
To complete performance index
When TCPI is greater than 1.0, the project will be harder to complete than planned.
When TCPI is exactly 1.0, the project will be the same to complete as planned.
When TCPI is less than 1.0, the project will be easier to complete than planned.
SPI
Schedule performance index
MVP
Minimum viable products
MBI
Minimum business increments
A hierarchy decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables
Work breakdown structure
What is the 100 percent rule
The 100% rule means that if it is not represented in the WBS than it is not on the scope it is now focus
What is the lowest level of the WBS
Work packages
Management control point for scope schedule and cost typically at the end of the roll up level of the WBS
Control accounts