Acronyms Flashcards

1
Q

CV

A

Cost variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EV

A

Earned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CPI

A

Cost performance index
CPI values > 1.0 indicate a project is under planned cost
CPI values = 1.0 indicate a project is on planned cost
CPI values < 1.0 indicate a project is over planned cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

BAC

A

Budget at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

AC

A

Actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SV

A

Schedule value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

PV

A

Planned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

TCPI

A

To complete performance index
When TCPI is greater than 1.0, the project will be harder to complete than planned.

When TCPI is exactly 1.0, the project will be the same to complete as planned.

When TCPI is less than 1.0, the project will be easier to complete than planned.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

SPI

A

Schedule performance index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

MVP

A

Minimum viable products

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

MBI

A

Minimum business increments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A hierarchy decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables

A

Work breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the 100 percent rule

A

The 100% rule means that if it is not represented in the WBS than it is not on the scope it is now focus

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the lowest level of the WBS

A

Work packages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Management control point for scope schedule and cost typically at the end of the roll up level of the WBS

A

Control accounts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Numbering system used to identify the components of the WBS

A

Code of accounts

17
Q

A component of the WBS with known content but incomplete schedule information

A

Planning packages

18
Q

What type of organizational structure has a part time pm

A

Functional organization