Negotiate Project Agreements Flashcards
What is the Moscow technique
Must have should have could have won’t have
What is a paired comparison
Directly compares options to rank a shortlist
What is used to organize a requirement list? Example basic performance excitement in different reverse used to build a project
Kano model
What type of project has an objectives of agreement that must be met below: stage gates, scope acceptance, milestones, closure approvals and handoffs
Traditional
These verify objectives of agreement have been met for what type of project? Backlog assessments, iteration closure, product review, retrospectives
Agile
Identifying stakeholders is not a one-time process and can be conducted several times throughout the project Life cycle after a major change. You start this at the beginning of the project which means it in what process group?
Initiating
The salience model shows what three dimensions
Power legitimacy and urgency
What plan shows details on how effected stakeholder management can be realized and must be reviewed and updated regularly the lifecycle process
Stakeholder engagement plan