Negotiate Project Agreements Flashcards

1
Q

What is the Moscow technique

A

Must have should have could have won’t have

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a paired comparison

A

Directly compares options to rank a shortlist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is used to organize a requirement list? Example basic performance excitement in different reverse used to build a project

A

Kano model

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What type of project has an objectives of agreement that must be met below: stage gates, scope acceptance, milestones, closure approvals and handoffs

A

Traditional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

These verify objectives of agreement have been met for what type of project? Backlog assessments, iteration closure, product review, retrospectives

A

Agile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Identifying stakeholders is not a one-time process and can be conducted several times throughout the project Life cycle after a major change. You start this at the beginning of the project which means it in what process group?

A

Initiating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The salience model shows what three dimensions

A

Power legitimacy and urgency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What plan shows details on how effected stakeholder management can be realized and must be reviewed and updated regularly the lifecycle process

A

Stakeholder engagement plan