Risk Management Flashcards
What guidance is available in relation to the Management of Risk on a Construction project?
RICS guidance note called management of risk 1st edn 2016
Have you been involved in the preparation of a Risk Register?
Yes - I have on several projects, working with whole design teams to amalgamate a list of risks, the level of threat they pose to the project and potential mitigations. I have then had experience costing these risks.
What does the RICS Guidance Note say in relation to the allocation of Risk?
It defines it as how the responsibility for risk is split between the contracted parties
That it is dependent on the procurement route being used
What are the 4 categories of Risk identified under NRM 1?
Design development
Construction
Employer change
Employer Other
Can you give me an example of a Risk Quantification Technique?
Percentage addition
Percentage addition is based on a percentage of the cost
plan and should only be used for preparing rough and
initial order cost estimates.
A percentage risk for all elements of the project where risk is expected is derived,
multiplied by the cost of that element and then totalled to
give an overall risk allowance.
For example, 5% x
£100,000 construction costs (£5,000) + 10% x £10,000
design team cost (£1,000) gives a risk allowance of
£6,000.
Have you heard of the Term a ‘Monte Carlo’ Simulation? What does this relate to in relation to the Management of Risk, and associated Costing?
This is a computer-generated simulation used to model outcomes.
The inputs for a quantitative risk analysis (QRA) are typically the probability values for each risk and an assessment of their impact; for example, a minimum cost
impact of £10,000, a most likely cost impact of £15,000 and a maximum cost impact of £30,000.
Computer-based analysis software can generate graphs
that show the following:
* probabilities of project completion at various costs, for example, 90% certainty of completion for less than £xxx
* distribution of out-turn cost outcomes, for example most likely cost outcome and
* identification of the risks that have the most impact on the project outcome.
* other statistical information
Note that Predict! RA or @Risk may also be used to prepare cost plans; these build in the estimated uncertainties for quantities and rates
The results of the QRA will only be as good as the information on which it is based. Since most uncertainty
estimates will be subjective, the accuracy of the results will only be approximate.
You have mentioned that you used a Defined Provisional Sum for the Laboratory Benching at UoL Adrian Decant Refurbishment. What do you mean by the Term Defined Provisional Sum? How were the Works defined? What are the Risk associated with a Defined Provisional Sum? What other type of Provisional Sums exist? What is the difference?
Defined Prov Sum - the full spec of the
benching had not been designed by the but the quantity was known so a reasonable sum could be included to allow for this.
This had been noted as a risk however as the benching had not been designed or ordered which posed risk to procurement/construction time
Also the spec could end up more expensive than allowed for in the contract sum.
There are also undefined provisional sum - less information is known so the contractor cannot be expected to make allowance for these in their programming or preliminaries.
You have stated that you chaired a Risk Workshop at Le Gros Clark refurbishment project. What was the purpose of this? What were your anticipated outcomes?
Purpose of a risk workshop was to bring the design team together to gather all members perspective on potential risks to the project. I used this meeting to compile the risk register which was then used to discuss level of risk posed, level of impact, probability of occurring and possible mitigations. The aim was to have a full risk register at the outcome to present to the client which I could then cost and incorporate into my cost plan, which also helps the client have a fuller understanding of how the risk allowance included has been reached as they have been involved in the process.
What is a Monte Carlo analysis?
A mathematical approach to calculating risk-based outcomes and the probability they will occur.
What software is mentioned for Monte Carlo analysis?
@risk online software
What input have you had in a Risk Register?
Allocated costs to risk items on the dental hospital demolition project.
How did you manage the risk register during the UoB NCDH?
Continually reviewed the register monthly as part of the cost reporting process and chaired risk management workshops.
When were risks reviewed in the risk management workshops?
Risks were reviewed for mitigation status and new probability calculations based on progress.
What was a specific risk in the UoB NCDH project?
Risk of asbestos being found in the demolition.
How was the asbestos risk mitigated?
Through consistent reporting and testing throughout the project.