Project Financial Control and Reporting Flashcards

1
Q

Why do you omit prov sums at the start?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Can you tell me how you assessed change on the Innovation Centre project?
valuation rules

A

Under the JCT D&B, these are:
For measurable works – If works are of a similar nature then CSA/ BoQ rates should be used where possible. Where there are no works of similar nature then fair rates should be used.
Where the works are not measurable – Dayworks should be used (I.e. Prime cost, (materials, plant and labour) plus a percentage addition for incidental costs, materials and labour (within Contract Particulars) – should be valued in line with RICS definition of dayworks – 2 options – 20 page document setting out how to value.
Also paid OH&P/ Additional design fees etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Can you talk me through some of the main headings you included in the cost report you produced on the Innovation Centre project?

A
  • Exec Summary – changes/ risks/ rolling FA
  • Key Risks
  • Contract data – i.e. valuation amount
  • Cash flow
  • Rolling Final Account
  • Provisional Sums
  • Instructed variations
  • Anticipated Variations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How did you produce the cashflow on this project?

A

For this project I produced an initial projected cashflow using a standard S curve model based on the contract sum, programme and contractor cash flow. Then each month I modelled the actual spend based on my interim valuations against the anticipated spend to highlight to my client how works were progressing on site, spend to date etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What information do you need to produce a cash flow/ what needs to be considered?

A
  • Programme – start/ end dates – also defects rectification period/ release of retention
  • Contract Sum
  • need to account for holiday periods etc.
  • Risk Register – risks should be included
  • Fee schedules from consultants
  • Any known variations
  • Sectional completion details if relevant – i.e. retention release at different times
  • Provisional Sums
  • Any materials off-site – could increase expenditure
  • Any direct costs, i.e. furniture
  • Prelims – could use prelims book or £/week etc.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How do preliminaries affect a cash flow?

A

You need to consider both fixed and time related preliminaries. For example site set up costs will only be required during the early stages, then preliminaries will mostly be time related, i.e. cost/week, until the site removal costs are incurred at the end of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does EBITDA stand for?

A

Earnings Before - Interest, Taxes, Depreciation, and Amortization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a Prime Cost Sum?

A

A unit rate for materials where quantities are unknown, excluding associated prelims, overhead, and profit

Used for long lead items; for example, a carpet spec may be unknown, so a rate of £25/m2 is used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is loss and expense in project management?

A

Costs incurred that are not claimable elsewhere, such as variations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is not taken on loss and expense?

A

No retention is taken

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How would you calculate loss and expense?

A

Request evidence of direct loss and expense from the contractor as soon as practicable and update monthly when costs are realized. The CA/QS replies within 28 days with the ascertained amount showing the difference.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is value management?

A

The overall process on a project where value is consistently achieved and considered through choices and options.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Can you give an example of value management in practice?

A

Advising the client to include recommended spares on a contract for equipment, saving costs on future variations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is EBITDA?

A

Earnings Before - Interest, Taxes, Depreciation, and Amortization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a Prime Cost Sum?

A

a. This is for supply of materials usually and is a unit rate for that material where the quants are not known yet. They exclude all associated prelims, OH&P
b. They are used for long lead items
c. i.e. if the spec of carpet is unknown so a rate of £25/m2 is used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is loss and expense

A

Costs incurred not claimable anywhere else such as variations. No retention is taken on loss and expense

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How would you calculate loss and expense?

A

Loss and expense is considered a relevant matter in JCT. In previous projects I requested the contractor provide evidence of the direct loss and expense as soon as practicable, and update this information monthly when cost is realised. The CA/QS shall within 28 days reply with ascertained amount showing the difference.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Talk me through how you have delivered Value Management for a client?

A

a. Value management is the overall process on a project where value is consistently achieved and strived for by making and considering choices and options. I have contributed to this on the University of Birmingham NCDH project where there was an option that I explored from a commercial perspective to make up the levels on the site using material that would’ve been considered otherwise hazardous and would’ve been expensive to remove and dispose of.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

How would you create a cashflow forecast?

A
  • I would need to have access to the construction programme and contract sum analysis in order to
    populate the cashflow.
  • The values associated with each element of construction could be forecasted at times to reflect their
    installation within the programme.
  • I would split the works into the different packages as shown on the contract programme and include
    individual s-curves for each package.
  • Obtaining drawdown schedules from specialist subcontractors and professional consultants can also
    assist when populating the cashflow.
  • An alternative approach would be to utilise a previous cashflow from a similar scheme or to use
    cashflow forecasting software although this may not be as accurate.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

If your construction budget was £2.5m and proposed construction
period was 25 weeks, would a forecast cashflow expenditure of £100,000 per week be realistic?

A
  • In reality this would not be very realistic as the cashflow expenditure per week is unlikely to have a flat
    or regular profile.
  • In reality the expenditure is much more likely to have an S-curve profile where at the start of the
    scheme, the expenditure per week will be fairly low as the site setup and enabling works are undertaken.
  • As the scheme progresses, items that are of higher value such as the steel frame and M&E installations
    will be undertaken. The cost expenditure per week at this stage will be much higher than at the start of
    the scheme.
  • As the scheme draws to a close, minor finishing items such as decoration and cleaning packages will be
    undertaken again resulting in a lower expenditure cost per week
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is the benefit of a cashflow forecast?

A
  • A cashflow forecast allows the employer to gain an understanding of the financial requirements over the project duration and setup any funding requirements for the scheme in advance
  • It can also act as a check against valuations and provide an early indication of financial difficulties if the actual expenditure is lagging behind the forecast.
22
Q

What would you include within a Financial report?

A

I would typically look to include:
- Contract sum total
- Value of Instructed variations
- Value of potential future variations
- Ongoing claims
- Provisional sum adjustments
- The anticipated final account total
- The total of certified payments

23
Q

What is the purpose of a financial report?

A
  • To report against budgeted values and act as a working cost check on the project budget
  • To give the client an understanding of any saving or additional monies required
  • To report contract progress compared to pre-contract predictions
24
Q

What are variations?

A
  • Alterations or modifications to the design, quality or quantity of the contract works or to the site access/working conditions
25
Q

Why might variations arise?

A

a) changes to specification
b) discrepancies between contract documents
c) discrepancies with statutory requirements
d) errors and omissions
e) deficiencies in employer’s requirements

26
Q

What form must architect’s instructions take?

A
  • It is best practice under the majority of contracts for instructions to be made in writing
  • The QS is not usually authorised to make additions to the contract sum for instructions that are not in written form
27
Q

What are the protocol for dealing with oral instructions?

A
  • The validity of oral instructions depends on whether the form of contract being used contains
    mechanisms for them to be valid.
  • For example within the JCT Standard Building Contract (SBC):-
    o Where the Contract Administrator issues an instruction otherwise than in writing, it shall be of
    no immediate effect
    o But the Contractor shall confirm in writing receipt of the verbal instruction within 7 days.
    o If the Contract Administrator does not dissent by notice to the Contractor within 7 days from
    receiving the contractors confirmation, it shall take effect as from the expiry of the latter 7 day
    period.
  • In my opinion it is always best practice to follow up verbal instructions with written instructions as
    soon as possible.
28
Q

Can the contractor object to carrying out a variation?

A
  • Some contracts allow the contractor to object to an instruction in special circumstances for example:-
  • In the JCT Standard Building Contract the requirement to comply with a valid instruction is subject to
    certain exceptions, where:-
    o Where the instruction might affect the efficacy of the design of the Contractors Designed
    Portion.
    o Where the instruction might affect the contractor’s compliance with the CDM Regulations.
    o Where the instruction may infringe patent rights.
    o Where the instruction relates to a named specialist, and the contractor is unable to enter into a contract with that firm.
29
Q

What can the architect do if the contractor does not comply with an instruction?

A
  • This depends on the form of contract being used however under JCT suites if the contractor does not follow an instruction, the architect will be required to issue a notice to comply to the contractor
  • If the contractor still fails to comply, the architect can instruct another party to carry out the work and the contractor will be liable for any additional costs incurred
  • In this circumstance it is important to record the costs and obtain a range of quotations
30
Q

What 3 methods are there of obtaining a cost for variations under JCT forms of contract?

A

This depends on the form of contract being used, under JCT SBC, quotations can be made by:-
o Agreement between the employer and contractor.
o A schedule 2 quotation.
o Valuation by the QS under the valuation rules

31
Q

What are the time periods for Schedule 2 quotations under JCT SBC?

A

o The architect should request via issue of an AI.
o The contractor has 7 days to notify that they will not provide one.
o If not, they have 21 days to provide the quotation.
o The architect then has 7 days to confirm in writing the acceptance or rejection.
o The acceptance is called the ‘confirmed acceptance’

32
Q

What costs does the schedule 2 quotation contain?

A
  • Value of the work.
  • Any adjustment of time.
  • Money in lieu of direct loss and expense.
  • The fair and reasonable cost of preparing the quotation
33
Q

What costs is the contractor entitled to if the schedule 2 quotation is rejected?

A

The fair and reasonable cost of preparing the quote, as long as the quote itself was fair and reasonable

34
Q

What are the valuation rules under JCT Forms of Contract?

A

There are three rules for measurable work:-

o If it is of a similar character, quantity and in the same conditions as existing work, then the bill
rates should be used.
o If it is of a similar character, but different quantity or conditions, the bill rates should be used as
a basis but a fair allowance should be made to take account of the difference.
o If it is not of a similar character, fair rates and prices should be used

35
Q

What about non-measurable work?

A

This would typically be valued by the dayworks procedure based on the cost of labour, plant and
materials that have been incurred

36
Q

What is a star rate?

A
  • A rate that is based on the bill rates but includes a fair allowance.
  • To deviate away from the bill rates there must be a reason as to why the star rate is being adopted.
  • This may be because the conditions on site for installation are more complicated that first envisaged
37
Q

What are ‘fair rates and prices’?

A
  • A market rate.
  • A rate based on actual costs.
  • A rate in line with current cost data.
38
Q

What are dayworks?

A

The prime (actual) cost of all the materials, labour and plant used in carrying out the work, along with a percentage additions to each category as set out in the contract

39
Q

What document should the prime cost be calculated in accordance with?

A

This should be calculated in accordance with the ‘Definition of the Prime Cost of daywork carried out under Building Contracts’ published by the RICS

40
Q

What information is necessary to be able to assess dayworks?

A
  • Vouchers showing the amount of time spent on each activity (dayworks sheets).
  • Names of the workmen.
  • Plant and materials used.
  • This information should be given to the architect or authorised person at the end of the week for
    verification.
41
Q

Can the QS alter hours which he considers to be excessive on a
dayworks sheet that is authorised by the architect?

A

No the hours recorded and signed off should be maintained within the variation

42
Q

What would you do if the contractor submitted 10 dayworks sheets to
you for payment?

A
  • I would verify with the architect that a relevant variation has occurred and is recorded on an Architects
    Instruction.
  • I would check to ensure there is no other contractual method of valuing the variation.
  • Providing the Architects Instruction is in place and no other mechanism for valuation is available I would seek verification of the hours and materials
43
Q

If you and the contractor’s QS could not agree on something how would you resolve it?

A
  • I would discuss with the partner and client to try and seek a resolution with the contractor.
  • The contractor could take the dispute to adjudication if necessary but all parties should try and resolve the matter by negotiation in the first instance.
44
Q

What is quantum meruit?

A

This translates to ‘what he deserves’ for example fair and reasonable costs that have been incurred.

45
Q

Give an example of where quantum meruit might be used

A

If the employer and contractor reach a separate agreement on acceleration, the costs of this may be based on a ‘fair and reasonable’ basis.

46
Q

What is loss and or expense under JCT Forms of Contract?

A

L&E reimburses the contractor for direct loss and/or expense incurred in carrying out additional work or from an employer’s breach of contract

47
Q

What are the procedures for claiming loss and expense under JCT Forms of Contract?

A
  • As soon as the regular progress of the work is affected, or is likely to be affected, or the contractor becomes aware of any other matter that would cause them to incur loss and expense, they should notify the architect in writing.
  • The contractor should submit any further information as requested by the architect.
  • The contractor should also submit any further information as requested by the Architect or QS to enable the amount of loss and expense to be ascertained.
48
Q

What are Relevant Matters under JCT Forms of Contract?

A

Events listed in the Contract that entitle the contractor to loss and/or expense

49
Q

What are the relevant matters?

A

There are 5 relevant matters:-
o Variations.
o Instructions.
o Execution of an approximate quantity that was not a reasonably accurate forecast of quantity.
o Suspension by the contractor for non-payment.
o Any impediment, prevention or default by the employer.

50
Q

What is the key thing to remember when assessing loss and expense claims?

A

It should be the actual loss incurred by the contractor

51
Q

What are the common heads of claim in loss and expense
applications?

A
  • Prolongation.
  • Thickening of preliminaries for example extra supervision required due to variations.
  • Disruption causing plant or labour to be underemployed.
  • Increases in labour or material costs during the period of delay.
  • Head office overheads.
  • Loss of profit.
  • Finance charges.
  • Acceleration costs.
  • Claim preparation costs.