Case study Flashcards

1
Q

Did you include any risk allowances within your pre-tender estimate for either of these issues faced?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How would you generate a risk allowance?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Did you advise to your client to include an undefined provisional sum instead of a defined provisional sum?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the difference between a defined and an undefined provisional sum? And why?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How did you generate the allowance of £10k for the provisional sum?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How did you assess the costs for the fencing given that it’s quite a bespoke piece of work?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

You say that the value engineering option proposed was to use smaller plant for the demolitions works, did this have a programme impact?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What was your role as cost manager during the value engineering exercise?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the relevant events under the contract? Give me 3 examples

A

There are 14 Relevant Events under the 2016 D&B Contract (cl. 2.26):
Changes. Employer’s Instructions. Delay of giving of possession of the site. Antiquities. Suspension by the contractor for non-payment. Impediment, default, or prevention by the Employer/ Employer’s Persons. Statutory Undertakers work. Exceptionally adverse weather. Specified Perils. Civil commotion/ threat or use of terrorism. Strike or lockout. UK Government/Public Authority affecting the works/ Delay to approval by a statutory body. Force Majeure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

With your preferred option of acceleration, what was the cost of this?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Did you advise the client that they would be entitled to claim Liquidated Damages if the contractor didn’t achieve the PC date?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. What were the LAD’s vs the cost of acceleration to the client and was this explored as part of your recommendation?
    i.e. offsetting the cost of acceleration vs contractor’s liability for damages?
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly