Reverse Formulas and Calculations Flashcards

1
Q

Cost of Project or Investment / Annual Cash Inflows

A

Project Payback Period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Predicts likelihood of reaching EAC

Formula: (BAC-EV)/(EAC-AC)

Greater than 1 – harder to complete and meet EAC
Less than 1 – easier to complete and meet EAC

A

TCPI (Utilizing EAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Predicts likelihood of reaching BAC

Formula: (BAC-EV)/(BAC-AC)

Greater than 1 – harder to complete and meet BAC
Less than 1 – easier to complete and meet BAC

A

TCPI (Utilizing BAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Predict how much more the remainder of the project will cost

Formula: EAC-AC

A

Estimate to Complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Project of being over or under budget based on current performance

Formula: BAC-EAC

(Positive = under budget, Negative = over budget)

A

Variance at Completion (VAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Shows overall schedule adherence

Formula: EV/PV

(Greater than 1 = ahead of schedule, Less than 1 = behind schedule)

A

Schedule Performance Index (SPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

N(N-1)/2 N=Number of Stakeholders

A

Communication Channel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What the project should be worth

A

Planned Value (PV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The difference between the earned value (EV) and planned value (PV)

Formula: EV-PV

(Positive = ahead of schedule, Negative = behind schedule)

A

Schedule Variance (SV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What the project is worth

Formula: % Complete x BAC

A

Earned Value (EV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Forecasts final project costs based on current performance

Standard Formula: BAC/CPI

Future Work at Planned Cost Formula: AC + BAC - EV

Initial Costs Estimate Flawed: AC + Estimate for remainer of project

CPI and SPI affect reamainder of project formula: AC + [BAC-EV/CPIxSPI)]

A

Estimate at Completion (EAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What the project budget is

A

Budget at Completion (BAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The different between the earned value (EV) and the actual value (AV) cost

Formula: EV-AC

(Positive = under budget, Negative = over budget)

A

Cost Variance (CV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What the project has spent so far

A

Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Shows overall cost efficiency on the project

Formula: EV/AC

(Greater than 1 = under budget, Less than 1 = over budget)

A

Cost Performance Index (CPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly