7 - Project Cost Management Flashcards

1
Q

The actual amount of monies the project has spent to date.

A

Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

An approach that relies on historical information to predict the cost of the current project. It is also known as top-down estimating and is the least reliable of all the cost-estimating approaches.

A

Analogous Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

An estimating approach that starts from zero, accounts for each component of the WBS, and arrives at a sum for the project. It is completed with the project team and can be one of the most time-consuming and most reliable methods to predict project costs.

A

Bottom-Up Estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

This estimate is also somewhat broad and is used early in the planning processes and also in top-down estimates. The range of variance for the estimate can be from –10 percent to +25 percent.

A

Budget Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A cost-estimating approach that uses a database, typically software-driven, to create the cost estimate for a project.

A

Commercial Database

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

An allowance to account for overruns in costs. Used at the project manager’s discretion and with management’s approval to counteract cost overruns for scheduled activities and risk events.

A

Contingency Reserve

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Costs are parallel to each WBS work package. The costs of each work package are summed up to their corresponding control accounts. Each control account then is summed to the project costs.

A

Cost Aggregation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The approved version of the time-phased project budget, excluding any management reserves, which can be changed only through formal change control procedures and is used as a basis for comparison to actual results.

A

Cost Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The cost aggregation achieved by assigning specific dollar amounts for each of the scheduled activities or, more likely, for each of the work packages in the WBS.

A

Cost Budgeting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A component of a project or program management plan that describes how costs will be planned, structured, and controlled.

A

Cost Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The monies spent to recover from not adhering to the expected level of quality. Examples may include rework, defect repair, loss of life or limb because safety precautions were not taken, loss of sales, and loss of customers. This is also known as the cost of nonconformance to quality.

A

Cost of Poor Quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

All costs incurred over the life of the product by investment in preventing nonconformance to requirements, appraisal of the product or service for conformance to requirements, and failure to meet requirements.

A

Cost of Quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

MA measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.

The formula is EV/AC

A

Cost Performance Index (CPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost.

The formula is EV – AC.

A

Cost Variance (CV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

This estimate type is one of the most accurate. It’s used late in the planning processes and is associated with bottom-up estimating. You need the WBS in order to create the definitive estimate. The range of variance for the estimate can be from –5 percent to +10 percent.

A

Definitive Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Costs are attributed directly to the project work and cannot be shared among projects (for example, airfare, hotels, long-distance phone charges, and so on).

A

Direct Costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

The measure of work performed expressed in terms of the budget authorized for that work

A

Earned Value (EV)

18
Q

The expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.

A

Estimate At Completion (EAC)

19
Q

The expected cost to finish all the remaining project work.

A

Estimate To Complete (ETC)

20
Q

Costs that remain constant throughout the life of the project (the cost of a piece of rented equipment for the project, the cost of a consultant brought on to the project, and so on).

A

Fixed Costs

21
Q

The process of comparing the planned expenditure of project funds against any limits on the commitment of funds for the project to identify any variances between the funding limits and the planned expenditures.

A

Funding Limit Reconciliation

22
Q

Costs that are representative of more than one project (for example, utilities for the performing organization, access to a training room, project management software license, and so on).

A

Indirect Costs

23
Q

An event that will likely happen within the project, but when it will happen and to what degree is unknown. These events, such as delays, are usually risk-related.

A

Known Unknown

24
Q

An approach that assumes the cost per unit decreases the more units workers complete, because workers learn as they complete the required work.

A

Learning Curve

25
Q

A market condition where the market is so tight that the actions of one vendor affect the actions of all the others.

A

Oligopoly

26
Q

The loss of potential gain from other alternatives when one alternative is chosen.

Or

The loss of potential future return from the second-best unselected project.

A

Opportunity Cost

27
Q

An estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters.

A

Parametric Estimating

28
Q

The authorized budget assigned to scheduled work. It is the monetary representation of where the project should be at this point in time.

A

Planned Value (PV)

29
Q

The final variance, which is discovered only at the project’s completion.

A

Project Variance

30
Q

This is a statistical approach to predicting what future values may be, based on historical values. This creates quantitative predictions based on variables within one value to predict variables in another. This form of estimating relies solely on pure statistical math to reveal relationships between variables and to predict future values.

A

Regression Analysis

31
Q

An analytical technique to determine the essential features and relationships of components in the project management plan to establish a reserve for the schedule duration, budget, estimated cost, or funds for a project.

A

Reserve Analysis

32
Q

This rough estimate is used during the initiating processes and in top-down estimates. The range of variance for the estimate can be from –25 percent to +75 percent.

A

Order of Magnitude

33
Q

A measure of schedule efficiency expressed as the ratio of earned value to planned value.

The formula is EV/PV.

A

Schedule Performance Index (SPI)

34
Q

A measure of schedule performance expressed as the difference between the earned value and the planned value.

The formulas is EV – PV.

A

Schedule Variance (SV)

35
Q

Many vendors can provide what your project needs to purchase, but you prefer to work with a specific vendor.

A

Single Source

36
Q

Only one vendor can provide what your project needs to purchase. Examples include a specific consultant, specialized service, or unique type of material.

A

Sole Source

37
Q

Money that has already been invested in a project.

A

Sunk Costs

38
Q

A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget.

If you want to see if your project can meet the budget at completion, you’ll use this formula: TCPI = (BAC – EV)/(BAC – AC).

If you want to see if your project can meet the newly created estimate at completion, you’ll use this version of the formula: TCPI = (BAC – EV)/(EAC – AC).

A

To-Complete Performance Index

39
Q

Costs that change based on the conditions applied in the project (the number of meeting participants, the supply of and demand for materials, and so on).

A

Variable Costs

40
Q

The difference between what was expected and what was experienced.

A

Variance

41
Q

A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion.

The formula is BAC – EAC.

A

Variance at Completion (VAC)