Quiz #7 Flashcards
- The business is unclear on the direction and when features are to be expected for an
agile managed project. What project artifact helps communicate the goals, milestones, and
potential deliverables, releases, or other work outputs?
□ Product roadmap
□ Project charter
□ Requirements documentation
□ Configuration management plan
✓ Product roadmap
References: Agile practice guide, 5.2.2 - Backlog preparation
PMP Exam Prep, Lesson 3 - Topic B, Product roadmaps
- What does configuration management address?
□ Activities such as keeping track of all the changes the customer makes to the product
plans.
□ The way in which the product is configured for use to satisfy the end users and how that
develops as it is being built.
□ Documentation of the management of configuring the product for use and how changes
to the product will be incorporated into the overall project plan.
□ Activities such as how version control of project documents and changes to the product will
be initiated, analyzed, and traced.
✓ Activities such as how version control of project documents and changes to the product will
be initiated, analyzed, and traced.
References: PMBOK 6th edition, 4.2 .. Project management plan
PMP Exam Prep, Lesson 3 - Topic E, Configuration management
- Which of the following is concerned with revisions to project documents?
□ Version control
□ Configuration management
□ Both version control and configuration management
□ Document control
✓ Both version control and configuration management
References: PMBOK 6th edition, 4.6. Perform integrated change control
PMP Exam Prep, Lesson 3 - Topic E, Configuration management
- Your project team holds weekly status meetings. Should the notes from last week’s
meeting be considered a project artifact?
□ This decision is up to the project manager.
□ Yes, if significant project issues were discussed.
□ Yes, even if the meeting resulted in only routine topics.
□ No, meeting notes are not artifacts.
✓ Yes, if significant project issues were discussed.
References: PMBOK 6th edition, 4.6. Perform integrated change control
PMP Exam Prep, Lesson 3 - Topic E, Configuration management
- How do you describe an effective change control system?
□ An effective change control system includes the forms, tracking methods, processes, and
approval levels required for authorizing or rejecting requested changes.
□ An effective change control system includes the documented procedures for
authorizing or rejecting.
□ Requested changes in a project.
□ An effective change control system specifies how the project scope will be controlled,
changed, and approved.
□ An effective change control system integrates all of the changes for a project.
✓ An effective change control system includes the forms, tracking methods, processes, and
approval levels required for authorizing or rejecting requested changes.
References: PMBOK 6th edition, 4.6. Perform integrated change control
PMP Exam Prep, Lesson 3 - Topic E, Configuration management
- The project manager is working with the team as they perform the work to create the
project deliverables. Some adjustments need to be made to the project plan and the
baselines. What would be needed in order for the project manager to allow such changes?
□ Change requests.
□ Input from stakeholders that their needs have adjusted from what was originally
planned.
□ Approved change requests.
□ The sponsor decides on a different way to accomplish the work.
✓ Approved change requests.
References: PMBOK 6th edition, 4.6. Perform integrated change control
PMP Exam Prep, Lesson 3 - Topic E, Configuration management
7. What are some of the reasons for performance variations in a project? (Choose four.) □ Specification changes □ New regulations □ Missed requirements □ New changes to the project plan □ Inaccurate initial estimates
✓ Specification changes
✓ New regulations
✓ Missed requirements
✓ Inaccurate initial estimates
References: PMBOK 6th edition, 4.5. Monitor and control project work
PMP Exam Prep, Lesson 3 - Topic F, Causes of project changes
- A problem occurs during the project execution. It is not a big problem, but it does bother
some of the stakeholders. The project manager requests that it be added to the issue log.
What would be the reason for this?
□ The issue log serves as a place to document problems that occur and to track their
resolution.
□ The issue log will be reviewed by the risk team at its next meeting to develop a
contingency plan.
□ The issue log will be submitted to the change control board for a change approval.
□ The issue log serves as a place to document the unidentified risks.
✓ The issue log serves as a place to document problems that occur and to track their
resolution.
References: PMBOK 6th edition, 4.3. Direct and manage project
PMP Exam Prep, Lesson 3 - Topic G, Issue log
- Which one of the following statements about issues is correct?
□ Stakeholders use the issue log to manage an issue.
□ An issue should be assigned to only one person.
□ There must be no open issues when the project is closed.
□ Only issues that are behind schedule need to be discussed during project status
meetings.
✓ An issue should be assigned to only one person.
References: PMBOK 6th edition, 4.3. Direct and manage project
PMP Exam Prep, Lesson 3 - Topic G, Issue log
- How does a risk become an issue?
□ The project manager judges the risk to be significant enough that it is stipulated to be an
issue.
□ The risk has a high probability of happening in the immediate future.
□ The risk has happened
□ The risk owner escalates the risk to an issue.
✓ The risk has happened
References: PM BOK 6th edition, 11. 7 Monitor risks
PMP Exam Prep, Lesson 3 - Topic G, Risks and issues
- What is true of lessons learned during the project?
□ Should be documented only in the closeout report.
□ Should consist of only project data.
□ Should be documented throughout the project.
□ Should consist of only things that went well during project execution.
✓ Should be documented throughout the project.
References: PMBOK 6th edition, 4.4. Manage project knowledge
PMP Exam Prep, Lesson 3 - Topic H, Lessons learned
12. A team member asks you where she can find a set of building codes. Which type of knowledge is this? □ Implicit □ Explicit □ Tacit □ General
✓ Explicit
References: PMBOK 6th edition, 4.4. Manage project knowledge
PMP Exam Prep, Lesson 3 - Topic H, Lessons learned
- What is the difference between a lessons-learned register and a lessons-learned
repository?
0 The two terms mean the same thing.
0 The register applies to a single project, and the repository applies to many projects.
0 The repository applies to a single project, and the register applies to many projects.
0 The register contains only areas that need improvement in future projects, and the
repository contains areas of improvement as well as positive findings.
✓ The register applies to a single project, and the repository applies to many projects.
References: PMB0K 6th edition, 4.4. Manage project knowledge
PMP Exam Prep, Lesson 3 - Topic H, Lessons learned
Scenario:
For questions 14, 15, 16 and 17: The 234 West Adams project has a tight schedule, as well as a
strict budget. You are concerned that any possible changes could negatively affect project
performance baselines. You need to ensure that there is a standardized method for handling
changes. Your development company has included a Change Control Board (CCB) in the
process.
14. Who will you involve in the change control process for the new-build project?
□ The project manager is only involved to avoid delays and additional costs.
□ Key stakeholders, including the development company senior executive, the strategic planning
□ The project team members, they have the expertise to evaluate the change requests.
□ The Sponsor and customers, since they are those that have defined project requirements.
✓ Key stakeholders, including the development company senior executive, the strategic planning
individuals and the PMO.
References: PMB0K 6th edition, 4.6. Perform integrated change control
PMP Exam Prep, Lesson 3 - Topic F, Manage project changes
- The carpenter informs you that the windows and door installation will have a significant
delay and is asking for a change in subsequent schedule dates. What action should you take
first?
□ Coordinate changes across knowledge areas.
□ Document the change request in a change control system.
□ Update the project plan to reflect changes.
□ Bring the information to the stakeholders for evaluation and approval.
✓ Document the change request in a change control system.
References: PMB0K 6th edition, 4.6. Perform integrated change control
PMP Exam Prep, Lesson 3 - Topic F, Manage project changes