Quiz #2 Flashcards
Which of the following should be included in a project charter? (Choose two)
Measurable objectives
Detailed deliverables list
Key stakeholders list
Change request form
Measurable objectives
Key stakeholders list
References: PMBOK 6th Edition, 4.1- Develop Project Charter
PMP Exam Prep, Lesson 1- Topic G - Project
What are the rules for the duration of a clang stand-up meeting?
Less than 10 minutes
More than 15 minutes
10 -15 minutes
Weekly frequency
10 -15 minutes
References: Agile Practice Guide, Annex A3_3.2 Scrum PMP Exam Prep, Lesson 1- Topic G - Agile Ceremonies
Which of the following is not a technique for estimation?
Planning Poker
T-Shirt Sizing
Product Box
Story Pointing
Product Box
Reference: PMP Exam Prep, Lesson 1- Topic G - Estimation Techniques
Which of the following do not relate to Product Box?
Describe aspects of a solution
Tool to help estimation of efforts
Close to a marketer describing product features
Collaboration game
Tool to help estimation of efforts
Reference: PMP Exam Prep, Lesson 1- Topic G - Product Box
Which of the following are delivery models for training? (Choose two)
Virtual classroom
Self-paced e-learning
Prior knowledge
Testing and validation
Virtual classroom
Self-paced e-learning
References: PMBOK 6th Edition, 9.4 - Develop Team
PMP Exam Prep 1st edition, Lesson 1- Topic E
Kanban-style Boards include:
Definition of roles and responsibilities
Status of work to do, completed and in progress
Detailed Gantt chart
Overall progress performance reports
Status of work to do, completed and in progress
References: Agile Practice Guide, 5.4 - Measurements in Agile Projects
PMP Exam Prep, Lesson 1- Topic D - Guidelines to Evaluate Task Accountability
Use a training calendar to? (Choose two)
Publish schedule to customer stakeholders
Create a mechanism for registration and sending confirmation
Build training material
Evaluate trainer
Publish schedule to customer stakeholders
Create a mechanism for registration and sending confirmation
References: PMBOK 6th Edition, 9.4 - Develop Team
PMP Exam Prep, Lesson 1- Topic E - Training Cost and Schedule
Baselining is a technique for measuring the of training.
Efficacy
Content
Exhaustiveness
Duration
Efficacy
References: PMBOK 6th Edition, 9.4 - Develop Team
PMP Exam Prep, Lesson 1- Topic E - Baseline and Post-training Assessments
Which of the following is a good practice for the use of collaboration tools?
Select tools with the best features.
Select tools that the team lead has experience using.
Focus on collaboration and team norms before focusing on tools.
Use the tools that the previous project used.
Focus on collaboration and team norms before focusing on tools.
References: PMBOK 6th Edition, 9.4 - Develop Team
PMP Exam Prep, Lesson 1- Topic F - Implement Options for Virtual Team Member Engagement
Which of the following are examples of virtual team collaboration tools? (Choose two)
Shared task boards
Your laptop hard drive
Social media
Team chat boards
Shared task boards
Team chat boards
References: PMBOK 6th Edition, 9.4 - Develop Team
PMP Exam Prep, Lesson 1- Topic F - Collaboration Technology
Which of the following should be included in a Communications Plan? (Choose two)
How and when team meetings are run
Equipment assigned to each team member
Project Charter
Preferred communications approaches with external stakeholders
How and when team meetings are run
Preferred communications approaches with external stakeholders
References: PMBOK 6th Edition, 10.1 - Plan Communications Management PMP Exam Prep 1st edition, Lesson 1- Topic F - Communication Plan
Basic needs of a virtual team (Choose two)
Clear and shared goal
Good communication plan
Good definition of roles and responsibilities
Good team charter
Clear and shared goal
Good definition of roles and responsibilities
References: PMBOK 6th Edition, 9.4 - Develop Team
PMP Exam Prep 1st edition, Lesson 1- Topic F - Virtual Team Member Needs
Which one is not an objective of the kickoff meeting?
Establish project context
Develop a communication plan
Assist in team formation
Ensure proper alignment to project vision
Develop a communication plan
References: PMBOK 6th Edition, 4.2 - Develop Project Management Plan PMP Exam Prep, Lesson 1- Topic G - Kickoff Meeting
All the following are objectives of the Sprint planning EXCEPT:
Review the highest prioritized user stories
Ask questions
Do a retrospective
Agree on forecasts for story completion
Do a retrospective
Reference PMP Exam Prep, Lesson 1- Topic G - Iteration Planning
The establish team velocity is 8 story points. A Product Backlog has items prioritized by business value with the following estimated story points: Story 1= 3 Story Points, Story 2 = 4 Story Points, Story 3 = 2 Story Points and Story 4 =1 Story Points. The team is now meeting during a Sprint Planning session and needs to commit to stories for the next spring. Which of the following stories should the team commit to?
Stories 1, 2 & 3
Stories 1, 2 & 4
Stories 1 & 2
Stories 2, 3 & 4
Stories 1, 2 & 4
References: Agile Practice Guide, 5.4.1 - Agile teams Measure Results PMP Exam Prep, Lesson 1- Topic G - Task Boards