What are some techniques that a project manager can use to appraise the skills of a potential team member? (Choose two)
Ability tests
Focus groups
Kanban boards
RACI matrix
References: PMBOK 6th Edition, 9.4 - Develop Team
PMP Exam Prep, Lesson 1- Topic A - Pre-assignment Tool
Ability tests
Focus groups
What does it mean if you are identified as an R in a RACI chart?
You are accountable for the result
You should be engaged to provide needed inputs
You should be kept up to date on the status
You are responsible for the activity’s execution
You are responsible for the activity’s execution
References: PMBOK 6th Edition, 9.1- Plan Resource Management PMP Exam Prep, Lesson 1- Topic A - The RACI Chart
Which of the following are components of a Resource Calendar? (Choose two) Working days Training Strategies Availability of physical resource Recognition Plans
Working days
Availability of physical resource
References: PMBOK 6th Edition, 9.2 - Estimate Activity Resources
PMP Exam Prep, Lesson 1- Topic C - Resource Calendars
Which of the following are part of an effective team charter? (Choose two) Shared values Project objectives Resource assignments Conflict resolution
Shared values
Conflict resolution
References: PMBOK 6th Edition, 9.4 - Develop Team
PMP Exam Prep, Lesson 1- Topic B - Team Charter
In which of the following situations would brainstorming be an appropriate technique? Conflict resolution Sprint reviews and demos Identifying and prioritizing options Running a stand-up meeting
Identifying and prioritizing options
References: PMBOK 6th Edition, 5.1- Plan Scope Management PMP Exam Prep, Lesson 1- Topic B - Brainstorming
Which of the following are components of a project agreement? (Choose two) Pricing and payment terms Incentives and penalties Team members Complete product backlog
Pricing and payment terms
Incentives and penalties
References: PMBOK 6th Edition, 12.2 - Conduct Procurements
PMP Exam Prep, Lesson 1- Topic C - Negotiations
Work performance data is integrated and contextualized to do what? Plan communication Raise issues Build a team charter Identify stakeholders
Raise issues
References: PMBOK 6th Edition, 43 - Direct and Manage Project Work PMP Exam Prep, Lesson 1- Topic C - Performance Report
Which of the following are methods to prioritize project objectives and deliverables? (Choose two) Paired Comparisons Planning Poker First In, First Out MSCW (Moscow) Analysis
Paired Comparisons
MSCW (Moscow) Analysis
References: Agile Practice Guide, 52 - Common Agile Practices Product Backlog PMP Exam Prep, Lesson 1- Topic C - Prioritization Techniques
Which of the following are types of project metrics that may be appropriate for a given project? (Choose two.) Percentage of work completed Defects Subcontractor approvals Process compliance
Percentage of work completed
Defects
References: PMBOK 6th Edition, 8. - Project Quality Management
PMP Exam Prep, Lesson 1- Topic C - Performance Report
10. Which of the following is commonly associated to approaches that store or lock away information? Information radiator Information refrigerator Information compliance Information tooling
Information refrigerator
References: Agile Practice Guide, A3.4 - Kanban Method
PMP Exam Prep, Lesson 1- Topic A - Guidelines to Knowledge Transfer
- Which of the following is the best approach to estimating effort?
The project manager estimates all of the work
A team lead estimates all of the work
The work is estimated by the people who will be asked to do it
The estimates are inflated to avoid second guessing from the customer
The work is estimated by the people who will be asked to do it
References: PMBOK 6th Edition, 6.4 - Estimate Activity Duration PMP Exam Prep, Lesson 1- Topic D - Estimates
- What is self-organization? (Choose two.)
Asking teams to assess and agree to work goals as a group
Allocating all resources before they get assigned to a different project
Using a pull-based approach to ensure effective use of team resources
Having the project manager stipulate roles and responsibilities and assign all the work to individual team members
Asking teams to assess and agree to work goals as a group
Using a pull-based approach to ensure effective use of team resources
References: Agile Practice Guide, 43 - Agile Teams
PMP Exam Prep, Lesson 1- Topic A - Project Responsibilities within the Team
- What are some objectives of running a Retrospective? (Choose two)
Provide the stakeholders access to the team.
Generate insights.
Agree to 1-2 experiments to try to improve team performance.
Get feedback on the product.
Generate insights.
Agree to 1-2 experiments to try to improve team performance.
References: Agile Practice Guide, 52 - Common Agile Practices PMP Exam Prep, Lesson 1- Topic D - Retrospective
- When forming teams, it’s critical to understand the and
needed to perform project work and produce deliverables
Roles, responsibilities
Skills, competencies
Level of influence, impact
Risk, quality
Skills, competencies
References PMBOK 6th Edition, 9.1- Plan Resources management PMP Exam Prep, Lesson 1- Topic D - Team Strengths
- When is the ideal time to hold a retrospective?
Right after iteration planning
Just before iteration planning
At the start of the next release
During the iteration review/demo
Just before iteration planning
References: Agile Practice Guide, 52 - Common Agile Practices PMP Exam Prep, Lesson 1- Topic C - Lessons Learned