Earned Value Flashcards

1
Q

Authorized budget assigned to scheduled work

A

Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Measure of work performed expressed in terms of the budget authorized for that work.

A

Earned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How is earned value calculated ?

A

EV = % completed x Planned Value (PV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Realized cost incurred for the work performed on an activity during a specific time period.

A

Actual Cost (AC) : money that has been spent for work that has been completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Measure of schedule performance expressed as the difference between the earned value and the planned value.

A

Schedule Variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is schedule variance calculated

A

SV = EV - PV

Schedule variance = earned value - planned value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Measure of schedule efficiency expressed as the ratio of earned value to planned value.

A

Schedule performance index (SPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How is the schedule performance index calculated?

A

SPI = EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does an SPI above 1 mean?

A

Project is on schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Amount of budget deficit or surplus at a given point in time, expressed as the difference between the earned value and the actual cost.

A

Cost variance (CV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How is the cost variance calculated?

A

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does a CV of zero mean?

A

Project is on budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does a positive CV mean?

A

Project is performing under budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does a negative CV mean?

A

Project is performing over budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.

A

Cost Performance Index (CPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How is the cost performance index calculated?

A

CPI = EV / AC

17
Q

What does a CPI greater than 1.0 indicate?

A

Project is under budget.

18
Q

What does a CPI of 1.0 mean?

A

Project is on budget

19
Q

What does a CPI of less than 1.0 indicate?

A

Project is over budget.

20
Q

Current projected final cost of the project.

A

Estimate at Completion

21
Q

How is the estimate at completion calculated?

A

EAC = BAC/CPI

22
Q

The sum of all budgets established for the work to be performed.

A

Budget at Completion (BAC)

23
Q

The amount of additional money you will need to complete the project.

A

Estimate to complete (ETC)

24
Q

How is the estimate to complete calculated?

A

ETC = EAC - AC