Quiz 14 PMI Code Of Ethics Flashcards
PMI has contacted you regarding an ethics violation of a CAPM candidate. The question is in regard to a friend who said he worked as project manager under your guidance. You know this is not true, but to save a friendship, you avoid talking with PMI. This is a violation of which of the following?
The PMI code to cooperate on ethics violation investigation
The PMI code to report accurate information
The PMI code to report any CAPM violations
The law concerning ethical practices
The PMI code to cooperate on ethics violation investigation. By avoiding the conversation with PMI in regard to the ethics violation of a friend, you are, yourself, violating the PMI Code of Ethics and Professional Conduct The situation requires you, a CAPM, to work with PMI on their investigations. You’re not reporting accurate information on a CAPM violation, so the PMI code to report any CAPM violations is not appropriate for the question. In this instance, PMI isn’t asking you about laws, but about a CAPM candidate who happens to be your friend.
You are the project manager for the Log Cabin Project. One of your vendors is completing a large portion of the project. You have heard a rumor that the vendor is losing many of its workers because of labor issues. In light of this information, what should you do?
Stop work with the vendor until the labor issue is resolved
Communicate with vendors in regards to the rumor
Look to secure another vendor to replace the current vendor
Negotiate with the labor union to secure the workers on the project
The project manager should confront the problem by talking with the vendor about the rumor. A is incorrect and would delay the project and possibly cause future problems. C is incorrect and may violate the contract between the buyer and the seller. D is also incorrect the agreement is between the vendor and the performing organization, not the labor union.
You are the project manager for the PMH Project. Three vendors have submitted cost estimates for the project. One of the estimates is significantly higher than similar project work in the past. In this scenario, you should do which of the following?
Ask the other vendor about the highest estimate from third vendor
Use the cost estimate from historical information
Take the high cost to the vendor to discuss the discrepancy before reviewing the issue with the other vendor
Ask the vendor that supplied the high estimate for information on how the estimate was prepared
Ask the vendor that supplied the high estimate for information on how the estimate was prepared. Most likely, the vendor did not understand the project work to be procured, so the estimate is skewed. A clear statement of work is needed for the vendors to provide accurate estimates. A, B, and C are all inappropriate actions because they discuss another vendor’s estimate. This information should be kept confidential between the buyer and the seller. In some government projects, release of the winning bid information may be required.
You are the project manager of the LKH Project. This project must be completed within six months, but after two months, the schedule has begun to slip. As of now, the project is one week behind schedule. Based on your findings, you believe you can make some corrective actions and recover the lost time over the next month to get the project back on schedule for its completion date. Management, however, requires weekly status reports on cost and schedule. Which of the following should you do?
Report that the project is one week behind schedule but will finish on schedule based on cited corrective action
Report that the project is on schedule and will finish on time
Report that the project is off schedule but will finish on time
Report that the project is running late
Report that the project is one week behind schedule but will finish on schedule based on cited corrective action. The project manager should report an honest assessment of the project with actions on how he plans to correct the problem. B and C is incorrect because it does not provide an honest answer to management. D is incorrect because it does not provide a solution to the problem.
As a contracted project manager, you have been assigned a project with a budget of U.S. $1.5 million. The project is scheduled to last seven months, but your most recent EVM report shows that the project will finish ahead of schedule by nearly six weeks. If this happens, you will lose $175,000 in billable time. What should you do?
Bill the entire $1.5 million since this was the approved budget
Bill the entire $1.5 million by adding more work at end of the project
Report to the customer the project status and completion date
Report to the customer the project status and completion date and ask if they would like to add any features to account for the money not spent
Report to the customer the project status and completion date. An honest and accurate assessment of the project work is always required. A and B are incorrect because these actions do not reflect an honest assessment of the work. D is incorrect because it offers gold plating and recommends additional changes that were not part of the original project scope. In addition, because this is a contracted relationship, the additional work may not be covered within the original project contract and may result in legal issues.
You are the project manager of the PMH Project. You have been contracted to design the placement of several pieces of manufacturing equipment. You have completed the project scope and are ready to pass the work over to the installer. The installer begins to schedule you to help with the installation of the manufacturing equipment. Which of the following should you do?
Help the installer place the equipment according to the design document
Help the installer place the equipment as the customer sees fit
Refuse to help the installer since the project scope has been complete
Help the installer place the equipment but insist that the quality control be governed by your design specifications
When the project scope is completed, the contract is fulfilled and the project is done. Any new work items should be sent through the proper channels within an organization to create a new project or work order. In this instance, the contract change control system should be used or a new contract should be created. A, B, and D are incorrect since this choice is outside of the scope and have not been covered in the contract.
You are the project manager of the 12BA Project. You have completed the project according to the design documents and have met the project scope. The customer agrees that the design document requirements have been met; however, the customer is not pleased with the project deliverables and is demanding additional adjustments be made to complete the project. What is the best way to continue?
Complete the work as customer requested
Complete the work at 1.5 billable rate
Do nothing the project scope is completed
Do nothing management from the performing organization and the customers organization will need to determine why the project failed before adding work
Do nothing the project scope is completed. When the project scope has been completed, the project is completed. Any additional work, without a contract change or new contract, would be dishonest and would betray the customer or the project manager’s company. A and B incorrect since additional work is not covered in the current contract. D is incorrect because the project did not fail the deliverables met the requirements of the project scope and the design document
You are the project manager of the AAA Project. Due to the nature of the project, much of the work will require overtime between Christmas and New Year’s Day. Many of the project team members, however, have requested vacation during that week. What is the best way to continue?
Refuse all vacation requests and require all team members to work
Allow vacation request only for those team members who are not needed during that week
Divide tasks equally among the team members so each works the same amount of time
Allow team members to volunteer for overtime work
A, B, and C are autocratic response to the problem, and although the results may seem fair, this isn’t the best choice. D is the best choice for this scenario because it allows the project team to be self-led and is sensitive to the needs of the project team.
You are a project manager for your organization. Your project is to install several devices for one of your company’s clients. The client has requested that you complete a few small tasks that are not in the project scope. To maintain the relationship with the client, you oblige her request and complete the work without informing your company. This is an example of which of the following? Effective expert judgement Violations of ethics Contract change control Integrated change control
B is correct. When the project manager completes activities outside of the contract and does not inform the performing organization, it is essentially the same as stealing. The CAPM must be held accountable for all the time invested in a project. A is incorrect this is not expect judgement. C is incorrect because the contract has not been changed or attempted to be changed. D is incorrect. The changes the project manager completed for the customer were not sent through any change control system, but were completed without documentation or reporting.
You are the project manager of the JKN Project. The project customer has requested that you inflate your cost estimates by 25 percent. He reports that his management always reduces the cost of the estimates, so this is the only way to get the monies needed to complete the project. Which of the following is the best response to this situation?
Do as the customer asked to ensure the project requirements can be met by adding the increase as contingency reserve
Do as the customer asked to ensure the project requirements can be met by adding across each task
Do as the customer asked by creating an estimate for customers management and another for the actual project implementation
Complete an accurate estimate of the project. In addition create risk assessment on why the project budget would be inadequate
A, B, and C are all incorrect because they are ethically wrong. The CAPM should always provide honest estimates of the project work. D is correct. It would be inappropriate to bloat the project costs by 25 percent. A risk assessment describing how the project may fail if the budget is not accurate is most appropriate
You are the project manager for the BNH Project. This project takes place in a country different from yours. The project leader from this country presents a team of workers who are all from his family. You should do which one of the following?
Reject the team leaders recommendation and assemble your own project team
Review the resume and qualifications of the project team leaders before approving team
Determine whether the country tradition includes hiring from the immediate family before hiring from outside the family
Replace the project leader with impartial project leader
C is correct. You should first confirm what the local practices and customs call for in regard to hiring family members before others. A and D are incorrect This choice does not consider the qualifications of the project team leader and the project team. In addition, it does not take into account local customs. B is incorrect as well; although it does ponder the qualifications of the project team leader, it does not consider the local customs. The project team leader’s ability is not called into question; the family members are the issue.
You are about to begin negotiations on a new project that is to take place in another country. Which of the following should be your guide on what business practices are allowed and discouraged?
The project charter
The project plan
Company policies and procedures
PMI code of ethics and professional conduct
C is correct. The company policies and procedures should guide the project manager regarding the decisions he makes in the foreign country. A and B are incorrect. These documents are essential but usually do not reference allowed business practices. D is also incorrect. Although the CAPM Code of Ethics and Professional Conduct harbors crucial information, the company’s policies and procedures are more specific to the project work and requirements.
One of your project team members reports that he sold pieces of equipment because he needed the money to pay for his daughter’s school tuition. He says he has paid back the money by working overtime without reporting the hours worked so that his theft remains private. What should you do?
Fire the project team member
Report the project team member
Suggest the team member report self to HR
Tell the team member you are disappointed and not to do again
B is correct. This situation calls for the project team member to be reported to his manager for disciplinary action. A is inappropriate because the project manager may not have the authority to fire the project team member. C is inappropriate because the project manager must take action to bring the situation to management’s attention. D is inappropriate because no formal discipline actions are taken to address the problem.
You are the project manager of the SUN Project. Your organization is a functional environment, and you do not get along well with the functional manager leading the project. You are in disagreement with the manager about how the project should proceed, the timings of the activities, the suggested schedule, and the expected quality of the work. The manager has requested that you get to work on several of the activities on the critical path even though you and she have not solved the issues concerning the project. Which of the following should you do?
Go to the senior management and voice concerns
Complete the act as requested
Ask to be taken off the project
Refuse to begin activities on the project until issues resolved
B is correct. The project manager must respect the delegation of the functional manager. A, C, and D are all inappropriate actions because they do not complete the assigned work the functional manager has delegated to the project manager.
You are completing a project for a customer in another country. One of the customs in this country is to honor the project manager of a successful project with a gift. Your company, however, does not allow project managers to accept gifts worth more than $50 from any entity. At the completion of the project, the customer presents you with a new car in a public ceremony. Which of the following should you do?
Accept the car since it is customs of the country to refuse it would be an insult to your host
Refuse to accept the car because it would result in a conflict with your organization to accept it
Accept the car and then return it to the custom in private
Accept the car and then donate the car to a charity in customers name
B is correct. Although this solution may seem extreme, it is the best answer because to accept the car in public would give the impression that the project manager has defied company policy. In addition, accepting the car would appear to be a conflict of interest for the project manager. A, C, and D are incorrect. Accepting the car, even with the intention of returning it or donating it to charity, would be in conflict with the company’s policies regarding the acceptance of gifts.