Chapter 13 Flashcards

1
Q
Managing communications necessary to satisfy the needs of and resolve issues with project stakeholders is part of
 Plan Communications 
 Identify Stakeholders 
 Report Performance 
 Manage Stakeholder Engagement
A

Manage Stakeholder Engagement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Stakeholder requirements and expectations provide an understanding of stakeholder
resource requirements.
level of communication during the project
issues that might require corrective actions.
requested changes.

A

level of communication during the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
Which of the following is an example of work performance information?
Percentage of work completed 
Employee satisfaction 
Number of defects in deliverables 
Project earned value report
A

Project earned value report. The work performance data are the raw facts about the project. These raw facts are analyzed and transformed into work performance information for the project stakeholders. The project earned value report is produced after the analysis of raw project facts. This report is then communicated to the project stakeholders. The project earned value report is an example of work performance information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The below organizational process assets are inputs to the Plan Stakeholder Engagement process. Which of the following organizational process assets is of particular importance to this process?
Templates
Policies and procedures
Configuration management knowledgebase
Lessons learned from past similar project

A

Lessons learned from past similar projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
Which of the following documents is a very sensitive document that must not be shared outside the project management team?
Stakeholder engagement plan 
Communication management plan 
Change management plan 
Scope management plan
A

Stakeholder engagement plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
Stakeholder engagement levels include:
 Aggressive 
 Passive 
 Supportive 
 Risky
A

Supportive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
Which of the following is NOT a stakeholder management process?
 Plan Stakeholder Management 
 Identify Stakeholders 
 Manage Stakeholder Engagement 
 Control Stakeholder Management
A

Control Stakeholder Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which of the following activities is not carried out during the Manage Stakeholder Engagement process?
Engaging stakeholders to obtain their commitment to the project
Managing stakeholders through communication and negotiation
Addressing stakeholder concerns and issues
Adjusting strategies and plans for engaging stakeholders

A

Adjusting strategies and plans for engaging stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

If the project yields less than desirable results, the project manager has a professional obligation to hold a lessons learned session. Attendees should include
Internal stakeholders.
External stakeholders.
All key stakeholders.
Upper management and internal stakeholders.

A

All key stakeholders. All key stakeholders should attend the lessons learned session, particularly if the project “fails” or has failing results

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
Which of the following is an executing process from the project stakeholder knowledge area?
 Identify Stakeholders 
 Plan Stakeholder Management 
 Manage Stakeholder Engagement 
 Control Stakeholder Engagement
A

Manage Stakeholder Engagement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How are lessons learned during the project life cycle handled?
They are reviewed and discussed.
They are documented and distributed.
Feedback meetings are scheduled.
They are updated and sent to engineering

A

They are documented and distributed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
Which of the following stakeholder management processes focuses on the development of stakeholder management and engagement strategies?
 Identify Stakeholders 
 Plan Stakeholder Engagement 
 Manage Stakeholder Engagement 
 Monitor Stakeholder Engagement
A

Plan Stakeholder Engagement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
What is the primary output of the Plan Stakeholder Engagement process?
 Stakeholder Engagement Plan 
 Communications Management Plan 
 Stakeholder Register 
 Project Management Plan
A

Stakeholder Engagement Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Inputs to Plan Stakeholder Management include:
Issue log
Pareto charts
change requests
Schedules, variances, and evaluation procedures.

A

Issue log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
Which of the following is not a tool and technique of the Plan Stakeholder Engagement process?
 Expert judgment 
 Stakeholder analysis 
 Meetings 
 Data Analysis
A

Stakeholder analysis. Stakeholder analysis is carried out during the Identify Stakeholders process. This is not a tool and technique of the Plan Stakeholder Engagement process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Jim is currently carrying out the Plan Stakeholder Engagement process. During the exercise, he feels the need to update the project schedule. The draft version of the project management plan is ready but has not been approved as yet. How should Jim update the project schedule?
Jim can directly update the project schedule as the project management plan has not been approved as yet.
Jim can update the project schedule through a change request.
Jim should complete the Plan Stakeholder Engagement process and start the Control Schedule process to incorporate desired changes at this stage.
Jim cannot update the project schedule at this stage.

A

Jim can directly update the project schedule as the project management plan has not been approved as yet.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q
Managing project stakeholders is crucial to the success of any project. Which of the following types of stakeholders should be given due consideration during the Plan Stakeholder Engagement process in order to minimize risks to the project?
 Resistant stakeholders 
 Neutral stakeholders 
 Supportive stakeholders 
 Leading stakeholders
A

Resistant stakeholders

18
Q

Which of the following is not a typical component of a Stakeholder Engagement Plan?
Stakeholder engagement levels
Methods of updating the stakeholder management plan
Stakeholder issues and conflicts
Stakeholder communication requirements

A

Stakeholder issues and conflicts. All of the choices except stakeholder issues and conflicts typically get documented in the stakeholder engagement plan. Stakeholder issues and conflicts are recorded in the project issues log

19
Q
Tools and techniques used Manage Stakeholder Engagement include
 Issue log  
 Negotiation  
 Change log  
 Lessons learned register
A

Negotiation

20
Q
Inputs to identify stakeholders include
 benefits management plan 
 program charter 
 enterprise process assets 
 all of the above
A

benefits management plan

21
Q
\_\_\_\_\_\_ involves managing communications to satisfy needs and requirements of stakeholders.
 Manage Stakeholder Engagement 
 Identify Stakeholders 
 Monitor Stakeholder Engagement 
 Plan Stakeholder Management
A

Manage Stakeholder Engagement

22
Q

Mark is the project manager for designing a new product line. Mark has identified most of the project stakeholders and met them in person to identify their roles and responsibilities, and their interests and expectations for the project. What should Mark do next?
Conduct a stakeholder impact and influence analysis
Assess how influential stakeholders would respond to different situations and events
Update the Stakeholder Management Plan
Schedule stakeholder identification meetings

A

Conduct a stakeholder impact and influence analysis

23
Q
George has been recently recruited in a ground handling company at a major airport. He has been asked to conduct a feasibility study to determine whether outsourcing the aircraft catering function to a third party would be a viable business decision or not. As the first step, Georges wishes to identify project stakeholders and analyze their influences and expectations. Linda is a senior project manager in the company who has recently conducted a similar project regarding outsourcing aircraft cleaning function to a third party. Linda is not a stakeholder in Georges project. Meeting Linda in order to gain insights about project stakeholders and their influences relate to which of the following tools and techniques of the Identify Stakeholder process?
 Expert judgment 
 Stakeholder analysis 
 Analytical techniques 
 Organizational process assets
A

Expert judgment. Analytical techniques and organizational process assets are not the tools and techniques of the Identify Stakeholders process. Meeting Linda to gain insights regarding the project relates to the Expert Judgment tool and technique of the Identify Stakeholders process. Since Linda is not a project stakeholder, meeting Linda does not directly relate to stakeholder analysis

24
Q
What is the prime focus of project stakeholder management?
 Stakeholder analysis 
 Stakeholder communications 
 Stakeholder engagement 
 Stakeholder identification
A

Stakeholder engagement

25
Q

Which of the following is incorrect regarding the Salience Model?
It classifies project stakeholders
It is based on stakeholder organizational roles and responsibilities
It is based on stakeholder powers and ability to enforce their will
It is based on stakeholder urgency

A

It is based on stakeholder organizational roles and responsibilities. The Salience Model classifies project stakeholders based on their powers and urgency

26
Q
Which of the following is not a discrete process defined in the PMBOK (R) Guide?
 Identify Stakeholders 
 Analyze Stakeholder Expectations 
 Plan Stakeholder Engagement 
 Monitor Stakeholder Engagement
A

Analyze Stakeholder Expectations

27
Q

Nancy is initiating a manufacturing process improvement project. It is critical for Nancy to identify her project stakeholders early on and analyze their influences, interest and expectations. The organization exhibits the typical behavior of a functional organization and she is experiencing a lot of resistance carrying out this process. Which of the following inputs will help Nancy get a head start with the process?
Stakeholder analysis
Meetings with stakeholders
Project charter
Lessons learned from previous similar project

A

Lessons learned from previous similar projects

28
Q

Which of the following statements in incorrect regarding project stakeholders?
Stakeholder interests can be negatively affected by the project
Stakeholders can be external or internal to the performing organization
Stakeholder identification is a continuous process and it is not critical to identify stakeholders early in the project
Organizations directly involved with the project are also project stakeholders

A

Stakeholder identification is a continuous process and it is not critical to identify stakeholders early in the project

29
Q
Which of the following is not a Tool and Technique of the Identify Stakeholders process?
Stakeholder register		 
Data analysis	 	 
Expert judgment	 	 
Meetings
A

Stakeholder register

30
Q
Which of the following is not a tool and technique of the Manage Stakeholder Engagement process?
Communication skills	 	 
Change requests		 
Interpersonal skills	 	 
Ground Rules
A

Change requests

31
Q
Which of the following is not an interpersonal skill?
Planning		 
Trust building	 	 
Active listening	 	 
Resolving conflicts
A

Planning

32
Q

Which of the following is not a desirable behavior?
Paying attention to the speaker
Nonverbal communication during communication
Interrupting the speaker in the middle of a speech if the topic being discussed is not interesting
Asking questions and giving feedback

A

Interrupting the speaker in the middle of a speech if the topic being discussed is not interesting

33
Q

Why is the change log an input to the Manage Stakeholder Engagement process?
The change log records all the change requests
The change log documents stakeholder communication requirements
The change log can be used to communicate recent changes to the appropriate stakeholders
The change log records current stakeholder engagement level information

A

The change log can be used to communicate recent changes to the appropriate stakeholders

34
Q
Which of the following documents is an input to the Manage Stakeholder Engagement process that documents stakeholder specific communication requirements, information to be communicated, formats and methods of distribution and the reasons for the information distribution?
Communication management plan
Stakeholder management plan
Change log	 	 
Organizational process assets
A

Communication management plan

35
Q

Which of the following does not happen during the Manage Stakeholder Engagement process?
Components of the project management plan might get updated
Project objectives in the project charter might get updated
Stakeholder list in the stakeholder register might get updated
Lessons learned in the organizational process assets might get updated

A

Project objectives in the project charter might get updated

36
Q

Which of the following organizational process assets is not an input to the Manage Stakeholder Engagement process?
Project advisory boards
Organizational communication requirements
Issue management procedures
Historical information about previous projects

A

Project advisory boards

37
Q

Stacey is managing a website development project. The project is approximately halfway through the execution phase. During a project status update meeting for the key stakeholders, the project sponsor requested a few minor changes to the project scope. What must Stacey do?
Adjust the scope management plan accordingly
Adjust the scope statement and the project WBS
Refer the project sponsor to the change control board
Write a change request on behalf of the sponsor and send to the change control board

A

Write a change request on behalf of the sponsor and send to the change control board

38
Q

James is setting up a project management office at a company. Setting up a PMO is a complex project as the scope and requirements of the project are continuously changing. The project is still in the initiating phase and during a brainstorming session a few functional managers could not agree on some of proposed project objectives and deliverables. What should James do in this situation?
Facilitate consensus between functional managers
Ignore the concerns as functional managers would never accept the existence of a PMO
Seek the project sponsors support to force the preferred decision
Issue a change request

A

Facilitate consensus between functional managers

39
Q

The project management plan is an input to the Monitor Stakeholder Engagement process because:
It contains the project charter
It contains the stakeholder register
It contains the stakeholder management plan
It contains subsidiary plans from each project management knowledge area

A

It contains subsidiary plans from each project management knowledge area

40
Q
Which of the following is not a tool and technique of the Monitor Stakeholder Engagement process?
Data Analysis	 	
Communication methods	
Communication skills	 	 
Meetings
A

Communication methods

41
Q

The benefit of actively managing stakeholders is
reduces the chances of having unresolved stakeholder issues.
It enhances operation synergy.
It limits disruptions during the project.
any of the above

A

any of the above

42
Q

What is the prime objective of the Monitor Stakeholder Engagement process?
It produces work performance information
It produces the change management plan
It adjusts the stakeholder management plan
It updates the organizational process assets

A

It adjusts the stakeholder management plan