Chapter 13 Flashcards
Managing communications necessary to satisfy the needs of and resolve issues with project stakeholders is part of Plan Communications Identify Stakeholders Report Performance Manage Stakeholder Engagement
Manage Stakeholder Engagement
Stakeholder requirements and expectations provide an understanding of stakeholder
resource requirements.
level of communication during the project
issues that might require corrective actions.
requested changes.
level of communication during the project
Which of the following is an example of work performance information? Percentage of work completed Employee satisfaction Number of defects in deliverables Project earned value report
Project earned value report. The work performance data are the raw facts about the project. These raw facts are analyzed and transformed into work performance information for the project stakeholders. The project earned value report is produced after the analysis of raw project facts. This report is then communicated to the project stakeholders. The project earned value report is an example of work performance information.
The below organizational process assets are inputs to the Plan Stakeholder Engagement process. Which of the following organizational process assets is of particular importance to this process?
Templates
Policies and procedures
Configuration management knowledgebase
Lessons learned from past similar project
Lessons learned from past similar projects
Which of the following documents is a very sensitive document that must not be shared outside the project management team? Stakeholder engagement plan Communication management plan Change management plan Scope management plan
Stakeholder engagement plan
Stakeholder engagement levels include: Aggressive Passive Supportive Risky
Supportive
Which of the following is NOT a stakeholder management process? Plan Stakeholder Management Identify Stakeholders Manage Stakeholder Engagement Control Stakeholder Management
Control Stakeholder Management
Which of the following activities is not carried out during the Manage Stakeholder Engagement process?
Engaging stakeholders to obtain their commitment to the project
Managing stakeholders through communication and negotiation
Addressing stakeholder concerns and issues
Adjusting strategies and plans for engaging stakeholders
Adjusting strategies and plans for engaging stakeholders
If the project yields less than desirable results, the project manager has a professional obligation to hold a lessons learned session. Attendees should include
Internal stakeholders.
External stakeholders.
All key stakeholders.
Upper management and internal stakeholders.
All key stakeholders. All key stakeholders should attend the lessons learned session, particularly if the project “fails” or has failing results
Which of the following is an executing process from the project stakeholder knowledge area? Identify Stakeholders Plan Stakeholder Management Manage Stakeholder Engagement Control Stakeholder Engagement
Manage Stakeholder Engagement
How are lessons learned during the project life cycle handled?
They are reviewed and discussed.
They are documented and distributed.
Feedback meetings are scheduled.
They are updated and sent to engineering
They are documented and distributed
Which of the following stakeholder management processes focuses on the development of stakeholder management and engagement strategies? Identify Stakeholders Plan Stakeholder Engagement Manage Stakeholder Engagement Monitor Stakeholder Engagement
Plan Stakeholder Engagement
What is the primary output of the Plan Stakeholder Engagement process? Stakeholder Engagement Plan Communications Management Plan Stakeholder Register Project Management Plan
Stakeholder Engagement Plan
Inputs to Plan Stakeholder Management include:
Issue log
Pareto charts
change requests
Schedules, variances, and evaluation procedures.
Issue log
Which of the following is not a tool and technique of the Plan Stakeholder Engagement process? Expert judgment Stakeholder analysis Meetings Data Analysis
Stakeholder analysis. Stakeholder analysis is carried out during the Identify Stakeholders process. This is not a tool and technique of the Plan Stakeholder Engagement process
Jim is currently carrying out the Plan Stakeholder Engagement process. During the exercise, he feels the need to update the project schedule. The draft version of the project management plan is ready but has not been approved as yet. How should Jim update the project schedule?
Jim can directly update the project schedule as the project management plan has not been approved as yet.
Jim can update the project schedule through a change request.
Jim should complete the Plan Stakeholder Engagement process and start the Control Schedule process to incorporate desired changes at this stage.
Jim cannot update the project schedule at this stage.
Jim can directly update the project schedule as the project management plan has not been approved as yet.