Chapter 5 Flashcards

1
Q
What Validate Scope tool is used to verify if work and deliverables meet requirements and product acceptance criteria?
Alternative identification.	 
Inspection.		
Expert judgment.	 	 
Product analysis.
A

Inspection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Organizational process asset updates to the Control Scope process include
the causes of variances and corrective actions chosen.
the results of requested changes.
changes to the project scope statement.
made to schedule and cost control.

A

the causes of variances and corrective actions chosen.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
\_\_\_\_ Project Scope manages changes to the scope baseline.
Control		
Plan	 	 
Manage	 	 
Verify
A

Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
What control tool will provide the project manager information about the magnitude of variation from the scope baseline?
Work performance information.
Variance analysis.		
WBS.	 	 
WBS dictionary.
A

Variance analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Control Scope:
assures all requested changes are processed.
manages uncontrolled work
only manages controlled changes, but not uncontrolled changes.
recommends preventive action for uncontrolled changes.

A

assures all requested changes are processed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
Control Scope outputs include:
pareto charts	 	 
change requests		
approved deviations	 	 
none of the above
A

change requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Approved change requests that impact project scope are
changes to the approved project scope statement
changes evident in the performance report.
modifications to the approved scope baseline.
modifications to the SBS.

A

modifications to the approved scope baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
Inputs to Control Scope include:
Work performance data		
The Risk Register	 	 
Resource histograms	 	 
all of the above
A

Work performance data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
Variance analysis is a scope control technique that uses \_\_\_\_\_\_ to assess the magnitude of variation.
comparative project resource charts
tracking systems	 	 
project performance measurements
replanning formulas
A

project performance measurements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Scope creep is:
When features are added without prior customer approval.
The adding of project (scope) functionality features without considering time involved.
Adding features and functionality without considering cost and resources.
All of the above.

A

All of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A Gantt chart is:
seldom used.
only used when the project is behind schedule.
a graphic display of schedule-related information.
a textual display of schedule-related information

A

a graphic display of schedule-related information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A WBS is
Answer choices Correct Your choice
A hierarchy that defines and organizes project work.
A technique for evaluating a component or product during a project phase.
A common approach to implementing a quality improvement project program.
A contractual component that designates how activity time and materials are used throughout the duration of the project

A

A hierarchy that defines and organizes project work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Scheduled work, cost estimates, and work to be monitored and controlled, are contained in
the WBS dictionary.
the lowest level WBS components.
work performance reports.the scope baseline.

A

the lowest level WBS components.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
Project Requirements can include
security requirements.	 	 
business requirements.	 	 
technical requirements.	 	 
all of the above
A

all of the above.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
Imposed dates for specific activity completion or project deliverables are called
completion dates.	 	 
schedule activities.	 	 
schedule milestones.		
delivery date
A

schedule milestones.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A work package is
a risk-mitigating component of the WBS.
A group of work components performed during the course of a project.
a document that defines and describes each component in the WBS.
a project work component at the lowest level of the WBS

A

a project work component at the lowest level of the WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

A project manager uses the WBS
To see how planned activities are related to overall performance.
To see how planned activities are related to overall budgeting and scheduling.
To see who is responsible for designated planned activities.
All of the above

A

All of the above.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q
Tools and techniques used to define scope include
Answer choices	Correct	Your choice
product review.	 	 
expert judgment.		
alternative factors.	 	 
all of the above
A

expert judgment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q
Items in the project scope statement include
The scope baseline.	 	 
The WBS dictionary.	 	 
the WBS.	 	 
Project constraints
A

Project constraints.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

The project scope statement
details the needs of the project.
is a statement of ‘what needs to be done’.
states the project objective.
defines the potential risks that might deter success.

A

is a statement of ‘what needs to be done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q
The project scope baseline contains
the initial WBS.		
Capital investment control.
Human resources	 	 
Project procedures
A

the initial WBS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q
Components of the scope baseline include:
SBS	 	 
WBS dictionary		
Product scope	 	 
none of the above
A

WBS dictionary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q
Requirements documentation includes
Quality requirements	 	
Acceptance criteria	 	 
Training requirements	 	 
all of the above
A

all of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q
What Define Scope output details the project's deliverables and the work required to create the deliverables?
The project charter.	 	 
The project boundaries.	 	 
The project scope statement.
The project scope management plan.
A

The project scope statement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
When developing the product scope description, the project management team must describe deliverables at a summary level or greater detail. define the process and criteria for accepting products. list and describe specific project constraints associated with the project scope that limit options toward product development. provide sufficient detail to support later project scope planning.
provide sufficient detail to support later project scope planning.
26
``` Resources used to define scope include: consultants stakeholders industry groups all of the above ```
all of the above
27
``` What types of actions do the project manager and project team perform to execute the project management plan to accomplish work defined in the project scope statement? Pareto analysis Review risks Contact stakeholders None of the above ```
Review risks
28
``` Variance analysis is used to define scope. control scope. collect requirements. define risk ```
control scope.
29
``` Outputs from Validate Scope include: accepted delivery. change approvals. project document updates. none of the above. ```
project document updates.
30
``` Based on project needs, the project scope management plan may be formal or informal. formal. informal and concise. formal and highly detailed. ```
formal or informal.
31
``` The scope baseline includes WBS WBS dictionary project scope statement all of the above ```
all of the above
32
``` The account where scope, budget, actual cost, and schedule are integrated at a management control point and compared to earned value to measure performance, is a planning account. control account. performance account. planning package ```
control account.
33
``` The ________ addresses and documents project deliverables, boundaries, control, and acceptance project charter project plan contract project scope ```
project scope
34
Brainstorming is a technique the management team uses to identify stakeholder expectations and how to most effectively accomplish them. determine the least risky methods and procedures in project execution. develop feasibility, overcome constraints, and achieve assumptions. generate alternative approaches to performing work and executing the project.
generate alternative approaches to performing work and executing the project
35
``` ________ are tools and techniques used to define project scope. Expert judgment and meetings Templates, forms, and the scope baseline The PMIS and baseline Established monitoring and controls ```
Expert judgment and meetings
36
``` A ______ is a WBS planning component below the control account but above the work package, used for planning known work that does not have detailed activities planning account. control package. performance account. planning package ```
planning package
37
``` A tool used in creating the WBS is: work histogram composition decomposition decentralization ```
decomposition
38
``` What information is used to develop the project management plan and detailed project scope? Historical information Project charter information The preliminary project scope statement All of the above ```
All of the above.
39
``` The project team uses scope definition techniques such as product breakdown, value engineering, and systems analyses for stakeholder analyses. to determine product scope. for product analyses. to determine project requirements ```
for product analyses
40
The project scope management plan is intended to: Help the management team define and document project scope. provide guidance on how project scope should be managed and controlled. enable the creation of the WBS. All of the above
All of the above.
41
``` The _________ is built upon the major deliverables, assumptions, and constraints project scope statement project charter project scope control product scope ```
project scope statement
42
"Rolling wave planning is the interaction among the processes within the Planning Process. progressive detailing of the project management plan. the facilitation of activities across multiple processes. the continual process of evaluation and refining the project scope
progressive detailing of the project management plan.
43
``` Tailoring considerations in project scope management include Validation and control Limits and balances Source management The WBS ```
Validation and control
44
``` The project charter and the stakeholder register are _____ for collect requirements. risks assets outputs inputs ```
inputs
45
``` The project manager uses _____ to control scope. activity attributes organizational process history variance analysis procurement documents ```
variance analysis
46
``` _____________ describes how the project scope will be managed and controlled. The product management plan The WBS dictionary The project scope statement The project scope management plan ```
The project scope management plan
47
Which organizational process assets effect how project scope is controlled? Formal and informal policies and procedures. Risk management deficiencies. Conditions and standard specifications. project charter and the WBS
Formal and informal policies and procedures
48
``` Who is responsible for performing and preparing the analyses necessary to define the scope and generate project scope output? The project manager. The management team. Stakeholders. All of the above ```
All of the above.
49
``` Analysis of project performance can result change requests re-definition bid requests requests for proposal ```
change requests
50
The purpose of having a WBS dictionary is To provide a hierarchically organized depiction of the project organization. To provide information that identifies and defines project risks according to an established risk registry. To provide detailed information on resources needed and allocated for each subproject. To provide detailed information including work packages and control accounts.
To provide detailed information including work packages and control accounts
51
``` Inputs to Control Scope include Time baseline Scope team plan Risk Register none of the above ```
none of the above
52
A scope baseline is the schedule of resources needed and allocated for each subproject of the WBS. the approved, detailed project scope statement and its associated WBS. a distribution plan for scope components. the WBS tool for controlling time and resource allocation
the approved, detailed project scope statement and its associated WBS
53
``` Lower level WBS components must be _____ to ensure completion of the corresponding higher-level deliverables. monitored and controlled planned and controlled necessary and sufficient controlled and sufficient ```
necessary and sufficient
54
Project managers tend to get bogged down with too much planning detail. Excessive decomposition can lead to a decrease in efficient work performance. poor resource allocation. non-productive management. all of the above
all of the above.
55
Decomposition" refers to replacing defective project components. centralizing project program management to accomplish strategic objectives. identifying and managing satisfaction of quality standards for individual project components. subdividing project scope and deliverables into manageable components.
subdividing project scope and deliverables into manageable components.
56
``` The project manager creates a WBS to output WBS WBS Dictionary Project Document updates all of the above ```
all of the above
57
``` The WBS dictionary includes codes of cost description of consultation release criteria none of the above ```
none of the above
58
``` The project management team typically waits until the deliverable or subproject is clarified before developing the WBS. This progressive detailing of the project management plan is rolling wave planning. replanning scheduling milestones. bottom-up planning. ```
rolling wave planning.
59
``` ________ is the process of obtaining the stakeholders' formal acceptance to the completed project scope and deliverables. Control scope Define scope Create WBS Validate scope ```
Validate scope
60
``` Tools used in Validate Scope include Inspection Validation Recalibration Execution ```
Inspection
61
``` Validate Scope is concerned with acceptance of deliverables. Control Quality is concerned with meeting quality requirements for deliverables. In relation to Validate Scope, Control Quality is executed Generally before scope validation. During scope validation. Parallel to scope validation. Any of the above ```
Any of the above.
62
``` Outputs from Validate Scope include Accepted documents Change requirements Product alternatives none of the above ```
none of the above
63
``` Each WBS component is defined in terms of how the work is executed and controlled. For example, control components of a construction project could include ______ activities. analysis and scheduling closeout processing inspection and testing progress payment ```
inspection and testing
64
In the scope statement, the project manager includes: Project objectives and deliverables. Estimated project costs. A detailed project phase schedule. A project team directory for stakeholders
Project objectives and deliverables.
65
``` _______ states in detail what needs to be done. Project verification The project charter The project scope statement Work breakdown templates ```
The project scope statement
66
In the context of the project, product scope refers to: the product characteristics. the product functions. required work to accomplish end deliverables. all of the above
all of the above.
67
What is the project team doing when they examine the project and product requirements, and influences, and how those related influences will be managed? They are analyzing the project risks. They are analyzing and understanding the project scope. They are measuring the project and product status. They are creating the project management plan
They are analyzing and understanding the project scope
68
Why collect requirements? To provide a basis for defining and managing the project scope. To ensure the project baseline is appropriate for the type and character or project. To help ensure that effort expended on the project is relative to its size and complexity. To help ensure stakeholders and all those involved are formally informed about the direction and planned project objectives
To provide a basis for defining and managing the project scope
69
``` What activities are involved in scope management? estimating. executing. defining. all of the above ```
defining
70
``` _________ management ensures the project includes all the specified work required, and ONLY the specified work, which is necessary to successfully complete the project. Project Scope Control Risk ```
Scope
71
The primary benefit of collecting requirements is to influence the project's overall mission define the product and project scope mitigate overall product and project changes. establish guidelines project development and application
define the product and project scope
72
``` Directing and managing project work is the integrative process that performs activities outlined in the WBS. project scope statement. project charter. SOW ```
project scope statement
73
The following are inputs to Define Scope: deliverables, recommended changes and corrective actions. work performance information and reports. the project charter, requirements documentation and organizational process assets. organizational assets and updates.
the project charter, requirements documentation and organizational process assets.
74
``` The project manager uses product and stakeholder analyses, expert judgment, and alternatives identification during the process of Collect Requirements Define Scope Validate Scope Create WBS ```
Define Scope
75
``` The project scope is defined as: the degree of stakeholder involvement. the work to be done. plan creation. the project's specified needs ```
the work to be done.
76
What is an activity the project manager does when he/she attempts to manage a project's scope? Create a performance statement. Collect requirements. Estimate potential project risks. Subdivide the major anticipated project deliverables
Collect requirements.
77
``` During Collect Requirements, the project manager should consider how the scope activity will be managed. The scope of the deliverables. customer expectations Product scope. ```
customer expectations
78
``` The project scope begins as a general idea with end goals and objectives. The scope becomes more detailed as the team develops a structured breakdown of the project, identifying specific details. This process is: scope creep. planning. progressive elaboration. strategic design ```
progressive elaboration.
79
``` "Inspection" is an activity used in processing the project management plan. updating work breakdown. validate scope. define scope ```
validate scope.