Quantification and Costing of Construction Works Flashcards
Why were the New Rules of Measurement introduced?
- Prev Standard Method of Measurement (SMM7) purely designed for BoQ production for tender purposes
- Therefore lack of guidance and uniformity when preparing cost estimates and cost plans
- NRM introduced to provide common and consistent basis, to give employers more confidence around what’s been included
If producing estimates and cost plans, which measurement rules represent industry best practice for capital building and building maintenance works in the UK?
NRM (new rules of measurement)
Why should you use the NRM?
- Common and consistent basis for production of cost documents
- Adds confidence to clients
- If QS / firm pursued for negligence, NRM (if followed)would provide means of defence - represents best practice
- If not following NRM, would need good defence why this approach taken
Can you name the 3 documents in the NRM suite?
- NRM 1 - Order of cost estimating and cost planning for capital building works
- NRM 2 - Detailed measurement for building works
- NRM 3 - Order of cost estimating and cost planning for building maintenance works
Can you provide a brief overview of each of the NRM documents?
NRM 1
- Guidance for quantification of building works for purpose of preparing cost estimates and cost plans
- ‘Cornerstone’ of good cost management of construction projects, enables effective and accurate cost advice to be given to clients and other project team members
- Facilitates better cost control
NRM 2
- Prep BoQ and quantified schedules of works
- Rules invaluable for designing and developing standard / bespoke schedules of rates
NRM 3
- Guidance for quantification and description of maintenance works for purpose of preparing initial order of cost estimates
- Rules aid procurement and cost control of maintenance works
How is risk dealt with under NRM?
- Risk allowances not a standard percentage
- Should be properly considered assessment of risk, considering completeness of design and other uncertainties such as extent of site investigation undertaken
What are the 4 categories of risk identified in NRM?
- Employer change
- Employer other (funding risks, policy / spending practices)
- Design development (items of work missed as design developed)
- Construction (site risk, contamination, obstruction)
Why is it important to measure the works according to industry standards and best practice?
- Greater consistency and accuracy of pricing
- Ensure all parties price on same basis, reduce risk of dispute
Is it mandatory for Chartered Surveyors to follow procedures set out in NRM?
No, however when allegation of professional negligence made against a surveyor, the adjudicator / court likely to take account contents of any relevant guidance notes published by RICS in deciding whether surveyor acted with reasonable competence
Structure of NRM 1?
- Intro
- Measurement rules for order of cost estimating
- Measurement rules for cost planning
- Tabulated rules of measurement for elemental cost planning
- Appendices (definitions for GIA, NIA, functional units, elemental breakdowns, templates, general info for cost plan productions)
How does NRM define the ‘cost limit’ for the project?
NRM 1
Max expenditure the client is prepared to make related to completed building (inc construction, professional services, other project costs, items required post completion, during operation and risk allowances
How does NRM define the ‘base cost estimate’ for the project?
NRM 1
Evolving estimate of known factors without allowances for risk / uncertainty / inflation. Sum of works cost estimate, project and design team fees estimate, other development and project costs
Structure of NRM 2?
- General Introduction
- Detailed measurement of building works
- Rules of measurement for building works
- Appendices
Key headings for contractor preliminaries identified in NRM 2?
- Employer’s requirements
- Site accommodation
- Site records
- Completion and post-completion requirements
- Main contractor’s cost items
- Management and staff
- Site establishment
- Temporary services
- Safety and environmental protection
- Control and protection
- Mechanical plant
- Temporary works
- Site records
- Completion and post completion requirements
- Cleaning
- Fees and charges
- Site services
- Insurance, bonds, guarantees, warranties
Types of BoQ under NRM2?
Firm
- Reliability of tender price increases in relation of accuracy of quants provided. If no design changes, firm BoQ at tender stage = final cost
Approximate
- Not enough detail to prepare firm, decided by client that time/cost to produce firm one not warranted
- No lump sum price provided, but tender price totals
- Qty’s subject to remeasurement on completion by QS / cost manager
How do you measure structural steelwork under NRM 2?
Section 15 - measured in tonnes, itemised according to lengths (n.e. 1m / 1-9m / >9m), weight (n.e. 25kg/m / 25-50kg/m / 50-100kg/m) and type (columns, beams, rafters, bracing, purlins, cladding rails)
What items would you measure in association with structural steelwork under NRM 2?
- Framing erection
- Permanent formwork
- Cold rolled purlins and cladding rails
- Isolated structural member
- Filling hollow sections
- Surface preparation and treatment
- Localised protective coatings
How do you measure brickwork walls under NRM?
Masonry- section 14
- Measured in sqm, itemised according to wall thickness, type of construction and method of formation
Other items to measure in association with brickwork / masonry?
- Chimney stacks
- Arches
- Brick reinforcement
- Forming and closing cavities
How do you deal with ground water under NRM 2?
Section 5 - Excavating and Filling
- Measured on itemised basis, original below ground level stated and reference to whether water is polluted
- If post contract water level differs from pre-contract level, measurements must be taken and revised accordingly
- Method and place of discharge left to discretion of contractor unless stated otherwise
What are levels 1, 2, 3 [and 4] mentioned in NRM?
- [Section 4 and] Appendix B of NRM2, describes the logic and arrangement of the levels for elemental cost planning, in increasing amounts of detail
L1 - group element (i.e. facitating works)
L2 - element - key part of group element (i.e. major demolition works)
L3 - sub-element (i.e. soft strip works)
[L4 in Section 4 - component- building work forming sub-element)]
Structure of NRM 3?
- General introduction
- Measurement rules for building maintenance works
- Measurement rules for order of cost estimating
- Cost planning of repair and maintenance works
- Calculation of annualised costs for repair and maintenance works
- Elemental cost planning
- Appendices
Can you name some of the pricing documents we might use at tender stage?
- Bill of quantities (BoQ)
- Schedule of rates (SoR)
- Contract sum analysis (CSA)
- Schedule of work (SoW)
- Priced activity schedule
Why might a CSA make it difficult to agree post contract cost changes?
- Higher level breakdowns (usually elementally) so contractor substantiation is required to agree costs post contract
- More difficult to determine if an item has been costed for and how priced