Design Economics and Cost Planning Flashcards
What is a Section 106 agreement?
Agreements between local authorities and developers- negotiated to grant planning consent
What is contingency?
Sum included in estimate to cover unknown expenses / unmitigated risks during project
How is contingency assessed?
- Should reflect risks, unknown specific items associated with project
- Early design stage, may be % (say 5-10%)
- As risk register is compiled throughout project, this total can be included as contingency
What is meant by a base date within a cost estimate?
- Date where rates and prices within cost estimate based on
- Included for basis of calculations (i.e. starting point for inflation adjustments)
What RIBA stage is an OCE typically produced?
Stage 0 - 1
What RIBA stage is a Cost Plan typically produced?
Stage 2 - 4
What are the RIBA stages of work?
- Strategic definition
- Preparation and briefing
- Concept design
- Spatial coordination
- Technical design
- Manufacturing and construction
- Handover
- Use
What information do you receive at Stage 0 and 1?
- Architectural brief with unit aspirations
- Level of specification
What information do you receive at Stage 2?
Floor plans, elevation drawings, structural, civil, M&E notes, proposals, reposts and strategies
What information do you receive at Stage 3?
Coordinated design packages from architectural, civil, structural and M&E
What information do you receive at Stage 4?
Fully detailed technical design, enough to produce BoQ or schedule of works
What are the changes from RIBA Plan of Work 2013 to 2020?
- Stage 3 - develop design -> spatial coordination
- Stage 5 - construction -> manufacture and construction
- More recognition of MMC and focus on sustainability
What is construction to ‘shell and core’?
- Basis structure, services and building envelope
- Usually includes fitout of landlord and common areas (i.e. main reception, bathrooms, lifts, stair cores)
- Base services typically terminated at entry points to each lettable floor plate
- Life safety services infrastructure typically provided
What is a CAT A fit out?
‘developer’s fit out’
- Generic fit out items to suit most developers, i.e. safety elements, basic fittings (suspended ceiling tiles, raised floors, lighting, power distribution to floor plates)
What is CAT B fit out?
- Additional works to CAT A provision, such as bespoke elements specific to building user needs, enables tenant to occupy and use space
- Typically includes partitions, power distribution to floor boxes, data cabling, artwork and branding, toilet finishes
Where can you find definitions for levels of fit out?
BCO (British Council of Offices) fit-out guide
What is an order of cost estimate (OCE)?
NRM1 definition
- method of cost prediction- estimate based on benchmark data for a similar type of project, based on strategic definition / initial brief
- purpose to establish affordability of client’s proposed development
- takes place prior to full set of working drawings, forms initial build up to cost planning process
Purpose of an order of cost estimate?
Establish if proposed building project is affordable and, if affordable, establish a realistic cost limit
(cost limit = max expenditure the client is prepared to spend on proposed building project)
Difference between an order of cost estimate and cost plan?
- OCE typically stage 0-2, provides possible cost based on higher level info- Initial phase of cost planning process, usually completed with sqm areas or functional units
- Cost Plan typically stage 2 onwards more detailed elemental breakdown, shows how costs are distributed across project, based on a more detailed, specific design
Difference between feasibility study, order of cost estimate and cost plan?
- Feasibility - sets budget
- Order of cost estimate - reviews options
- Cost plan - analyses how budget is being spent
Can you explain the term ‘cost per functional unit’?
NRM1 definition - Unit rate that, when multiplied by no. functional units gives building works estimate
- Can help recommend cost limit
What typical information accompanies an order of cost estimate?
- Covering letter / email
- Executive summary
- Cost limit
- Notes, assumptions and exclusions(i.e. on spec)
- Drawing and info on which the estimate is based
- Schedule of value enhancing options
- Risk register
Format of a feasibility / order of cost estimate?
- Presented on cost per sqm/functional unit/elemental basis, potentially as a range
- Range -> i.e. for element rates for main elements
- Considerations for any site abnormal costs / enabling works
- Prelims, contingency (risk), inflation, location factor adjustments
What is a functional unit?
- unit of measurement considering prime use of building
- i.e. how many apartments / beds / bedrooms
- i.e. retail - net lettable retail space