JL Submission - Technical Flashcards
DE
What are the RIBA stages of work?
- Strategic definition
- Preparation and briefing
- Concept design
- Spatial coordination
- Technical design
- Manufacturing and construction
- Handover
- Use
DE
What are the changes from RIBA Plan of Work 2013 to 2020?
- Stage 3 - develop design -> spatial design
- Stage 5 - construction -> manufacture and construction
DE
What information is typically expected at the end of Stage 0?
Plan of Work 2020 - Strategic Definition
- Client Requirements
- Business case
- Feasibility study / order of cost
DE
What information is typically expected at the end of Stage 1?
Plan of Work 2020 - Preparation and Briefing
- Project brief
- Feasibility studies
- Site information
- Project budget and programme
- Procurement strategy
- Responsibility matrix
- Information requirements
- Order of cost
DE
What information is typically expected at the end of Stage 2?
Plan of Work 2020 - Concept Design
- Project brief derogations
- Signed off stage report
- Project strategies
- Outline specification
- Cost plan
DE
What information is typically expected at the end of Stage 3?
Plan of Work 2020 - Spatial Coordination
- Signed off stage report
- Project strategies
- Updated outline specification
- Updated cost plan
- Planning application
DE
What information is typically expected at the end of Stage 4?
Plan of Work 2020 - Technical Design
- Manufacturing information
- Construction information
- Final specifications
- Residual project strategies
- Building regulations application
DE
What information is typically expected at the end of Stage 5?
Plan of Work 2020 - Manufacturing and Construction
- Building manual (H&S file, fire safety info)
- Practical completion certificate (and defects list)
- Asset information
DE
What information is typically expected at the end of Stage 6?
Plan of Work 2020 - Handover
- Feedback on project performance and post occupancy evaluation
- Final certificate
DE
What information is typically expected at the end of Stage 7?
Plan of Work 2020 - Use
- Feedback on post occupancy evaluation
- Updated building manual (inc H&S and fire safety info) as necessary
DE
What is an order of cost estimate (OCE)?
NRM1 definition
- method of cost prediction- estimate based on benchmark data for a similar type of project, based on strategic definition / initial brief
- purpose to establish affordability of client’s proposed development
- takes place prior to full set of working drawings, forms initial build up to cost planning process
DE
Purpose of an order of cost estimate?
Establish if proposed building project is affordable and, if affordable, establish a realistic cost limit
(cost limit = max expenditure the client is prepared to spend on proposed building project)
DE
Difference between an order of cost estimate and cost plan?
- OCE typically stage 0-2, provides possible cost based on higher level info- Initial phase of cost planning process, usually completed with sqm areas or functional units
- Cost Plan typically stage 2 onwards more detailed elemental breakdown, shows how costs are distributed across project, based on a more detailed, specific design
DE
What typical information accompanies an order of cost estimate?
- Covering letter / email
- Executive summary
- Cost limit
- Notes, assumptions and exclusions(i.e. on spec)
- Drawing and info on which the estimate is based
- Schedule of value enhancing options
- Risk register
DE
How would you price a feasibility / order of cost estimate?
- Presented on cost per sqm/functional unit/elemental basis, potentially as a range
- Range -> i.e. for element rates for main elements
- Considerations for any site abnormal costs / enabling works
- Prelims, contingency (risk), inflation, location factor adjustments
DE
What information do you need to be able to carry out an order of cost estimate?
No established minimum information, but availability affects accuracy and detail
- Building location and type / purpose
- Floor area / no. functional units
- Assumed storey height and whether RAF / suspended ceilings envisaged
- Initial floor plans and drawings
- Indication of spec, M&E
- Budget and cashflow restraints
- Site conditions
- Indicative professional fees
DE
What is a cost plan?
NRM1 definition
- Estimate based on specific design
- Statement showing apportionment of estimate / agreed budget between cost headings
- Method of cost prediction
DE
Purpose of a cost plan?
- Cost consultant document to control design development
- Identify agreed cost limit and how money allocated to different building elements
DE
When would you do a cost plan?
- Typically between RIBA Stage 2-4, increasing detail throughout project
- Stage 4 typically forms basis of PTE (to compare against tender submissions)
PTE no longer referenced in RIBA plan of work
DE
What benefits does a cost plan provide to a project and its team?
- Help predict final project cost
- Designers aware of cost implications and proposals to help arrive at practical and balanced designs
- Provides info for the employer to make informed commercial decisions
DE
Do you need a programme to complete the cost plan?
- Would be helpful- prelims presented as a weekly rate in developed cost plan, so programme or at least high level dates would be required
- Key info required = design and tendering periods, start on site date, construction period, completion date
DE
How do you structure an elemental cost plan? / Typical components?
In accordance with company templates, which follows NRM recommended structure:
- Elemental summary, then breakdowns on separate sheets (facilitating, substructure, superstructure etc)
- Area schedule
- Depending on info, I would provide a cost for contractor’s prelims based on weekly rates / benchmarking / programme
- Add % for OH&P, professional fees, other project costs, then any risk and inflation
- List of drawings and information used
DE
What benefit does the client get out of accurate cost planning?
- Confirms to the client whether scheme is affordable or not
- Places client in informed position to make commercial decisions
- Acts as value management tool- ensure client gets building meeting their needs and representing best value
DE
How would you deal with a cost plan which is over budget?
- Analyse costs to assess sources of increase
- Communicate matter to client and project team clearly
- Identify any abnormally high elements of work
- VE- identify where potential savings can be made, or offer scope reduction