Conflict Avoidance, Management and Dispute Resolution Procedures Flashcards

1
Q

How do you avoid conflict in the first instance?

A
  • Clear tender / contractual information
  • Effective communication
  • Record keeping - put things into writing, filing emails
  • Follow company procedures and policy (inc QA)
  • Follow RICS standards, guidance, professional statements
  • Negotiate issues as early as possible
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How to initially deal with conflict?

A
  • Raise issue with all parties, try to resolve through communication and negotiation
  • Face-to-face meeting usually best way to find resolution
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What indicates success of a final account negotiation?

A
  • All parties come away happy
  • Costs agreed within client budget
  • Negotiation resolved in timely manner
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Causes of most disputes?

A
  • Commercial aspects
  • Unclear / confusing documentation and drawings
  • Teams under pressure - time / resource constraints
  • Insufficient detail / consideration to contracts
  • Unclear scope of service
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What to do if negotiation breaks down and the matter cannot be resolved?

A

Consider ADR (alternative dispute resolution)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is dispute resolution?

A

Actions / processes used to resolve conflict, dispute or claim between parties

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Forms of alternative dispute resolution?

A
  • Mediation
  • Conciliation
  • Negotiation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Formal methods of dispute resolution?

A
  • Adjudication
  • Arbitration
  • Adjudication
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Considerations prior to selecting form of dispute resolution?

A
  • Cost in relation to claim being sought
  • Timescales
  • Impact on business relationships and reputation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What dispute resolution processes are named in your contract?

A

i.e. JCT - negotiation, mediation, adjudication, arbitration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does it mean if a dispute has been crystalised?

A

Dispute has been referred to formal dispute procedure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What does ADR stand for?

A

Alternative dispute resolution
- Other options to traditional binding dispute resolution processes (litigation and arbitration)

Main forms:
- Negotiation
- Mediation
- Adjudication

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the TCC?

A

Technology and Construction Court
- Handles disputes about buildings, engineering, surveying
- Cases usually >£250,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is mediation?

A
  • Parties agree to independent third-party neutral system to facilitate discussion, with goal of reaching settlement
  • Mediator encourages parties to come together
  • Power to settle remains with parties, process led by mediator (mediator doesn’t award winning party)
  • Mutual (voluntary) agreement, initiated at any time between parties
  • Non-binding
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is negotiation?

A
  • Process where parties resolve issues between themselves (informal private / facilitated discussion), ending when both parties come to agreement
  • Simple, easily resolvable, compromises
  • Cooperation of all parties, all agree to be bound by this settlement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is your most successful negotiation?

A

base on own experience
- Reference project, explain what dispute was in relation to
- Explain how I prepared for example, i.e. holding meeting with client / internal team
- Explain non-negotiable items and items conceded, how these were decided
- Talk to assessors through end outcome, how did I insure this was positive for client, wider team, project (i.e. consideration for long term approach)

17
Q

What could indicate success of a negotiation on a final account?

A
  • Both parties satisfied with outcome and feel fair, reasonable compromise reached
  • Partnering approach adopted with both parties feeling long-term relationship and reputations maintained
18
Q

What is conciliation?

A
  • Similar to mediation- conciliator facilitates settlement- they don’t decide any issues / fact - conducts process
  • Conciliator prepares “Recommendation” - sets out solution to dispute, no authority to seek evidence / call witnesses
  • Conciliator acts as message, encourages diplomacy
  • If neither party dissents / initiates adjudication / arbitration, recommendation becomes final and binding
19
Q

What is an expert witness?

A
  • Person whose experience and knowledge of particular field goes beyond what’s expected of a layman
  • Makes their knowledge available to court / other bodies- helps to understand issue to reach reasoned decision
20
Q

What is expert determination?

A
  • Parties agree to refer disagreement to impartial expert third party, bound by their decision
  • More informal, simpler, cheaper than arbitration / litigation
  • For technical disputes, can shortcut to a binding decision
21
Q

How does the adjudication process work in terms of timeframes?

A
  • Either party serves notice to other party of intention to refer dispute to adjudication
  • 7 days (of notice issue), referring party must serve Referral (statement of case) and secure appointment of adjudicator (named / nominating body in contract). Adjudication void if not served in this time.
  • Referral contains detailed explanation of referring party’s claim regarding dispute in notice + supporting documentation
  • After appointment, adjudicator sets out timetable, permits other party to issue response to Referral
  • Adjudicator must make decision within 28 days of referral
22
Q

Can the 28-day decision period be extended?

A

Can be extended to 42 days by mutual agreement of both parties

23
Q

Is the adjudication process binding?

A

Binding and enforceable in court unless adjudicator has acted outside their jurisdiction / shown bias

24
Q

Is there an appeal process for adjudication?

A

No, but parties can take same dispute to litigation / arbitration (if in contract)

25
Q

What if a building contract doesn’t have adjudication provisions?

A
  • Adjudication is now a legal (statutory) right in UK (England, Scotland, Wales) construction contracts (since Construction Act came into force)
  • If contract doesn’t qualify under construction act, Scheme for Construction Contracts applies in its entirety
26
Q

Who enforces requirement for building contract to contain provisions for adjudication?

A

Housing grants, Construction and Regeneration Act 1996 (Construction Act)

27
Q

Who pays for the adjudication?

A

Both parties jointly liable for adjudicator fees, adjudicator can decide who is to pay the fees

28
Q

Adjudicating bodies under JCT?

A
  • Royal Institute of British Architects (RIBA)
  • Royal Institution of Chartered Surveyors (RICS)
  • constructionadjudicators.com
  • Association of Independent Construction Adjudicators
  • Chartered Institute of Arbitrators
29
Q

Can you omit adjudication from a contract?

A

Yes however it’s included in the Construction Act and is mandatory, therefore would still be an option

30
Q

What is arbitration?

A
  • Lawsuit without court involvement
  • Parties agree (via contract / subsequent agreement) to pursue lawsuit in court
  • This gives arbitrator power to issue decision to parties’ rights and obligations - such decision legally binding on all parties
31
Q

Advantages of arbitration?

A
  • Private process - no public process (not necessarily confidential) - can preserve reputations
  • Faster than litigation
  • Arbitrator can have relevant expertise on matter, and their decision can be enforced as judgement of the court
32
Q

Disadvantages of arbitration?

A
  • Parties must bear costs of arbitrator and venue
  • Limited appeal rights
  • For low value disputes, arbitrator fees can be uneconomical
33
Q

Arbitration options listed in contract conditions?

A
  • Royal Institute of British Architects
  • Royal Institution of Chartered Surveyors
  • Chartered Institute of Arbitrators
34
Q

What is litigation?

A
  • Parties commencing claim in civil courts
  • Courts have inherent jurisdiction to hear dispute in respect of (practically) anything
  • Nature, complexity and dispute value determines which court will hear particular dispute
35
Q

Advantages of litigation?

A
  • Judges compel parties to comply with timeframes, can sanction for non-compliance
  • Judges have power to make orders and provide interim releaf
  • Defined rights of appeal in cases where errors of fact/law made
36
Q

Disadvantages of litigation?

A
  • Potentially greater costs if dispute not well managed
  • Potentially longer period to obtain judgement
  • Generally public
  • Judgement subject to appeal
37
Q

Difference between arbitration and litigation procedures?

A

Arbitration
- Governed by Arbitration Act 1996
- Must be agreement by both parties to enter into arbitration
- Wide degree of discretion by parties to how proceedings conducted
- Private process
- Similar to litigation- formal submissions, expert evidence, hearings and decision

Litigation
- Proceedings conducted in court
- Public process following civil rules
- High costs, but process can deal with multi-party disputes and civil procedure rules (aiming for accessibility, speed and efficiency)