Contract Administration Flashcards
Who is responsible for administering the building contract?
- JCT MW/IC/SBC - Contract Administrator
- JCT DB - Employer’s Agent
- NEC3 and NEC4 - Project Manager
Please detail some key responsibilities of the contract administrator under a JCT contract?
- Administering the contract between contracting parties
- Determining EoT and L&E claims
- Issuing PC statements
- Issuing instructions
- Certifying interim payments
- Administrating change control procedures
- Collating and issuing schedules of defects
- Notifying partial possession / certifying sectional completion / non-completion
How does the EA role differ from the CA role?
CA - solely responsible for administering contract for the employer. Impartial role in the contract
EA - acts on behalf of the employer in all matters. When carrying out certification and decision-making, EA should still act impartially
What is practical completion?
- PC - point at which a building project is complete (except minor defects and outstanding works that can be put right without undue interference/disturbance to an occupier
- Project is “capable of beneficial occupation and use’ by Employer
Can you rescind the PC statement once it has been issued?
No - once issued, it’s final and binding on the employer
What are the consequences for the contractor and employer once the PC statement has been issued?
- 50% retention released (STC)
- Defect rectification period starts
- Employer usually required to start insuring and securing building
- Employer’s ability to levy liquidated damages ends
- Performance bond / PCG expires
What is a non-completion certificate?
- Formal written notice that contractor has failed to complete the works described in the Contract by the completion date
- Enables liquidated damages to be levied
What are the consequences of a non-completion certificate?
Triggers right for employer to levy liquidated damages if they choose to do so (employer must also write to contractor notifying them of intent and issue pay less notice to recover LDs)
If a project was due to finish before Christmas, but an extension of time was given which meant the contractor finished after Christmas, is the contractor entitled to costs over the Christmas break, which is normally 2 weeks?
- Depends on why EoT issued and whether L&E allowed to be claimed for
- If L&E can be claimed, contractor would be entitled to costs over Christmas period
What is the defects liability period?
- Duration at end of contract (usually 1 year after PC certificate issued) where contractor undertakes to rectify any defects arising within the structure at the Contractor’s expense, providing they were due to materials and workmanship not in accordance with contract
- If the contractor failed to rectify any defects, the employer may employer someone else to undertake and recover cost from main contractor (can use retention monies)
What’s your understanding of latent defects and what contractual issues are associated?
- Latent defects not readily identifiable upon inspection, only come to fruition some time after completion, potentially after years
- Claim in contract can only be brought about within limitation period (6 / 12 years depending on whether executed as a deed or underhand)
What should the CA do if latent defects are discovered?
Issue instruction to contractor as necessary, may include to instruct compliance with 3rd party examining / opening up works to identify defect
Why might the EA instruct the contractor to ‘open up’ works which have been covered up?
- If they suspect work isn’t completed in ‘proper and workmanlike manner’ or believes ‘materials, goods, or work not in accordance’ with the Contract
- Defined under clauses 3.12 and 3.13
When issuing instructions for further opening up and testing to determine the extent of non-compliance what sort of things should the CA consider?
- Significance of non-compliance and consequences on building owners, users, adjoining properties and public
- Reason for non-compliance
- Level of supervision and control employed by contractor
- Recognised testing methods
- Time and consequential costs of opening up
Assuming the EA has instructed the contractor to ‘open up’ the works, what are the potential outcomes? (including effect on cost and completion date)
- If works NOT defective, contractor paid for opening up, may be entitled to adjustment of completion date
- If works ARE defective, contractor remedies at own expense / gives Employer saving, EA can instruct Contractor to open up similar work, which if defective no payment / adjustment of completion date. If not defective, completion date may be adjusted but still no payment