Project financial control Flashcards
If asked by the client to produce a Cashflow analysis how would you do this
“Plotting S-Curve
Review of programme/ works to forecast the spend across the months”
What can cashflows be used for
To forecast the monthly spend
What are the different components of a cost report
"Cover QA/QC Contract details Executive summary (current condition, cashflow, programme etc) Provisional Sums EAI's Potential EAI's Contentious issues Cashflow section Warranty tracker Last payment cert"
What are the different types of contingency and how would you calculate an allowance
“Construction Risk - Ground risk, existing buildings
Design Development Contingency - Planning changes, procurement delays, statutory requirements
Employer Change Risk - Changes in scope, quality, time
Employer other risk - Early handover, acceleration, LAD’s
Properly considered assessment not percentage based on design completion , uncertainty and investigation done
What is a provisional sum and how is it expended
“Provisional sum is a an allowance for an as yet undefined scope of works
Defined - Nature of the works, how to be fixed, programme included
Undefined - Cannot be defined or allowed is an allowance without detail”
What is a Final account
“Financial conclusion of works
It includes all adjustments made within the contract sum”
Are LAD’s included within a final account
No
How do you agree a variation with a contractor
“Following the valuation rules within the JCT
Contract rate
Similar contract rate
Fair rate for works
Labour and materials”
Are verbal instructions legally binding under the JCT
Yes
Under JCT D&B who is responsible for issuing a Final Account statement
Contractor
What is VE
Value Engineering - Re active approach to reduction of cost but maintain functionality
Can you pay for materials off site
“Yes
Listed items in the JCT
Through a Vesting cert”
What is a Vesting Cert
“Vests the ownership to the client
Ensure they are insured and stamped and separate”
Why is financial control so important
“Pre Contract
Allows the client to understand the cost of the current design and if this is inline with their budget
Allows the client to allocate their budget/VE if required
Post Contract
Allows the client to understand the predicted outturn cost (Final account)
Cashflow to ensure that finances are available through the scheme
Allows client to understand exposure to risk, anticipated variations & costs, Contentious items, EOT’s L&E “
How do you agree a final account
“It can be a protected process. We review EAI’s agreed ensure included.
Provisional sums included adjusting for the actual cost
Resolution of contentious items
May require negotiation to resolve the final items of costs”
Who submits a final account and when
“Contractor submits final account
I. Following PC contractor must submit FA
ii. If not submitted within 3 months employer may give notice. If not submitted within a further 2 months employer can issue final account statement.”