Case Study Flashcards
What other procurement route would you of recommended to the client in place the JCT D&B?
“I would recommend Traditional
It would allow the client to maintain control of design and get the design to a more progressed stage without handing control to the contractor.
Whilst this would potentially extend the programme it would allow the client to specify all details and design requirements as I feel there were areas within our design that were lacking or still in abatement
Would have given more cost certainty between PTE & Tenders
Current thoughts on TPI
“It is currently circa 2.2% (CHECK CLOSER TO INTERVIEW)
Lower than current market trends show”
What is the CPC forecast for inflation over the next couple of years
“CPC have carried out some forecasting for the residential sector and believe;
Pessimistic 8.5% 2022 - 6.0% 2023
Realistic 5.5% 2022 - 4.0% 2023
Optimistic 5.0% 2022 - 3.0% 2023”
What indices or market intelligence do you use to advise the client of changes in the market coming up?
“We use intelligence we receive from contractors & tender prices
Other consultants forecasts
BCIS
Articles & web links such as construction inquirer”
Are there any observations of criticisms of the BCIS and the TPI
“It is only as good as the information that is supplied to it.
If consultancies/ contractors don’t provide enough sample information then it will not be reflective of the wider industry”
Is it standard for clients to go with an unamended contract
No, We always (normally) see clients amend the contract
Is it fair that the clients amend the JCT contract
“No. The JCT is tested through the courts amending this changes the legal president of the contract
It will always be for the benefit of the client
Leads to protracted pre contract negotiations”
Your swing was circa 18% from lowest to highest. What is a swing that you would recommend to a client is acceptable
“No. We would anticipate this being circa 5% (NORMALLY)
Due to the changing market conditions however we are increasingly see this closer to 10% due to the uncertainty in the market the smaller the scheme the bigger the impact we are seeing in tender price as smaller contractors have less buying power”
What other elements of note did you VE other than FFE
“Finishes - Savings for acoustic ceiling tiles
Finishes - Vinyl wall covering (Paint)
Finishes - Green wall
External works - £20k tepee & bases
External - 5k connecting pathway
Glazed Entrance - £36k ADD back £12k for draft lobby
Electrical - £37k Omit Speed gates”
Did you focus on M&E or is there a reason you didn’t
M&E wasn’t a focus
HVAC diffusers relocated but layout remained mainly unchanged
Lighting was all new but internal layout not changed so LUX levels needed to be maintained
What happened in instances where you disagreed with the value that the contractor had proposed to be omitted
“We had to negotiate our position with the contractor
I discussed it with the client to set out our position to ensure agreement
Set this out to the contractor highlighting areas we agreed but highlighting where I had concerns
listened to the contractors positions and agreed on a position both agreed on.”
How does the unamended JCT deal with inflation in the contract
“Option A - Contribution, levy and tax payable as an employer
Option B - In addition to A this covers labour & material costs
Option C - Formula adjustment using the Formula Rules
OPTION D - NO PROVISION
JCT allows for an alternative provision to be stated by agreement by the parties”
Fluctuation Provision Option A - Contribution, levy and tax payable as an employer
Option A - Contribution, levy and tax payable as an employer
Deals with adjustments to contract sum based on TAX changes that an employer has to pay
Adjustment is made when statutory tax or duty change”
Fluctuation Provision Option B - In addition to A this covers labour & material costs
Option B - In addition to A this covers labour & material costs
“This allows for adjustment for labour & materials
Contract is based on wage fixing body. If a rate changes at the base date then the contract sum is adjusted
It includes; wage, bonus, OT, AL etc
Calculation can be difficult
Option A&B can require the contractor to supply full build up of rate& prices in tender. Not 100% accurate as contractor price will be approximate of plant labour materials”
Fluctuation Provision Option C - Formula adjustment using the Formula Rules
Option C - Formula adjustment using the Formula Rules
“Formula adjustment relies on indicie adjustment based on base date (normally 1 month before return)
Contract sum divided into categories/work groups which are adjusted by indices up/down
Provision of non adjustable items can be included for elements not related to change”