Conflict avoidance, management and dispute resolution procedures Flashcards

1
Q

How can disputes be avoided

A

“Clear lines of discussion

Clear contract docs

abiding by the obligations of the contract”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is ADR

A

“Alternative dispute resolution anything other than litigation;

Negotiation
Conciliation
Mediation
Adjudication
Arbitration"
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is negotiation

A

Discussion between parties to resolve an issue

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is conciliation

A

“Independent party facilitates a discussion

It is legally binding”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is mediation

A

“3rd party comes in to facilitate discussions

Not legally binding

courts recommend this as the first process”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is arbitration

A

“Disputes heard by private tribunal

Alternative to litigation

it has 5 objectives;

  1. fair, cost effective and quick
  2. Promote party autonomy
  3. Courts have supportive powers
  4. Language user friendly and accessible
  5. follows the law

Outcome binding and final”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the schedule of Adjudication

A

Option under the JCT

RICS can be selected as adjudicator

Construction act provides for the provision of adjudication

  1. any one can serve notice of intent to adjudicate
  2. Adjudicator must be appointed in 7 days
  3. decision must be done within 28 days
  4. can be extended by agreement (14 days)”
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the RICS dispute resolution board

A

Independent impartial panel providing guidance to resolve project issues and mitigate impact on schemes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How is an adjudicator appointed

A

“Normally already nominated through the contract

RICS, RIBA etc”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the Technology and Construction Court

A

The court that hears disputes related to construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Benefits of ADR

A

ADR gives parties in dispute the opportunity to work through disputed issues with the help of a neutral third party. It is generally faster and less expensive than going to court. When used appropriately, ADR can: save a lot of time by allowing resolution in weeks or months, compared to court, which can take years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Does the mediator give a verdict

A

Recommend an outcome based on going to court

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Does adjudication need to be specified in the contract

A

It is a statutory requirement for adjudication to be allowed for

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the JCT default dispute resolution options

A

“Negotiate
Mediate
Adjudicate
Arbitrate/Litigate”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Is the adjudicators decision binding

A

Binding until disputed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When can you challenge an adjudicator decision

A

Decision is binding until PC then it can be challenged

17
Q

Why is litigation avoided

A

“Expensive

Takes time

The decision is public”

18
Q

RICS guidance note for conflict avoidance

A

Conflict avoidance and dispute resolution in construction.

Identifies key issues we should be aware of in disputes, and good practice principles for avoiding disputes/ resolving disputes.

Good document management and people management is the first principles. Dispute resolution is, negotiation, mediation or conciliation, adjudication