Procurement & Tendering Flashcards

1
Q

What is the difference between tendering and procurement

A

“Procurement is the obtaining of goods and services

Tendering is the process of obtaining price and resource”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What tender strategies have you found most effective through the pandemic and why

A

“Two stage or negotiated

Order books are full

removes risk for contractor of spending time and money

Hesitancy to price on single stage”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What 3 factors are evaluated in deciding the procurement route

A

“Time

Cost

Quality”

RISK

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a Form of Tender

A

Formal acknowledgement that they understand and accept the terms and conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a certificate of bone fide tender

A

Acknowledgement that this is a realistic and accurate bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What has replaced OJEU

A

“Find a tender which is an online platform

No need to post on OJEU”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does a tender report consist of

A
"Cover
QA/QC
Basis of tender
Summary of returns received
Analysis/equalisation done
Analysis back to estimate
Summary and recommendation"
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

If a contractor submitted their return at 12:02 and the deadline was 12 what would you advise the client to do

A

“Make the client aware

Proceed with analysis

Does not seem fair and reasonable to exclude the contractor for 2 minutes”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are some advantage of 2 stage tender process

A

“Early contractor design input

Integrated design team

Greater cost certainty

Cost savings”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Is the lowest price always the tender we should recommend

A

No, We should recommend (dependent on scoring criteria) the price that represents the a value that the contractor will be able to complete the works competently and safely

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How would you deal with an error in a tender submission

A

“JCT Practice Note

Alternative 1 – Standby or withdraw
Alternative 2 – Standby or Adjust”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What RIBA stage would you tender the work for a traditional contract

A

RIBA Stage 4 - Technical Design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What would the tender consist of

A
"FOT
Instructions to Tenderers
Contract Conditions
Prelims
Amendments
Full set of drawings, specs etc
Pricing schedule
Appendices"
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is traditional procurement route

A

“Client maintains control of design

Contractor takes risk for pricing of the drawings not the design

If design not complete or subject to change contractor will be eligible for variation

No risk premium from the contractor

Longer programme

Easy to compare tender returns”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a D&B procurement route

A

“Design and build where the contractor is responsible for design and construction

Single point of responsibility for design and construction

shorter programme as design and construction over lapped

Programme certainty

Novate designers

ER’s need to be clearly defined

Longer evaluation period required to ensure CP’s meet ER’s

Expensive post contract changes”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is management contracting

A

“Quick method of procurement

Final cost not known until completion

No motivation for the contractor to reduce costs

quick start on site

early contractor input

design can run into construction”

17
Q

What is construction management

A

“Client employs designers

Construction works carried out by trade contractors

Client in direct contracts with trade contractors

quick SOS

Early input can help

Good client brief must be provided

CM must have good understanding of what is required”

18
Q

What considerations to you need to give to time cost quality

A

“You cant satisfy all.

Scheme can be done on a short programme for low budget but quality will suffer

High budget high quality will take time

19
Q

What is the other consideration other than time cost quality

A

Risk - How risk averse is the client

20
Q

Why would project size and complexity affect procurement & tendering

A

“You may need to go through additional steps (PQQ, EOI)

You may need early contractor engagement (Two stage)

In order to manage risk or get contractor interest may need early engagement

21
Q

What is the merits of a two stage over a one stage

A

“Early contractor engagement

Provide greater cost certainty as the contractor involved in design and spec

Reduces risk of delay as the contractor can feed into the programme”

22
Q

What is a PQQ, when would you use one

A

“PQQ is a way to ensure that the contractors the tender is issued to have the requisite skill and experience

Asks a series of questions to ascertain level o knowledge”

23
Q

What is an expression of interest

A

EOI is tenderers response to a scheme to confirm interest in tendering

24
Q

How does negotiated open book work

A

“One contractor procured (based on experience)

Selected main packages

Contractor shared the procurement details and VFM processes that had been gone through to select sub contractors

This ensures market testing and VFM

Not always cheapest price”

25
Q

What is a mini comp an how does it work

A

“Consultants off a framework

Price only (already fulfilled quality aspect through framework)”

26
Q

How do you assess the most economically advantageous tender

A

“Cost of works within benchmark

Costs not too low (price reflects the works and current market)

Response to quality questions

Requisite skill and experience”

27
Q

Would you recommend negotiation to a client without frameworks in place

A

“Depends on market conditions

Time available

Relationship to contractor

Scheme complexity”

28
Q

How do you get VFM through a negotiation

A

“Through the use of framework/framework rates

Check against benchmark rates

Review Abnormals and assess the risk and value of these”

29
Q

How do you assess/normalise a tender

A

“Use the average cost or PTE to normalise cost

Use cost plan as benchmark

Highlight high/low out liars

Prov sums & prelims should be equalised also

Risk allowances should also be analysed”

30
Q

Why do you have robust tendering strategies

A

“1. Accountability

  1. Auditable
  2. Ensure everything is captured
  3. Parity
  4. Reduced claims of corruption
  5. Correct price paid for works”
31
Q

What period should be given for assessing tender periods

A

“Depends on
Complexity
Size
Market conditions

Traditional with BOQ - 1month
D&B not fully prescribed - 3-4 months
D&B clearly defined - 6-8 weeks

The tender period should not be extended as a standard matter of course”

32
Q

What have you seen recently in the market from tendering & procurement

A

“Difficult to get contractors to price for single stage

Negotiated or two stage the preferred (better chance of work, without cost of tendering)

Unable to get contractors to fix price for more than 12 months want fluctuations”

33
Q

What financial basis can works be procured

A

“Fixed price
Re-measurable
Reimbursable
Target cost”

34
Q

What are the UK Planning procedures?

A

Legal process to determine if a development should be permitted.

dealt with by planning officers who review current guidance to advise on if granted and what conditions should be granted along with the planning

Has statutory durations for when these should be resolved;

Simple development - 8 weeks

Technical details - 10 weeks

MAjor/complex development 13 weeks

35
Q

What is a development appraisal

A

Financial appraisal of the development. Understanding of the full financial cost of the scheme (land, planning etc & Construction) to what the return can be on the investment. through rents or sales and the required tenure split