Procurement & Tendering Flashcards
What is the difference between tendering and procurement
“Procurement is the obtaining of goods and services
Tendering is the process of obtaining price and resource”
What tender strategies have you found most effective through the pandemic and why
“Two stage or negotiated
Order books are full
removes risk for contractor of spending time and money
Hesitancy to price on single stage”
What 3 factors are evaluated in deciding the procurement route
“Time
Cost
Quality”
RISK
What is a Form of Tender
Formal acknowledgement that they understand and accept the terms and conditions
What is a certificate of bone fide tender
Acknowledgement that this is a realistic and accurate bid
What has replaced OJEU
“Find a tender which is an online platform
No need to post on OJEU”
What does a tender report consist of
"Cover QA/QC Basis of tender Summary of returns received Analysis/equalisation done Analysis back to estimate Summary and recommendation"
If a contractor submitted their return at 12:02 and the deadline was 12 what would you advise the client to do
“Make the client aware
Proceed with analysis
Does not seem fair and reasonable to exclude the contractor for 2 minutes”
What are some advantage of 2 stage tender process
“Early contractor design input
Integrated design team
Greater cost certainty
Cost savings”
Is the lowest price always the tender we should recommend
No, We should recommend (dependent on scoring criteria) the price that represents the a value that the contractor will be able to complete the works competently and safely
How would you deal with an error in a tender submission
“JCT Practice Note
Alternative 1 – Standby or withdraw
Alternative 2 – Standby or Adjust”
What RIBA stage would you tender the work for a traditional contract
RIBA Stage 4 - Technical Design
What would the tender consist of
"FOT Instructions to Tenderers Contract Conditions Prelims Amendments Full set of drawings, specs etc Pricing schedule Appendices"
What is traditional procurement route
“Client maintains control of design
Contractor takes risk for pricing of the drawings not the design
If design not complete or subject to change contractor will be eligible for variation
No risk premium from the contractor
Longer programme
Easy to compare tender returns”
What is a D&B procurement route
“Design and build where the contractor is responsible for design and construction
Single point of responsibility for design and construction
shorter programme as design and construction over lapped
Programme certainty
Novate designers
ER’s need to be clearly defined
Longer evaluation period required to ensure CP’s meet ER’s
Expensive post contract changes”