Project+ Extra 11 Flashcards

1
Q

??? hierarchical arrangement of identified risks that helps PMs organize potential sources of risk to a project. Much like WBS, RBS arranges categories into hierarchy, which allows project team to define risk at detailed levels.

A

Risk Breakdown Structure :

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Risk Analysis : evaluation of prob/impact of occurrence of risk in project. Qualitative/quantitative techniques used.

Risk-Averter : not likely to take risk thats considered high risk.

Risk-Neutral : tolerance to risk is proportional to amount of money at stake.

Risk-Seeker : accepts uncertain outcome, may be willing to take high risk regardless of consequences.

Communication Channels Formula : (n(n-1)) / 2

A

info

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

??? standards used to rate or score proposals, quotes, or bids and form a part of procurement solicitation documents. Objective Criteria -> can be readily demonstrated, specific, and measured. Subjective Criteria -> open to different interpretations.

A

Source Selection Criteria :

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

??? project scope baseline, requirements documentation, existing teaming agreements, project risk registers, risk-related contract decisions, activity resources requirements, project schedule, activity cost estimates, cost performance baseline, enterprise environmental factors, existing organizational process assets; after procurement plan is created other relevant outputs of procurement process -> procurements SOWs, make-or-buy decisions, procurement documents, source selection criteria, change requests.

A

Procurement Document Includes (procurement management plan) :

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

ROM : developed w/o any detailed base data and based on high-level historical data, expert judgement, or costing model. Made early in project. Accuracy -> -25% - +75%.

Range of Estimate : used as alternative to ROM where accuracy of estimate is not well known. Accuracy -> +-35%.

Approximate Estimate : based on more info than ROM estimates but lacks the detail for high accuracy. Estimate may be possible if project is similar to previous ones w/reliable historical data for costing or where proven costing model is applicable. Accuracy -> +-15%.

Budgetary Estimate : used for appropriation purposes. Accuracy -> -10% - +-25%.

Definitive Estimate : based on detailed info about project work and is developed by estimating cost for each work package in WBS. Accuracy : -5% - +10%.

A

info

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

??? allows use of ROM or approximates for later parts of work, while work that must be done earlier in project life cycle is estimated at definitive level.

A

Rolling Wave Estimate :

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

??? cost estimation based on bids obtained from vendors. Proposed costing from vendors is considered while developing estimates for project.

A

Vendor Bid Analysis :

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

??? estimates of costs necessary to finish project work. Including -> costs of direct labor, materials, equipment, facilities, service, IT, contingency reserves, and indirect costs. Costs estimates for each activity are added together to create overall cost estimate for work package.

A

Activity Cost Estimates :

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

??? involves supporting and extra info needed to justify cost estimates. Details can include project scope, justification for estimate, assumptions, constraints, confidence level of estimate, and expected range of estimates.

A

Basis of Estimates :

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

??? method of adjusting, spending, and allocating resources in order to bring expenditures into alignment w/budgetary constraints.

A

Funding Limit Reconciliation :

How well did you know this?
1
Not at all
2
3
4
5
Perfectly