Project Cost Mgmnt Flashcards

1
Q

Estimate of Costs

A

Process of developing an approximation of the monetary resources to complete project activities.

Expresses in units if currency.

Accuracy of estimates will increase as the project progresses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Rough Order Magnitude

ROM

A

Cost = unit rate x usage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Analogous Estimating

A

Uses parameters to measure cost. Used historical info and expert judgement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Parametric Estimating

A

Used statistical relationship between historical data and other variables to calculate an estimate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Bottom-up Estimating

A

Method of estimating a component of work. Cost of individual work packaged is estimated with greatest level of specified detail. Detailed cost is then rolled up to higher levels for subsequent reporting and tracking.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Determine Budget

A

Process of aggregating the estimated costs of individual activities or with packages to establish an authorized cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

S-Curve Budget

A

Displays cumulative curve of projects total budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Planned Value (PV)

A

Authorized budget assigned to the work to be accomplished for the activity or WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Earned Value (EV)

A

Work performed expressed in terms of the approved budget assignment to work for an activity or WBS

Compares the baseline plan to actual schedule and cost performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Actual Cost (AC)

A

Total cost actually incurred and recorded in accomplishing work performed for an activities or WBS component

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Schedule Variance (SV)

A

Measure of schedule performance on a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Cost Variance (CV)

A

Measure of cost performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Schedule Performance (SPI)

A

Measure of progress achieved compared to progress planned on a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Cost Performance Index (CPI)

A

Measure of the value of work completed compared to the actual cost or progress made on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Variance Analysis

A

Used to assess magnitude of variation to original cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Trend Analysis

A

Examines performances over time to determine if it’s improving or deteriorating

17
Q

The cumulative CPI has been show to be relatively stable after what percentage of project competion?

A

15-20%

18
Q

Performance Measurement Baseline

A

The undistributed budget is part of this