Project Cost Managment Flashcards
The actual amount of monies the project has spent to date.
Actual cost (AC)
An approach that relies on historical information to predict the cost of the current project. It is also known as top-down estimating and is the least reliable of all the cost-estimating approaches.
Analogous estimating
An estimating approach that starts from zero, accounts for each component of the WBS, and arrives at a sum for the project. It is completed with the project team and can be one of the most time-consuming and most reliable methods to predict project costs.
Bottom-up estimating
This estimate is also somewhat broad and is used early in the planning processes and also in top-down estimates. The range of variance for the estimate can be from -10 percent to +25 percent.
Budget estimate
A cost-estimating approach that uses a database, typically software-driven, to create the cost estimate for a project.
Commercial database
A planned amount of money or time which is added to -an estimate to address a specific risk.
An allowance to account for overruns in costs. This is used at the project managers discretion and with managements approval to counteract cost overruns for scheduled activities and risk events.
Contingency reserve
This requires you to aggregate or combine costs from an activity level to a work package level. The final sum of the cost estimates is applied to the cost baseline.
Cost aggregation
Projected budgets that predict the overall cost of a project in a particular period. They are also called time-phased budgets because they are budgets that are linked to a specific time period.
Output of Determine budget
Cost baseline
The cost aggregation achieved by assigning specific dollar amounts for each of the scheduled activities or, more likely, for each of the work packages in the WBS. This applies the cost estimates over time.
Cost budgeting
A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources, and the associated impact on the overall project cost.
Cost change control system
This dictates how cost variances will be managed.
Cost management plan
The monies spent to recover from not adhering to the expected level of quality. Examples may include rework, defect repair, loss of life or limb because safety precautions were not taken, loss of sales, and loss of customers.
Cost of poor quality/Cost of nonconformance to quality
The monies spent to attain the expected level of quality within a project. Examples include training, testing, and safety precautions.
Cost of quality
Measures the project based on its financial performance.
Cost performance index (CPI)
The formula is CPI = EV/AC.
The difference of the earned value amount and the cumulative actual costs of the project.
Cost variance (CV)The formula is CV = EV - AC.
This estimate type is one of the most accurate. Its used late in the planning processes and is associated with bottom-up estimating. You need the WBS in order to create the XXX. The range of variance for the estimate can be from -5 percent to +10 percent.
Definitive estimate
expenses tied directly to the product or the project and cannot be shared among projects (for example, airfare, hotels, long-distance phone charges, and so on)
Direct Costs
The completed to date and the authorized budget for that work. It is the percentage of the BAC that represents the actual work completed in the project.
Earned Value (EV)
This formula predict the likely completed costs of the project based on current scenarios within the project.
Estimate at Completion (EAC)