Calculations Flashcards

1
Q

Payback

A

Initial investment / return

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

RIO Return on Investment

A

((Project Value-Project Cost)/Project Cost) X 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Total amount of interest paid

A

Amt borrowed X (1 + Interest)to the N power, where N is timeframe
*Subtract that Amt from Amt borrowed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Your project will cost $80,000. The finance department estimates revenues the next three years to be: $20,000, $35,000, and $66,000. If the current interest rate is 5%, what is the estimated NPV for your project?

A

Year 1: $20,000 / 1.05 = $19,047.62;
Year 2: $35,000 / 1.10 = $31,818.18;
Year 3: $66,000 / 1.16 = $56, 896.55;
Total Cash Inflows: $19,047.62+$31,818.18+$56, 896.55 = $107,762.35;
$107,762.35 - $80,000 = $27,762.35.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What the project should be
worth.

A

Planned value (PV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What the project is worth

A

Earned value (EV)
Percent complete X BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What the project has spent
so far

A

Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What the project budget is

A

Budget At Completion (BAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The difference between
earned value and the actual
costs

A

Cost variance (CV)
EV (Percent Complete X BAC) -AC

Positive – under budget
Negative – over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The difference between
earned value and planned
value

A

Schedule variance (SV)
EV (Percent Complete X BAC) -PV

Positive – ahead of schedule
Negative – behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Projection of being over or
under budget based on
current performance

A

Variance at Completion (VAC)
BAC-EAC

Positive – under budget
Negative – over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Shows overall cost efficiency
on the project.

A

Cost Performance Index (CPI)
EV (Percent Complete X BAC)/AC

Greater than 1 – under budget
Less than 1 – over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Shows overall schedule
adherence

A

Schedule Performance Index
(SPI)
EV (Percent Complete X BAC)/PV

Greater than 1 – ahead of
schedule
Less than 1 – behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Forecasts final project
costs based on current
performance

A

Estimate at Completion (EAC)
Standard formula

BAC/CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Predict how much more the
remainder of the project will
costs

A

Estimate to Complete

EAC-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What does the standard deviation tell about a data set?
1. The mean of the population in the way it relates to the medium
2. The upper and lower spec limits of the population
3. The range of data points for the population
4. How diverse the population is

A
  1. How diverse the pollution is

The standard deviation is calculated by averaging all the data points to find out the mean. The average of how far each individual point is from that mean. Hence for a diverse population, a higher standard deviation will be there and vice-versa. Hence, standard deviation measures how diverse the population is.

17
Q

Float Equation

A

Slack/Float = LS – ES or LF – EF

If Float = 0, then the activity is on the critical path
If Float < 0, then the activity is Behind Schedule!

18
Q

Future Value of Money

A

 FV Future value=PV Present value(1+interest rate/rate of return)to the n power n is # of time periods
 Example: PV is 100,000, I is .06, n is 5 years
 FV=100,000(1.06)5th power
* FV=133,822.60

19
Q

Present Value of Money

A

PV=FV/(1+i)to the n power

20
Q

Net Present Value: anything greater than X is good

A

1

21
Q

Internal Rate of Return: anything greater than X is good

A

0

22
Q

Internal Rate of Return: anything greater than X is good

A

0