Programming and Planning Flashcards
What is a critical path?
The critical path is the shortest time to complete all activities in a logical order. It is a sequence of activities through a precedence network from start to finish, the sum of whose durations determines the overall duration.
What is a programme?
A programme is a timetable showing the forecast start and finish dates for activities or events within a project. When a PM has defined the scope of the project, understood quality requirements and risk and has estimates of activity duration in place, the next step is to put together within a schedule.
What is critical path analysis?
This is an activity based technique that determines the overall duration of the identified work based on estimates and logical dependencies. It is the method to determine the critical path and which activities are critical and which have total float (i.e. will not make the project longer if delayed).
It calculates the longest path of planned activities to logical end points or to the end of the project, and the earliest and latest that each activity can start and finish without making the project longer.
What is float
The time by which an activity may be delayed without affecting the overall project duration.
What is an EOT
An extension of time is a delay to the project that is of no fault of the contractor. The contractor needs to give notice in writing and try and mitigate the delay.
How is an EOT managed and what are the implications?
As a CA or EA, when a notice of delay is received, you need to acknowledge receipt and you need to review the EOT claim and challenge it to see if the contractor has tried to mitigate the delay even if they are not at fault. If you accept the delay caused by a relevant event, then you can grant the EOT an the completion date of the project is then adjusted.
What does a programme identify?
Programmes will often identify:
- Dates and duration allocated to tasks.
- A critical path - the sequence of critical tasks upon which the overall duration of the programme is dependent.
- Tasks which can only be carried out after the other tasks have been completed.
- Tasks which can be carried out in simultaneously.
- Float - the delay in which can be incurred without affecting the critical path.
- The need for specific resources such as plant, services or materials and their lead time.
Why is float useful?
Identifying float can be helpful in highlighting where it may be possible to transfer resource to tasks that are on the critical path.
What is a Gantt chart?
An activity / task shown graphically as a bar running horizontally. The preparation of the chart may include a range of basic data spread over columns:
- Activities, according to the order in which they are carried out.
- Budget or cost
- Quantity in its corresponding units
- predicted performance for working equipment.
- Duration of the activity.
How do you monitor progress and programme on site?
- Review the construction programme - planned vs actual.
- Materials on site
- Number of contractors on site.
- Review of the contractors signing in log and review against the proposed numbers in the RAMS.
- Review cash flow forecast - planned vs actual
- confirm specification of materials are being installed as per the manufacturers guidelines.
- Whether you are meeting key milestones
- Design sign off
What happens if an activity on the critical path is in delay?
This is likely to cause a delay to the programme unless it can be re-sequenced but might be unlikely as there would not be any float. It could result in an EOT and claim for L&E depending on the nature of the delay or if it is a fault of the contractor there might be provision for LDs.
Why is it important to regularly monitor progress against programme?
So that risk are identified, and slippage in programme is caught early and delay is mitigated.
What do you mean by a client direct programme?
This was a programme that I put together to demonstrate all of the works that will be carried out by contractors that were appointed directly by the client. These included AV and catering . They were not under appointment by the contractor.
During the exercise of aligning client direct programmes and main construction programme, how did you manage discrepancies and clashes in timings?
I acted as liaison between contractors and coordinated comments on programmes. I held meetings with contractors to ensure timescales were clearly coordinated and the team understood when others would be on site and who the main point of contact was.
How did you manage having multiple contractors on site at the same time?
- I ensured that the main construction took priority in terms of getting work done.
- I ensured the teams were in communication with one another and knew who there site contact was.
- I ensured there was agreement in relation to protection of equipment on site and areas that were off limits to others and lockable rooms etc.
- I ensured all parties knew what works were taking place when and what areas would be available and not available.
- I ensured that all teams were site inducted.
Why were these two particular items client direct and not within the contract?
Mainly as a means to cut out the main contractors overheads and profits and thus lower costs so mainly a cost decision.
However with the AV, the design wasn’t sufficiently progressed enough to move into the main contract at that time in the project.
It also allowed the client to maintain control over these two packages and link with its internal teams (catering and IT).
Why were these items carried out on site during construction and not after construction was complete?
Essentially this was to get ahead of the programme. Although ideally better, if we did it sequentially, the overall project duration would have been delayed.
We therefore agreed early access with the contractor.
Taking into account:
Health and safety and the contract clause 2.5 - early use by the employer.
We obtained consent by the contractor and ensured relevant insurers were notified.
What were the risks of having multiple contractors on site at the same time.
- Security
- Health and Safety
- Logistics
- Disruption to tasks
- Damage
- Blame
- Warranty issues
- Re-do work
What is an EOT?
An extension of time is the mechanism which allow the construction period to be extended where there is a delay that is not the contractor’s fault.