Construction Technology and environmental services Flashcards

1
Q

What are the RIBA Stages?

A
0 – Strategic definition
1 – preparation and brief
2 – Concept design
3 – developed design
4 – technical design
5 – construction
6 – handover 
7 – in use
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What happens at each RIBA Stage?

A

0 – Strategic definition – business case, core requirements, programme
1 – Preparation and brief – programme, budget, feasibility
2 – Concept design – test fit, prelim costs, finalise brief
3 – Developed design – costs, outline tech specs, design programme
4 – Technical design – architectural, structural, M&E, subcontractor design
5 – Construction
6 – Handover
7 – In use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Can you give an example of how elements of building work inter-relate?

A
  • Types of partitioning/acoustics
  • M&E services – types
  • Location of drainage
  • Natural lighting
  • Substructure – All work below underside of screed or lowest floor finishes including the damp-proof membrane. Excavations and foundations. Function is to transfer the load of the building to the ground and isolate it horizontally to the ground. Foundations – shallow- strip, pad, raft, deep – Piles, mini piles, pile walls, diaphragm walls,
  • Superstructure
    Frame: (Steel, portal, concrete, timber) loadbearing framework; Main floor and roof beams; Ties and roof trusses of framed buildings; Casing to stanchions and beams for structural or protective purposes
    Upper floors: Suspended floors, services floors
    Roof, roof structure, roof coverings (Felt and batten, plain tiles, interlocking tiles, slates, flat roofs), roof drainage, rooflights, roof features (canopy, cold roof, flat roof, green roof, long span, pitched, shingle, warm roof).
    Stairs and ramps
    External walls (Rainscreen cladding, masonry, Curtain wall system, timber, metal profile, brick slips
    Windows, doors)
    Internal walls, partitions, balustrades, moveable room dividers,
    Doors, hatches and other openings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the key considerations when reviewing the design of a space?

A
  • Occupancy levels
  • Natural light
  • M&E services (where are they placed, individual controls)
  • Access/ egress
  • Building control compliance
  • Cellular vs open plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the water quality guidelines?

A

• BSRIA – (British Services Research Information Association)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the implications of water outside the guidelines?

A
  • Build-up of pseudomonas in closed water system
  • Occurs in stagnant or low flowing water
  • Clogs the pipe and reduces efficiency
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the rectification process for water outside the guidelines?

A
  • Dosing the system will chemicals
  • Flushing the system
  • Testing for levels of pseudomonas
  • Ongoing maintenance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is high acoustic performance?

A
  • 55- 60db rating – shouting not audible
  • 45db – shouting audible but cannot be distinguished
  • 40db – loud speech faintly audible
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How are acoustics measured?

A

• Using a decibel meter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What advice do acoustic consultants provide?

A
  • Review design/building
  • Advise on acoustics
  • Test post completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How can acoustic performance be specified in the ER’s?

A

• In the performance specifications, the acoustic performance for rooms can be specified

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What happens if the acoustics do not reach the specified performance? How do you check this?

A

Test post completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the Building Regulations documents?

A

The Department for Communities and Local Government publishes guidance called ‘Approved Documents’ on ways to meet building regulations.

These contain:

  • general guidance on the performance expected of materials and building work to comply with the building regulations
  • practical examples and solutions on how to achieve compliance for some of the more common building situations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What enforces building regs?

A
  • Construction Act 1984
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What levels of approval are there?

A
  • Outline – initial docs

- Full plans – review of site on completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What happens if you do not comply with building regulations?

A

Failure to comply with the Building Regulations can result in a fine and/or an enforcement notice requiring rectification of the works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What event has led to a review of the Building Regs?

A

• Grenfell Tower

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are the operation and maintenance post contract?

A
  • On completion set of detailed O&M’s issued

* Includes details of products used, drawings and specs, guarantees and warranties, cleaning instructions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What are the impacts of different design solutions and construction processes on cost and programme?

A
Examples may include:
•  Acoustics – slab to slab, double glazed, cross talk
•	Control of M&E – location of services, 
•	Ceiling types (solid/non)
•	Flooring
•	Location of kitchens/wet services
•	Joinery
•	Cellular offices vs open plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What types of ventilation are there?

A
  • Natural

* Mechanical

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What types of Air con systems are there?

A
  • VRF/VRV – Variable refrigerant flow (water/refrigerant) has highest level of control
  • VAV – Variable air flow – air (no water) - AHU
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What are building regulations?

A

A minimum standard for design, construction and alterations to virtually every building. The regulations are developed by the UK government and approved by Parliament.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Can you name some of the approved documents?

A

Approved documents provide guidance for how each ‘part’ of the building regulations can be complied with when undertaking building work.

Part A – Structure
Part B – Fire Safety
Part F – Ventilation 
Part K – Protection from falling, collision and impact
Part L - Conservation of fuel and power
Part M – Access to and use of building
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Can you describe different types of foundations that you are aware of from your projects?

A

soil. Generally used on most stable subsoil types that are able to distribute loads for small dwelling or light commercial buildings. Formed of mass concreted.

Deep strip foundation – also known as trench fill. Used to reduce labour costs and reduce the risk of damage on heavy clay soils. The trench width usually matches a standard bucket width for the excavator.

Raft foundations – Usually for light structures on subsoils with poor bearing capacity. May need structural steel reinforcement.

Pile foundation – used on weak soils. Only suitable for subsoils that have no large stones and in which the hole does not collapse during excavation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What are HVAC systems?

A

Heating, ventilation and air conditions systems. A system that does any one of those tasks is a HVAC system. The objective of the system is to ensure that an indoor environment is both safe and comfortable for humans. Safety concerns IAQ which should have enough oxygen and be free of noxious gases. Comfort is based on human perception.
Most common AC system has 3 components, a central plan, a distribution system and a rejection unit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What are LTHW and CHW systems?

A

Closed water heating and cooling systems – not domestic systems.

Heating systems to provide ideal thermal comfort conditions under which the occupants can live and work, ensure that the products being used, store or manufactured I the space are protected from the cold, to protect the building fabric from the effects of cold weather.

Closed water systems are carefully designed to create precise and adaptable environmental conditions within buildings or process plant. The design necessitates the use of small bore control and regulating valves. If corrosion debris, installation debris or sludge are present these small orifices may become blocked and the system will not operate to design parameters. The presence of debris will make microbiology control more difficult. Ultimately if systems are not cared for the pipework and fittings may fail prematurely due to corrosion and other contributory factors. Water quality and treatment are therefore very important.

Heating and cooling systems for comfort.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What are the advantages and disadvantages of a steel frame?

A

Advantages:

  1. Strength - higher strength density than timber and concrete therefore heavier. Less steel is necessary to provide the same amount of support as C&T. Knock on advatnages - reduced material shipping costs, reduced labour, simplified design of foundations.
  2. Longevity - lasts longer than steel and concrete.
  3. Versatility - can be fabricated into different shapes but maintaining its strength.
  4. non-combustible so it is not a fire risk.
  5. Fast build times
  6. Can be fabricated off-site

Disadvantages

  1. susceptible to corrosion .
  2. high maintenance costs.
  3. extensive fireproofing costs.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What are the advantages and disadvantages of a concrete frame?

A

Advantages:

  1. costs less than steel
  2. Fire protection as part of the structure.
  3. maintenance is low.
  4. Cladding can be fixed t it and replaced easily.
  5. Good sound and heat insulation.

Disadvantages:

  1. More time consuming.
  2. Edges may not be as square and surfaces not as flat as steel.
  3. Possible need for steel reinforcement.
  4. Heavier so requires larger foundations.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What do you know about Part M of the building regulations/

A

Access to and use of buildings. It requires every building to have provision of easy access to all parts within the building . This also includes facilities of circulation for those who are disabled.

Everybody, including disabled, should be able to access all parts of the building.
Sanitary conveniences should be made available for all.
If there is seating arrangement available in the building for large audiences, there should be reasonable provision made for the seating of disabled people.

Looks at access into the building, around the building.
Stairs, entrances, reception desks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What is a coffered structure?

A

A series of sunken panels in the shape of a square, rectangle or octagon in a ceiling, soffit or vault.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What is thermal mass?

A

Describes the ability of a material to absorb, store and release heat energy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What is night time purging?

A

It can be necessary to provide cooling to building during warm weather, sometimes referred to as comfort cooling. Thermal mass can be used to help cool buildings. night time purging used the thermal mass of a building to absorb heat gains during the day and then cools the mass at night using external air and discharging accumulated heat to the outside so the temperature of the thermal mass is lowered ready for the next day.

the construction of the building needs significant thermal mass. maybe exposed concrete floor slabs or in RCPath’s case, exposes concrete structure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What are the outputs for stage 2?

A
Architectural concept
cost plan
project strategies
outline specs
project brief agreed
programme
planning advice via pre-app
planning application
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

What are the alternatives to the RIBA Plan?

A

I am aware of the APM plan for project management, and learnt about this during the time that I was study for my APMP but I haven’t used it in my experience. concept, definition, development/delivery, closure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

What is DDA?

A

Disability Discrimination Act 2005, however later superseded by Equality Act 2010

36
Q

What is an access statement?

A

Applicant must detail and justify how they have met Part M regulations and what has been put in place e.g. Teapoints solid joinery units at 900mm high (need to be no more than 850mm high) need to have 1500x 1500mm turning space, floor units, no space underneath work surfaces e.g. changing room facilities door in the basement cannot be opened without assistance, so management strategy - have a buddy system in place when these spaces are used

37
Q

What is an approved document?

A
  • An approved document sets out what is generally acceptable as reasonable provisions to meet building control regulations There may be other ways to comply with approved documents , there is no obligation to adopt any particular solution contained in an approved document.
38
Q

What is approved document M?

A
  • Building regulation in England to ensure that people are able to access and use buildings and their facilities. Gives guidance on how to comply with access and use requirements. Requirements 2,3 of Part M are optional requirements.
39
Q

How does Part M interact with other legislation?

A
  • The Workplace (health, safety and welfare) regulations. Equality Act 2010 - the act protects a person with disability from discrimination, harassment of victimisation Disability Discrimination Act - DDA
40
Q

When does Part M apply?

A
  • Where works have been completed, and it has not exceeded the 10 year period that makes provisions of Part M not applicable. When a non-domestic building is newly erected. Where an existing non-domestic is being altered, extended. Where an existing building goes through a material change of use to hotel, shop or public building
41
Q

What do O&Ms contain?

A
  • Contains the information required for the operation, maintenance and decommissioning and demolition of a building.
  • Prepared by the contractor with additional information from the designers and suppliers.
  • Requirements designed in the preliminaries section of the tender documentations
  • A draft version of the document should be provided for the client as part of the handover prior to certifying PC. The document is finalised after PC following final commissioning.
  • Description of the main design principles
  • Details of the building’s construction
  • As-built drawings and specifications
  • Instructions
  • Asset register of plant and equipment
  • Commissioning and testing results
  • Guarantees and warranties and certificates
  • Particular requirements for demolition, decommissioning and disposal
42
Q

What is extract air?

A

Stale air taken out of the space, which can be recycled or exhausted.

43
Q

What is HTHW?

A

High temperature water, water that is kept pressurised in a system that is hotter than 120 degrees C. It is hottest to stop water turning into steam MTHW operates at 90 – 120 degrees.

44
Q

What is infiltration?

A

Due to cracks, gaps or leaks where air from the outside leaks is due to wind or changes in temperature.

45
Q

What is VRF/ VRV?

A

Variable Refrigerant Flow, Volume Heat Recovery (2 pipe system) – Good for large spaces with separate rooms and meeting rooms because the system can dispense heat and cooling simultaneously. Gas and liquid heat pumping (3 pipe system) – Supply only heat or cooling to space (more popular), heating pipe, cooling pipe and return pipe.

Variable Refrigerant Flow, Volume Heat Recovery (2 pipe system) - Good for large spaces with separate rooms and meeting rooms because the system can dispense heat and cooling simultaneously, Gas and liquid Heat Pumping (3 pipe system)- Supply only heat or cooling to space (more popular), heating pipe, cooling pipe and return pipe

46
Q

How does VRF/ VRV work?

A

User controls the setting they desire locally from the site, this sends a note to the outdoor unit and examines the outdoor conditions, system adjusts itself to meet desire indoor requirements, automatic and adjusts constantly. Uses a refrigerant for heating and cooling. Can operate at different speeds providing better user control, the refrigerant is conditioned by an outdoor condensing unit and is distributed through multiple fan units. Disadvantages - higher upfront cost

47
Q

What is ventilation?

A

The supply of fresh air into a space.

48
Q

Where is boiler plant often located?

A

Basement or GF plant room.

49
Q

Where is the AHU and refrigerant plant normally located?

A

High level roof to ensure clean fresh air supply.

50
Q

Where might you find radiator systems?

A

Generally in naturally ventilated buildings. They are often located on the perimeter of room to offset cold drafts from windows and prevent condensation forming on glass

51
Q

What is M&E?

A

M&E are mechanical and electrical services which essentially are required in order to make a building work for the needs of its occupants - Mechanical can provide Heating, cooling, Air conditioning. Electrical can supply power supply and distribution, telecommunications,

52
Q

What is FCU (2 pipe or 4 pipe)?

A

Fan Coil Unit - term for a unit that can disperse both heating and cooling.
Unit Can be wall mounted, free standing or ceiling mounted.
2 pipe - 1 return 1 supply,
4 pipe 2 return 2 supply (more flexible can be heated and cooled at the same time).
FCUs contain a filter that cleans air supply, versatile in terms of space and layout, can require more maintenance, Locally controlled through thermostat, when temp of room reaches a certain temp signal sent to valve, valve automatically opens and closes to regulate CHW, LTHW to the FCU to provide the correct cooling to the circulated air. Flexible control for individual rooms.
Controls heating and cooling of the space, not supply fresh air, AHU supplies fresh air FCUs use chiller and boilers to determine temp of water in the system

53
Q

What are AHUs?

A

Air handling units – A device used to regulate and circulate air as part of a HVAC system. Usually a large metal box containing a blower, heating or cooling elements, filter racks or chambers, sound attenuators and dampers.

54
Q

What are chilled beams?

A

Chilled beams are a type of HVAC system which uses convection (The transfer of heat by the movement of a fluid (liquid or gas) between areas of different temperature) to heat or cool a space. Better at cooling than heating. Pipes of water are passed through a beam either integrated into the ceiling system as the beam chills the air around it, the cold air is more dense and falls to the bottom and is replaced by warmer air which rises lower operating costs.

55
Q

What is BIM?

A

BIM is widely used as the acronym for Building Information Modelling, defined as digital representation of physical and functional characteristics of a facility creating a shared knowledge resource for information about it and forming a reliable basis for decisions during its life cycle, from earliest conception to demolition.

56
Q

What is the purpose of earthing?

A

To prevent electric shocks when in contact with live wires, or indirectly when an object becomes live anything above 5mA is dangerous - but all shocks should be avoided.

57
Q

What is used to protect against electrocution?

A

Trunking, containment, metal casings.

58
Q

What is UPS?

A

Uninterrupted power supply, in the event the mains power fails it provides a back up for emergency services e.g. computers, fire detection, emergency lighting.

59
Q

How does a building get power?

A

Depends on how big the building is, you get power from the utility company which comes through a transformer than steps down the high voltage, then there is a meter which assesses power usage, then they might be a switchgear which distributes power safely through bus/feeder that take it up to the building, taken to a branch panels and you might get bus bar underfloor or trunking on each floor.

60
Q

What is a switchgear?

A

Switching equipment used in the transmission of electricity used to control, protect and isolate electrical equipment. In an electric power system, switchgear is composed of electrical disconnect switches, fuses or circuit breakers used to control, protect and isolate electrical equipment. Switchgear is used both to de-energize equipment to allow work to be done and to clear faults downstream.

61
Q

What is a comms room?

A

A server room that holds communication and network devices. Might have routers, switches, firewalls, computers, servers, storage devices, database servers. Needs A/C, temperature, security, antistatic flooring

62
Q

What kinds of cable management are there?

A

Trunking, cable tray, cable baskets.

63
Q

What is exhaust air?

A

Air removed into the atmosphere

64
Q

What is a false ceiling?

A

Suspended ceiling that allows access to high level services

65
Q

What is superstructure?

A

All internal and external structure above the substructure.

66
Q

What is the substructure?

A

All structure below the superstructure.

67
Q

What is a foundation?

A

Function is to safely sustain and transmit to the ground on which it rests the combined dead, imposed and wind loads of the structure.

68
Q

Name 4 different types of foundations

A
  • Strip
  • Pad
  • Raft
  • Pile
69
Q

What are the different types of piles?

A
  • Sheet piles
  • Secant piles
  • Bored piles
70
Q

What is underpinning?

A

Where the foundations of an existing building or structure requires strengthening and stabilising, a process of underpinning may be necessary. Excavated soil from beneath existing foundations is replaced with material, usually concrete, in a series of phases that increases the overall depth. This founds a new foundation beneath the existing one.

71
Q

What are the types of excavation?

A

Open
Perimeter trench excavation
Complete excavation

72
Q

What is a retained facade?

A

The facade of the building is retained whilst everything behind the front wall is demolished.

73
Q

What is a portal frame?

A

characterised by a beam and supported by columns either end. commonly used to create widespan enclosures such as warehouses.
The joints between the columns and beam are rigid.

74
Q

What is formwork?

A

Anything that holds fresh in-situ concrete in place until it hardens, such as plywood shutters, steel pan forms.

75
Q

What is the size of a brick?

A

standard bricks are 215mm x 102.5mm x 65mm

76
Q

how many bricks are in a m2?

A

60 per m2.

77
Q

What is pointing?

A

External part of the mortar joints in masonry construction.

78
Q

What is rain screen cladding?

A

it is cladding that manages the flow of rainwater on a building

not waterproof itself but serves as a screen.

79
Q

What are the factors that might affect the choice of materials for internal partitions?

A
fire rating requirements 
restrictions on noise
visually
fixed of movable
strength.
80
Q

What is the function of floor screed?

A

A screed is a layer of material laid in situ, directly onto a base, for one or more of the following purposes: obtain a defined level and to carry the final flooring.

81
Q

What are sheet piles?

A

A deep trench is excavated and concrete is poured in situ. the piles can be used to form basement walls or act as a retaining wall.

82
Q

What are secant piles?

A

Interlocking piles are bored to provide a combination of foundations and basement walls. They go someway in providing a waterproof structure.

83
Q

What are bored piles?

A

An auger is used to excavate the soil and then concrete is poured in once complete. A variation of this is continuous flight augered where the piles are bored and is the quietest form of piling an dis a fast and very economical technique.

84
Q

What is pre-cast piles

A

Brought to site and hammered into the ground.

85
Q

What are MMC?

A

Centres around off site construction techniques that can benefit from factory conditions and mass production techniques.