Commercial management of construction Flashcards
What are the different aspects that make up the commercials on a construction project?
Provisional sums Preliminaries Build costs Variations L&E
What are preliminaries?
May appear in the tender documents. Items do not form part or the works but are required by the method and circumstances of the works. They might include, method statements, PCI, approvals, testing and completion. They describe what is required to complete the works required by the contractor.
Site prelims include: welfare, offices, plant, waste clearance, water, electricity, protective clothing, site transport.
What is a contractor cashflow and what should you do if the contractor is invoicing less than its cashflow?
Ideally I would want to see a contractor invoicing against it forecast. If it was invoicing less, it may raise red flags i.e. is there a programme delay or an issue with procurement or manufacture. There may be a legitimate reason for this, such as resequencing but it should always be investigated.
What does a development budget include that a drawdown will not?
The client’s total budget for the entire project – which is useful to deem whether the project is viable and profitable:
- Construction cost
- Land and property acquisition costs
- Approval fees
- Planning costs – S106 and CIL
- Financing costs
- Site investigations
- FFE
- Moving staff
- Insurance
- Consultant fees
- Inflation
- Contingency
- VAT
What is contingency?
Allowance for unknown risks and risks becoming issues.
- Contingencies are downside risk estimates that make allowance for the unknown risks associated with a project.
- Sometimes based on a percentage
- Adverse weather, unforeseen circumstances, disputes, supplier failure, variations, unexpected site conditions
What makes up the costs of the project to the contractor?
- Preliminaries
- Build costs
- Contingency for unknowns costs
- Provisional sums
- OH&P
- Inflation
- Pricing schedule
What effect does the design and construction processes have on costs:
- Changes to ERS
- Design development
- Increased costs
- Material selection
- Techniques for construction
- Quality
- Availability
What techniques are used to reconcile the costs against income:
- Cost value reconciliation
- Monitor and measure expenditure and budgets
- Cashflows or tracking
- Actual costs v budget/ value of works - variations
What is a cashflow?
A forecast of payment and a tracker shower actual receipts and expenditure.
What is a valuation?
- Guidance note is - Interim valuations and payment 1st edition August 2015
- Process by which the QS arrives at the value. Normally involves visiting site and checking that the work has been carried out by visual inspection and or measurement.
- Must be realistic – too low creates unreasonable financial problems for the contractor. Too high, creates a risk to the employer of paying sums for which he or she obtains no benefit.
- Interim payments up to practical completion
- Interim application – contractor submits payment application to the QS not less than seven days before the ‘due date’
What is the payment timeline?
I’m more familiar with the payment timeline for the D&B 2011 contract and this was outlined as follows:
- Contractor submits its application for payment on or before the due date. Work is to be valued up to the due date only.
- QS values the works and makes it recommendation.
- 5 calendar days after the due date, the employer’s agent is to issue its certification.
- If a pay less notice is to be issued, the latest date will be 5 days prior to the final date of payment.
- Payment to be made by the final date for payment.
- From receipt of the contractors application, there is a 14 days turnaround time for the final date of payment.
When is retention released?
- 50% at PC
2. 50% are the end of defects liability period - usually 12 months but will be outlined in the contract.
What is the process for releasing the final retention monies?
- Final inspection
- Final payment certificate
- Defects list – Defects must be made good in a reasonable time
- Once all items have been made good, a Certificate of Making Good Defects can be issued with the final certificate to release the retention.
What is the final account?
The final figure of the construction works. It is the contract sum, plus or minus any adjustment made from variations.
What is a preamble?
- Explanation of a document.
- Help to interpret the document.
- Tendering procedures, negotiations, objectives, quality
What are build costs?
- Those costs incurred by the actual construction works themselves.