Contract Practice Flashcards
What are the different forms of standard building contract available in the UK?
JCT
NEC
FIDIC
Where are the different contract suits commonly used?
- JCT – most commonly used
- NEC – more suited to engineering contracts
- FIDIC – more suited to large international project e.g. Channel Tunnel
What is the JCT and what are their suite of contracts?
Joint Contracts Tribunal, formed in 1931 Suit of Contracts includes: • Standard (with quants, without, with approx.) • Intermediate • Minor works • Design and Build
What are the advantages with a standard form of contract? How is it formed?
The advantages of a Standard Building Contract include:
• Developed over a long period
• Has input from legal, client, contractor, local authority
• Has more case law
• Less costly and time consuming to produce than a bespoke contract.
• Guidance notes available
What is an intermediate Contract?
- Contract for simple works without any major complex service adjustments
- It is a form of traditional procurement
- Design must be in place
- Can have sectional completion
What is included in a payment notice?
- Date
- Issue number
- Contract sum
- Valuation sum
- Valuation sum minus retention
- Valuation sum minus amount previously certified
What are the timelines for payment? Where can this information be found?
- Interim valuation/applications date is stipulated in the contract, and is same day each month (or nearest business day).
- This is outlined in section 4 of the contract particulars
- Contractor can submit their application, is 7 days to review.
- CA/EA has 5 days from the due date to issue payment notice/cert.
- Employer has 14 days from the due date to issue payment.
- Payment timelines are outlined in Section 4 of the Conditions (4.9)
What is Practical Completion? What does it Trigger?
• When all works in the contract have been deemed to be completed and the client can take occupation.
- The point at which a building project is complete, except for minor/ de minimis defects that can be put right without undue interference or disturbance to an occupier.
- The contractor has complied with clauses 2.37 and 3.16
• It releases half of the retention
• Ends the contractor’s liability for LD’s
• Starts the defects liability period
- The client to carry out its own FRA.
What documentation is required at PC?
- Testing and commission certs
- Health and safety files
- Building control sign off
- O&M’s
- Clients insurance in place
What is sectional completion and what is partial possession?
- Sectional completion is defined in the contract
- Partial possession is not determined in the contract, and is up to the contractors discretion to grant.
- Both will mean that section is ‘practically complete’
- LD’s will cease for that period.
- Contractors decide whether to grant partial possession.
What are staged payments?
- OPTION A in the contract
- Pre-agreed stages defined in the contract particulars – milestones in the project
- On completion of the stage, payment is awarded.
What is the interim payment process? Where is this specified in the contract?
- OPTION B
- Payment at agreed specific dates throughout the project, usually on a monthly basis.
- This is outlined in the contract particulars and timings in section 4 of the contract conditions.
What guidance documents are available?
- RICS – Appropriate Contract Selection
* JCT – Guide to selecting the appropriate JCT
What is the difference between an Employers Agent and a Contract Administrator?
- CA = Standard form/ traditional of contract. Role only takes place when in contract. Administer the contract impartially.
- EA = D&B role takes place before contract.
What is a material/non-material breach?
- Material – serious breach. End contract
* Non-material – claim damages
What is the Housing, Grants and Regeneration Act?
- Ensure payments are mad promptly
* Any project over 45 days must have interim payments
What did the update to the Housing grants and regeneration act include?
- Dates for payment must be included in the contract
* If client fails to issue payment notice, contractor can issue default payment notice. (ISG vs Ceevic college)
What contract suite do you have experience in?
The JCT Suite, mainly D&B.
What do you know about NEC?
Both another form of contracts to choose from but I do not have experience in these.
NEC:
- Written in simple language.
Defects correction period is 2 – 3 weeks
- There is no QS.
- There are no provisional sums
- There are options for target cost contracts
- The programme is a contractual document
- Payment is located in three separate sections of the contract as opposed to JCT where it is all found in one - clause 4.
JCT deals with time and money separately with EOTs whereas NEC will deal with both time and money.
What does NEC stand for?
New Engineering contract
What is an EA?
- JCT D&B contract
- EA represents the client on all matters
- Role can commence at appointment rather than when the building contract starts.
What is a CA?
- JCT Traditional contract
- Solely responsible for administering the contract.
- An impartial role
- Commences when the building contract commences.
What is an interim valuation?
The payment process at interim stage of the project, set out at clause 4.7 and the contract particulars refer.
What are the payment timescales for a D&B contract?
This depends on whether you have opted for alternative A or B.
Alternative B is periodic payments, monthly.
- Contractor makes an interim application (7 days prior to due date)
- QS makes its recommendation within 2 days of the due date.
- +5 days of the due date for the payment notice by EA
- Pay Less Notice if applicable (no later than 5 days prior to final date for payment)
- Final date for payment of an interim payment is 14 days from its due date.