PMP Formulas Flashcards

1
Q

AC (Actual Cost)

A

ACWP (Actual Cost of Work Performed)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Definitive Estimate?

A

-5% to +10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Variance (= s2))?

A

Variance = ((P-O)/6)^2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Internal Rate of Return (IRR)?

A

Net Investment / Avg. Annual Cash Flow.

Higher is better. Also called Hurdle Rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Expected Monetary Value?

A

Probability * Impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Performance Index (SPI)?

A

SPI = EV / PV

Less than 1 is behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Budget Estimate?

A

-10% to +25%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Communication Channel?

A

n(n-1)/2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Working Capital?

A

Current Assets - Current Liabilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

% Communication of a PM?

A

90%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Benefit Cost Ratio?

A

Benefit / Cost
(Higher is better, >1 has benefit)
Exam can call it Cost-Benefit Ratio, where lower is better.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

PERT Mean Estimate?

A
PERT=(P+4m+O)/6
3 estimates for each task:
. P: Pessimistic
. M: Most Likely
. O: Optimistic
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Return on Assets (ROA)?

A

NEBT / Total Assets
OR
NEAT / Totals Assets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Sigma (o)?

A
1o = 68.27%
2o = 95.45%
3o = 99.73%
6o = 99.99985%
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Rough Order of Magnitude (ROM)?

A

-25% to +75%

-50 to +100%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Arrow Diagramming Method (ADM)?

A

Also called Activity on Arrow (AOA)
Only 1 relationship: F-S
Can have “dummies”
Can analyze using either Three-Point Estimates or CPM

17
Q

Scheduled Variance (SV)?

A

SV = EV - PV

Minus is behind schedule

18
Q

GERT?

A

Allows loops and repetitive activities

19
Q

Expected Monetary Value?

A

Probability * Impact

20
Q

Variance at Completion (VAR)?

A

VAC = BAC - EAC

21
Q

Budgeted Estimate?

A

-10% to +25%

22
Q

To Complete Performance Index (TCPI)?

A

TCPI = (BAC - EV) / (BAC - AC)
Values for the TCPI index of less then 1.0 is good because it indicates the efficiency to complete as less than planned. How efficient must the project team be to complete the remaining work with the remaining money.

23
Q

ROI (Return on Investment)?

A

ROI = Earnings

Investment / Higher ROI is better

24
Q

Payback period?

A

Time to recover cost of the project.

Lower payback period is better.

25
Q

Cost Variance (CV)?

A

CV = EV - AC

Minus is over budget.

26
Q

Point of Total Assumption (PTA)?

A

((Ceiling Price - Target Price)/buyer’s Share Ratio) + Target Cost

27
Q

Standard Deviation (=s)?

A
Deviation = (P-O)/6
3 estimates for each task:
P: Pessimistic
M: Most Likely
O: Optimistic
28
Q

Estimate at Completion (EAC)?

A
EAC = BAC/CPI
Same rate of spending.
EAC = AC+ETC
Use when Initial Estimates are flawed
EAC = AC+(BAC-EV)
Use when future variances are atypical.
EAC = AC +[(BAC-EV)/CPI]
Use when future variances are typical.
29
Q

Present Value?

A
PV=FV/{1+R]^n
Higher is better.
FV=Future Value
R=Interest Rate
n=number of time periods
30
Q

Discounted Cash Flow?

A

Cash Flow X Discount Factor

31
Q

Return on Sales (ROS)?

A

Net Income Before Taxes (NEBT)/Total Sales
OR
Net Income After Taxes (NEAT)/Total Sales

32
Q

Contract Related Formulas?

A

Savings = Target Cost - Actual Cost
Bonus = Savings * Percentage
Contract Cost = Bonus + Fees
Total Cost = Actual Cost + Contract Cost

33
Q

Working Capital?

A

Current Assets - Current Liabilities

34
Q

Cash Flow?

A

Cash Flow = Cash In - Cash Out

35
Q

Slack or Float?

A
LS - ES: Calculates slack with forward pass
Total Float (also called Slack, Float, or Project Float) is the total amount of time an activity can be delayed without delaying the project finish date.
LF - EF: Calculates slack with backwards pass.
Free Float Slack is the amount of time an activity can be delayed without its successor (following activity).
36
Q

Cost Performance Index (CPI)?

A

CPI = EV / AC

Less than 1 is over budget

37
Q

Precedence Diagramming Method (PDM)?

A

Also called Activity on Node (AON): Activities are in the boxes, arrows show the relationship.
Most commonly used today.
Has 4 relationships: F-S, S-S, F-F, S-F
No “dummies” (zero duration dependencies) allowed.
Can analyze using either Three-Point Estimates or CPM

38
Q

PV (Planned Value)?

A

BCWS (Budgeted Cost of Work Scheduled)