PMP Definitions Flashcards
The agreement to be able to assign project resources, make project decisions, and spend project funding
Authority
The process of accumulating, finishing, and interpreting information to achieve completion of a phase or project
Administrative Closure
The process of formally receiving the work of the project: the work should be complete and fulfill the needs for which it was created.
Acceptance
A piece of the project that must be completed (performed); sometimes called a “task”; can be divided into smaller pieces; typically has an assigned resource, cost amount, and expected duration
Activity
Represents the total costs that have actually been accrued up to a particular point in time; also known as actual cost of work performed
Actual Cost (AC
The comparison of a current product to industry standards or past standards to attain a measurement or baseline
Benchmarking
The process of determining the availability of human resources and amassing the team needed to complete the project
Acquire Project Team
A document created to define the project communication needs based on stakeholder needs
Communications Management Plan
A data-generating technique which includes team members or subject matter experts for the purpose of solving project problems, identifying project risk, and planning-related activities
Brainstorming
The process of managing the relationship between buyer and seller
Administer Procurements
A standard established by a company
Company Policy
Activities during which formal acceptance and completion procedures are attained from either a phase or the project itself
Closing Processes
A request for a change on a project that has been approved via formal or informal change request
Approved Change Request (Output/Input)
Requirements that are defined to be completed before the work can be accepted
Acceptance Criteria
A detailed list of activities that project team members use to know what work on the project they are responsible for completing
Activity List (Output/Input)
Process of using a previous project of similar characteristic (size, cost, scope) to estimate a new project
Analogous Estimates (Technique)
A role with a negative attitude toward the project
Aggressors
Tools and techniques used to create the foundation for information transfer on a project
Communications Infrastructure
Compensation in the planning for unknown items that could occur; typically schedule- or cost-related. Sometimes called reserve
Buffer
A formal document showing the hierarchy of components or pieces and their sub-components or sub-pieces that make up the product
Bill of Materials (BOM
The act of not providing certain confidential information to those who should not know about it
Confidentiality
A team-building technique in which team members are located together or as close to each other as possible
Co-location
An educated, logical guess about a variable when its details are unknown on a project or program
Assumption
Diagram that sorts and groups large numbers of brainstorming ideas for review and analysis
Affinity Diagram
A network diagramming method in which activities are shown on arrows and connected at nodes to show the sequence of activities. Also known as ADM, AOL
Activity-on-arrow (AOA)
Estimate/plan that the project tries to achieve (cost, scope, time, etc.)
Baseline
A predictable source of variation in a system
Common Cause
Deliver needed project information to stakeholders in an appropriate timeframe
Distribute Information
Compensation in the planning for unknown items that could occur; typically schedule- or cost-related; also commonly called buffer
Contingency Allowance
A type of power that can involve using a middle person to negotiate for the Project Manager
Attitude Power
A situation in which an individual or company engages in behavior that is inappropriate, but not necessarily illegal (it could be illegal)
Conflict of Interest
Analyze variances between actual performance and planned performance to effect improvements
Control
A technique to determine if the project assumptions are accurate, consistent, and complete and, if not, the resultant risks to the project
Assumption Analysis
An approach in which a previous project of similar characteristic is used to obtain the values (duration, resources, budget, etc.) for the current project being planned
Analogy Approach
A network diagramming method in which activities are shown on the boxes or circles of the network diagram and connected via arrows. Also known as PDM
Activity-on-node (AON)
A detailed estimating approach that usually involves team input - As the team builds the pieces of the estimate, they build the total estimate from the bottom up.
Bottom-Up Estimating
Creation and delivery of a product that has met the specified requirements and conformance (or functionality) of use
Conformance
A role that interrupts information flow on the project
Blockers
A report that includes significant variations from the planned activities
Exception Report
Pre-established actions that the team executes if a known risk event occurs on the project
Contingency Plans
A demand for consideration, under the terms of a contract, by a buyer from a seller or by a seller from a buyer
Claim
The process that protects the ownership rights of writing, songs, and other “creative” works; can include software, music, physical and electronic media.
Copyright
Standards to which project variables are compared for acceptability
Criteria
The formal or informal process of reviewing changes associated with a project; will result in approval or rejection of changes
Change Control
An approach in which the team or at least the Project Manager is involved in deciding on and estimating the individual pieces of the project to create the summary estimate
Bottom-up Approach
A network diagramming method that calculates the late start (LS) and late finish (LF) dates for each activity
Backward Pass
The total amount of money expected to be spent on a project based on the original cost estimates plus any approved changes
Budget
The point where the project and product meet the standards of the written specifications defined at project inception (or modified through change control)
Conformance to Requirement
A role that helps focus on making sure people on the project understand what the details of the project entail
Clarifiers
Estimates related to future project performance that are based on historical information and current project knowledge
Forecasts
Reserves that can help mitigate schedule or cost issues (risk), in the case of changes with the scope or quality on the project
Contingency Reserves (Output/Input)
The process of completing the contract; includes settlement on any open items
Close Procurements
The standards we use to determine what is right and wrong; varies for everyone
Ethics
The individual, group, or company that will own the work of the project when it is complete
Customer
A group of people formally recognized to approve or reject requested changes on a project
Change Control Board (CCB)
A technique used with groups to generate a large number of ideas
Brainstorming