Level 3 Flashcards

1
Q

What is an advanced payment bond?

A

A surety product that protects money being advanced to a contractor at the start of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What type of bond is an advanced payment bond?

A

On-demand bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why did you not do this under a letter of intent?

A

The value of the advanced payment bond was £2.5m as it was to order steel. This was viewed as high risk to be simply provided within a LOI.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why choose an advanced payment bond?

A
  • Facilitates material order before work started
  • Protects the client in terms of insolvency
  • Money is guaranteed by a surety that has met underwriting scrutiny
  • Steel will be cut and delivered months from the order is placed and helps the initial cashflow
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Can you explain how an advanced payment bond works?

A
  • Bond put in place at the start of the contract
  • Customer pays in advance
  • Customer deducts their advanced payment from valuations until full balance has been attributed to the contract.
  • Things go wrong customer can claim their advanced payment from the Surety provider less deductions for products or services that have been delivered and deducted from the advance payment sum.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why was the contractor unaware of the repayments?

A

The contractor had assumed there were different payment terms and ultimately I believe they did not read the contract or understand it when it was agreed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What risks were there with changing the payment dates?

A
  • Risk that if they didn’t the contractor would default
  • Negative cashflow might mean programme issues
  • Payment can be made when valuations are higher.
  • Overall payback period (6 months remained)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why were they unable to complete TWS on time?

A
  • Late procurement of the racking system
  • Ultimately delayed testing and commissioning
  • Unable to use warehouse solely for racking
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What do you need to get liquidated damages?

A
  • Non completion Notice
  • Notice employer may require of payment of or withhold LAD’s (before due date of final payment)
  • Notice demanding payment of or withhold LAD’s (5 days before final payment)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What was the change control procedure in the PEP?

A
  • Changes needed to come to PM team
  • PM would review programme implications
  • QS would review cost implications
  • External consultation included
  • Explained to the client and agreed before decision.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What lessons did you learn on Pixham Lane?

A
  • Some design periods were too ambitious
  • Fees and accurate budgeting
  • Over attendance at meetings
  • Same client, learnt time length of internal processes and approval procedure
  • Unclear sustainability strategy from the client / funder
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How did you establish a scope of services for the Interior Designer?

A
  • Review of current layout and recommendations
  • Areas of design
  • Outline expected drawings (developed with architect)
  • Meeting and presentation allowance
  • Finishes and FF&E schedule to allow costing
  • Requirements post-tender and during construction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Key Differences between single stage and negotiated tender?

A
  • No competitive tender period on full design
  • Faster start on site
  • Negotiation period instead of tender return
  • Design continuity throughout, not stopping for the tender period
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is an appointment?

A

Client formally engages the consultant to carry out services in compliance with the terms within the appointment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a Standard of Care?

A
  • Degree of care / caution a professional must exercise when undertaking its services
  • Designer has to provide ‘reasonable skill and care’
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Statutory Requirements?

A
  • Consultant obliged to comply with all statutory requirements
  • Aware of all relevant legislation
17
Q

Fee

A

Establishes how much fee is paid or calculated

18
Q

Types of Limitations of liability?

A
  • Aggregate cap on liability
  • Net contribution cluase
19
Q

Aggregate cap on liability

A
  • Sets a cap of the amount a client can claim on someone’s PII. This PII may be higher than the cap and therefore the client doesn’t get full access to the claim if it is over the cap level.
20
Q

PII

A

Covers consultant against liability arising from errors in providing a professional service.

21
Q

What are the differences between a long and short form appointment?

A
  • Long form includes a DRM as it is looking to be a complete document for the entire project.
  • Long form is likely to include novation wording and a deed of novation appended
  • Typically higher value more design intensive appointments for entire project duration
22
Q

What are the key items included within an appointment?

A

Standard of Care
Statutory Requirements
Limitations of Liability
Termination
Fee and Payment
Schedules

23
Q

What are the key items within a JCT contract?

A

Articles
Contract Particulars
Sections
Schedules