3 - Programming and Planning Flashcards

1
Q

What is the difference between Total and Free Float?

A
  • Total float is the amount of time an activity can be delayed before affecting the end date
  • Free float is the amount of time an activity can be delayed before affected a subsequent activity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the Critical Path?

A
  • A technique defining the sequence of activities determining overall programme duration. The shortest possible route from the programme start to finish.
  • There is no float on the CP
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Explain Earned Value

A

Earned Value looks at the value earned by the project by a point in time. Two key metrics are the Schedule Performance Index and the Cost Performance Index (SPI and CPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Explain the SPI calculation

A
  • Earned Value divided by Planned Value e.g.

100m wall, £1,000 per metre, 100 days duration. At day 10 there is 20m of wall complete.

20 divided by 10 = 2.

Greater than 1.0 is good, less is bad.

Can then apply this factor to the end date to get a forecast completion date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Explain the CPI calculation

A
  • Earned Value divided by Actual Cost e.g.

100m wall, £1,000 per metre, 100 days duration. At day 10 there is 5m of wall complete, but it’s cost £10,000:

5000 divided by 10,000 = 0.5

Greater than 1.0 is good, less is bad

Divided the total cost by 0.5 to get EAC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What kinds of Delay analysis are you aware of?

A

Split in to two key camps: proactive and retrospective.

  • Time impact analysis - do it as you go. Drop in the change.
  • Time Slice Window - Retrospectively split your programme in to time windows and drop in the impact sequentially. Effectively a retrospective NEC approach.
  • Collapsed As Built - Take the as-built and subtract the delay out of it

All require good records and programme data..

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How do you create a programme?

A
  • Scope of programme
  • WBS
  • Plug in constraints
  • Fill in what I know
  • Consult wider team
  • Add risk and opportunity
  • Run analysis of scenarios
  • Identify the CP
  • Identify assumptions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How can you show progress on a programme?

A
  • Drop line
  • % Complete metrics
  • Jagged drop line
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is time at large?

A

When there is no completion date or where completion date has become invalid following there being no clause covering the relevant event.

Removes obligation to pay LADs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are some alternatives to a Gantt Chart?

A
  • Network Diagrams
  • WBS
  • Kanban board/task list
  • Sprint cycles
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the difference between resource levelling and resource smoothing?

A

Both are used to avoid peaks and troughs, but:

Levelling = when resources are constrained, what is the programme going to be?

Smoothing = when time is constrained, can resources be smoothed out to achieve the end date? I.e. delay some tasks to get the CP done.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can you explain a time where the programme was impacted?

A

Change in use from residential to commercial.
Needed to programme the implications by liaising with consultants.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a gantt chart

A

A chart showing series of horizontal lines detailing the different work activities and their corresponding time periods to complete a particular objective.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Milestone Definition

A

A significant stage or step in achieving a particular outcome that has zero duration.

On Stapleford I programmed key milestones at the end of each RIBA Stage and the issuing of the Stage reports. Requirement for the funder to review.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a jagged drop line programme?

A

A programme showing progress as a percentage of work completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a straight drop line programme?

A

A vertical line drawn on the current date to indicate progress.

17
Q

What is a concurrent delay?

A

Two or more delays caused by different parties occurring independently of each other but in the same period.

18
Q

What is acceleration?

A

Completing the works in a shorter period of time than outlined in the contract.

19
Q

Can you give some acceleration examples?

A

Resequencing works
Working longer hours / weekends
Increasing labour / plant
Alternative forms of construction
Changing the design or specification
Reducing scope of the works

20
Q

What is a S73 Application

A

Minor Material Amendment - Allows you to remove or vary a planning condition

21
Q

What is a S278 Application

A

An agreement with the Council and Highways to make permanent alterations or improvement to the public highway

22
Q

What are S106 Agreements

A

Agreements with the council that are connected to the planning conditions

23
Q

What is a network diagram

A
  • Helps visualise the activities required to complete a task.
  • Series of nodes showing earliest start/finish and latest start/finish which creates dependencies between.
24
Q

What are the types of float?

A

Terminal Float
Total Float
Free Float

25
Q

What is the NPPF?

A

Sets the Gov’s economic, environmental and social planning policies. Apply to the preparation of local and neighbourhood plans and to decisions on planning applications.

26
Q

What are approved inspectors?

A

A body of people that inspector and monitor developments

27
Q

Whata re the four main types of planning permissions

A

Full application
Householder application
Outline application
Reserved matters - this follows outline

28
Q

What is project governance?

A

Set of policies procedures functions and responsibilities that define the establishment management and control of projects

29
Q

Difference between programme and project planning?

A

Project - Define dates and key deliverables
Programme - Undertaken on a larger scale and may comprise of several project, strategic vision or end goals

30
Q

What is the benefit of aligning resource to programme?

A

Allows activities that are under resourced to be spotted

31
Q

What is buildability?

A

How easy something is to physically build

32
Q

What are MMC’s?

A

Modern Methods of Construction
- Term to describe new technologies thaty improve speed quality and reliability on site. Bathroom pods, pre-cast concrete / piles etc

33
Q

What is terminal float?

A

Difference between planning completion and contract completion.

34
Q

What is a Section 96a?

A

A non-material amendment