2 - Project Finance Flashcards

1
Q

What are the different types of Cost Report?

A

1) Elemental
2) Construction
3) Project
4) Programme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Explain an S-Curve

A
  • Plots COWD against time
  • As you go through the project, an S-Curve is formed
  • Can analyse project performance by reviewing if you are in front of or behind the curve
  • HOWEVER - It can mean that maybe the costs were front loaded, or that the works are over-priced.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Cost Control?

A

The processes and procedures to align and manage cost in line with the Cost Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a Cost Plan?

A

The overarching plan of the project costs over time. An evolving document that grows in accuracy and scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What informs the early stages of a cost plan?

A
  • Initial appraisal through feasibility study
  • BCIS / Index amounts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What informs the middle stage of a cost plan?

A
  • PTE
  • Quants taken from design
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What informs the final stages of a cost plan?

A
  • CSA and Contract Sum

- Final account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Under NEC, what is Defined Cost?

A

The costs permitted under the Contract that are incurred/expended by the Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the Schedule of Cost Components?

A

List of categories of Defined Costs that form the total of the prices setting out what the contractor will be paid for and how that is calculated. These are:

  1. People
  2. Equipment
  3. Plant and materials
  4. Charges
  5. Manufacture
  6. Design
  7. Insurance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are Disallowed costs?

A

Costs that are incurred by the Contractor that they are not entitled to payment such as:

  • Amounts not justified by records
  • Amounts paid for something else not part of the project
  • Errors or mistakes in payment to others
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What cost measurement methods are there?

A
  • NRM1 - Order of cost planning for building works
  • NRM2 - Detailed measurement of buildings works
  • NRM3 - Order of cost and measurement of Maintenance Works
  • ICMS - International Construction Measurement Standards
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What was the Standard Method of Measurement replaced by?

A

NRM2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is an Outturn cost and what affects it?

A

Actual construction cost

Fixed costs - The works undertaken

Variable - Changes, prov sums etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the Price of Work Done to Date?

A

Defined cost the contractor will have spent before the next assessment date, which includes CEs, plus their fee

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a provisional sum?

A

An allowance or estimate included within the contract price.

This is not sufficiently defined, designed or detailed and may not be work the employer wants to carry out.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How does NEC deal with provisional sums?

A

They do not provide for provisional sums as if the scope is unclear the item should be excluded until it can be defined.

17
Q

What is a defined provisional sum?

A

Described in sufficient detail for the contractor to make an allowance for them in their programme, planning and preliminaries.

18
Q

What is an undefined provisional sum?

A

The contractor does not allow for programming and preliminaries. Contractor may be entitled to EOT or additional prelims when the works are underktaen.

19
Q

What are some pricing options within contracts?

A

Bill of Quantities
Lump-sum
Remeasurement
Target Cost
Guaranteed maximum price

20
Q

What is a lump sum contract?

A

Provides a payment for a set amount. It has been determined by a contractor by estimating their cost to provide the work.

21
Q

What is a remeasurement contract?

A

Work carried out on pre agreed unit rates

22
Q

What is a target price contract?

A

Target price is set and any cost savings are shared between the contractor and employer.

23
Q

What is a guaranteed maximum price contract?

A

Sets a limit the employer will pay the contractor regardless of the works incurred.

24
Q

What are contractor preliminaries?

A

Items that cannot be allocated to a specific project element.

25
Q

Can you give some examples of preliminaries?

A

Management and Staff
Site establishment
Temporary services
Security
Insurances

26
Q

What is a BoQ?

A

Means of breaking down the project into exact quantities which are measured in an industry wide recognised standard

27
Q

What is Life Cycle Costing?

A

Assesses costs occurring throughout a building’s lifespan, from construction, through use and maintenance, to end-of-life.

28
Q

What is an interim valuation?

A

A document pit forward by the contractor detailing their progress against each of the work elements.

29
Q

What is a variation?

A

A change or alteration to the scope of works.

30
Q

What is a pay-less notice?

A

Gives the paying party the right to pay less than the amount in the payment notice

31
Q

What is the payment timeline for a JCT D&B Contract?

A

Interim valuation date 7 days before Due Date
Due Date - Valuation
Payment notice - Issued by employer stating sum it considers is due on the due date. 5 days after Due Date
Payless notice At least 5 days before Final Date for Payment
Final date for payment. 14 days after Due Date

7 days from Interim Valuation Date to Due Date. 14 Days from Due Date to Final Payment

32
Q

What is the payment timeline for NEC Contracts

A

Assessment Date
Interim Valuation 7 Days
Due Date
Interim certification 5 days
Payless notice
Final Payment 7 days

33
Q

What is the final account?

A

The conclusion of the contract sum and signifies the agreed amount the employer will pay the contractor.

34
Q

Why did you want to avoid negative cashflow?

A
  • Insolvency risk
  • Cannot procure packages causing a programme risk
35
Q

Funding vs Financing

A

Financing is obtaining money for a project. Funding is money provided by an organization or government, for a particular purpose

36
Q

What is meant by the term surity?

A

Someone taking on the risk for another’s performance