3 - Development and Project Briefs Flashcards

1
Q

What is a business case?

A

The rationale behind the implementation of a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When is a business case done and what should it include?

A

Starts out the outset and develops with the project. It should include:

  • Reasons, business drivers, vision etc.
  • Required outcomes
  • Potential options
  • Objective and subjective considerations
  • Funding

When it develops, feasibility and cost analysis can be added.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the difference between a Business Case and a Feasibility Study?

A

Business case sets out the rationale for the project, whereas a feasibility study assesses how successful it could be.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a Feasibility Study and what does it contain?

A

Assessment of whether a project can be successful.

  • Summary of Client Brief / Business Case
  • Risks, Opportunities and Constraints
  • Site appraisal
  • Option comparison
  • Outline programme
  • Commercial analysis
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

At what RIBA stage should a feasibility study be done?

A

RIBA 0 - Strategic Definition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

At what RIBA stage should a Business Case be done?

A

RIBA 0 - Strategic Definition. But it should be a working document all the way through.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a Development Appraisal?

A

An assessment of the total development costs to look at overall profitability - supposed to answer the question ‘is it worth it?’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a Strategic Brief? How is it different to a Client Brief? How are they both different to a Project Brief?

A
  • SB comes at RIBA 0 describing the client’s requirements in sufficient detail to allow consultant appointments
  • CB then comes next (still RIBA 0) and sets out the client requirements
  • PB then comes in RIBA 1 which is an evolving document helped by the appointed consultants.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the Key Documents at the end of RIBA 1?

A
  • Project Brief
  • PEP
  • Appoint the professional team
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a PEP and when is it done?

A

Done at end of RIBA 1. Sets out the delivery execution plan of the project

  • Organogram
  • Constraints and risks
  • Stakeholders
  • Procedures to be followed such as change control and escalation
  • Reporting requirements

Maintained and updated throughout / approved by Client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What tools can assist in developing a Project or Client Brief?

A
  • PESTLE
  • Discussion with client
  • Due Diligence reports
  • Consultant discussions
  • Initial programmes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the RIBA stages?

A

0 - Strategic Definition
1 - Preparation and Briefing
2 - Concept Design
3 - Spatial Coordination
4 - Technical Design
5 - Manufacturing and Construction
6 - Handover
7 - Use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the GRIP stages?

A

This relates to rail infrastructure. I would ask an engineer regarding these design stages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What information is within a project brief?

A

DCS PP
Description of the client
Site information
Constraints
Programme
Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a project brief?

A

Defines the clients requirements and objectives allowing the project to be designed and specified.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How do you ensure the project brief is met?

A

Reviewing the design at the end of each RIBA Stage.
Reviewing the brief at key meetings
Capturing changes through the change control process

17
Q

What changed from RIBA Plan of Work 2013 to 2020?

A
  • Developed Design is Spatial Coordination / In-Use became Use
  • Addition of Manufacture in Stage 5
  • Green and BIM overlay from 2013 now incorporated
  • Sustainability project strategy. Design must focus on sustainable outcomes from the outset
18
Q

When would you do the development brief ?

A

RIBA 0

19
Q

What is a yield

A

Earning generated on an investment over a particular period of time

20
Q

What is a development brief?

A

Sets out the vision for a development
- Client description
- Organisational structure
- Planning requirements
- Consultation
- Budget
- Risks
- Client Requirements

21
Q

Statement of Need?

A

Describe possible requirements for the project