ECI contractor selection

A

non price attributes since price is negotiated once risks and such are discussed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

adv of ECI

A
work alongside agency
best for project, descisions made
innovation
better risk assessment
results in cheaper shorter greater cost certainty
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what are the three sperable portions in ECI

A

first, inital research, non price tender, request for funding . then
1 secondary investigation and first design-
2 planning and specimen design.
for 1 and 2, design is peer reviewed and time cost is negotiated
3 construction
for 3 a parallel estimator is hired for costing of works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

results. is ECI faster

A

no consensus, owner and contractors think faster but consultants think length cost negotiation and longer since involving contractor in design phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

results, is eci cheaper

A

cheaper for owner, not for consultant-dont like open book

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

is eci better quality

A

yes, clear objectives
ECI encourages work above expectations due to project
‘ownership’ but isnt better for environment bc resource consent legal stuff is the same depsite it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

eci-staff involvement issues

A
  • culture is biggest barrier,

- senior staff need to be there for key decisions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

risk factor eci

A

contractors have greater risk bc they are involved with the design but they know all details so overall lower risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

ECI is hybrid of what

A

allience (design phase) and DB (construction)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

when to use ECI

A

If there is a risk of not obtaining competitive tenders using other
procurement methods

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

so end adv and disadv of ECI

A
tendering process less costly
early procurement of materials
increased innovation
fewer variations during construction 
disadvantages
increased cost from optioneering
increased cost for having to hire a cost estimator
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

PBMC

A

performance based management contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

adv PBMC

A

reduction in costs, risk transfer, economies of scale, enhanced asset management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

disadv PBMC

A

costly tendering
long tender period
loss of flexibility
reduction in competition.