lecture 6 and 7 Flashcards

1
Q

two types of public law

A

criminal law,

taxation law/revenue

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

private law

A

contract law

law of tort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

other laws

A

international, national laws

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

sources of law

A

statutory -written by a body of legislators
(health and saftey, builidng act etc)
common law- is law developed by judges, courts,
Regulations-
By laws

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Building act consists of (2004)

A

people must be able to use it saftely
can excape in fire
attributes that enhance peoples living
promote sustainable environment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

health and saftey 1992

A

The Department of Labour administers and
enforces the HSE Act in most workplaces.
to promote the prevention of harm to all people at
work, and others in, or in the vicinity of, places of
work.
systematic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Chartered Professional Engineers of

New Zealand Act 2002

A
  • acts a registration
  • code of ethics
  • has professional body to make sure that happens
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Construction Contracts Act 2002

A

timely payments
provide speedy resolutions for disputes
provide remedy for recovery of payments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Resource management act 1991

A
to promote the sustainable management of natural
and physical resources, while
sustaining natural resources
mitigating negative effects
safeguarding air water etc
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what is a contract

A

promise between able parties, that create an obligation that is enforable by law

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

privity of a contract

A

the relation between the parties in a contract which entitles them to sue each other but prevents a third party from doing so.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

elements of a contract

A
offer
acceptance
consideration
intention to be bound
capacity
reality of consent
legality
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

3 forms of contract

A

contract
deed
covenant -covenantor makes promise to do or not do somthing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Offer

A
time dependant
can be revoked
comunicated
intending to lead to a binding contract
needs to be promissory
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

revocation of offer

A

can revoke before accepted
-scheduled revocation’good until’
offer revoked by counter offer -offeree asking for somthing else

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

so whats the order of things

A

invitation to treat
offer
acceptance
contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

a quote is an offer but must

A

state what work to be done
how long
rates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

how must accept

A

formal notification
by placing an order
by implication (tacit)
by reliance (offer used in subsequent tender offer)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

reaility of consent

A

mistake-wrong calcullation
missrepresentation -as an engineer you may give wrong information which leads contractor going into contract
duress-3rd party pressure to contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Procurement

A

the framework within which
construction is brought about, acquired, or
obtained.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is the difference between purchasing and procuring

A

procuring deals with the negotioation, and strategic selection of services and goods whereas purchasing is just odrering

22
Q

What is a procurement contract?

A

a contract where a buyer agrees to buy goods from a seller in exchange for consideration

23
Q

Rules of Contract Administration

A
  1. Read the contract!
  2. Do what the contract tells you to do!
  3. Do not do what the contract tells you not to
    do!
24
Q

list the delivery methods

A

-negotiated
-Design big build (traditional)-DBB
Design build (DB)
Project Manager Agent (CMA)
PPP
Alliances
Early contractor involvement

25
DEsign BID BUILD
owner has contracts with engineer, and contractor seperatly. 3 players. 2 contracts. 3 phases, design bid build
26
selection process for DBB
designer-qualifications based | contractor-lowest bid
27
DBB advantages for owner and contractor
``` owner-historically accepted -price fixed before construction. owner involvment is low -contractor takes risk for construction CONTRACTOR -contractor sets price owner involvement is low innobvation=opportunity ```
28
DBB disadvantages
``` OWNER -long delivery time no adive during design lead to change in scope low bid not always low final cost. COntractor low margins high risk for unforeseen conditions ```
29
Project Manager Agent (CMA)
4 players, 3 contracts, owner to architect, manager and consultant 3 phases, desgin bid build
30
Project manager agent selection process
PM-qual A/e qual QC low bid
31
CMA advantages
OWNER -increased representation flexibility increased value engineering
32
project manager disadvantages
OWner PM assumes no risk-owner holds contracts still PM licensing not avaliable higjh owner/PM invovlement
33
Design and Build
4 players, owner A/E, GC and desing builder. 2 phases, design build 1 contract
34
selection process
DB-qual and low bid
35
DB advantages
``` OWNER -reduced duration high constructability -claims reduction DB get both design and construction fees good relationship with AE and GC react quick to scope changes ```
36
DB disadvantages
``` OWNER reduced involvement difficulty of selection DB large staff more risk scope changes difficult to track ```
37
whats the trend with these delivery processes
DB going up DBB going down CMA staying low
38
comparison for cost
DB costs 4.5% less than DBB | DB cost 1.5%less than CMA
39
why this difference in cost
DBB expensive bc phases dont overlap, timely, change in scope=big cost,. CMA next as expensive bc price settled before design, less competion. DB cheapest. fastest
40
ALLIance
``` costly to start selection on qualification better quality major contractors are now stakeholders -group environment, creative open book risk sharing is major difference ```
41
PPP
public private partnership has to be larger than 50 mill 25-35 years large projects
42
PPP more characteristecs
output clearly measurable | delivers an asset not an avctivity
43
more PPP
costed on whole life basis high maintenance requirements-transfer maint shift risk to private sector
44
what was the result of the leighton works JV and what does it mean
the main contractor did not have to act fairly in choosing the subcontractors tender by law. this mean anyone tendering where the docunents fo not fully comply with the hoigh corurt criteria can have no expectatio that their tender will be treatred fair. or that late tenders willl not be sought.
45
list the order of how tenders go down
contractor makes invitation to treat which includes conditions. tenderer makes an offer, if it is non capable of acceptance it is a non conforming tender. this is either accepted or negotiated
46
first lot of steps in southern road project preperation
designation(land designated to be built on) concept design specimen design PRINCIPAL REQUIREMENTS consents (need specific details, no room for change after) appeals
47
Tender steps In Souther road project
interactive meetings then supply quality premium then tangible cost adjustment then price evaluation with these two factors. lowest adjusted tender is used
48
what is SQP
supply quality premium-track record, scale for risk
49
what is TCA
tangible cost adjustment | adjust price for using different parts of other tenders
50
what occurs during construction to assure no suprises
certification
51
why do Consenting procedures work against DB | practice
because to get a consent for the project you need all specifications which leaves no room for changes which would normally be done in db. DBB is allg with consenting proceudres
52
advantages and dis of the southern road project
- increased competition throguh interavtive meetings | - reduced competition through reduced numbers of bidders