Lecture 7. Procurement II Flashcards

1
Q

Delivery methods?

A
  • Negotiated
  • Design bid build (DBB) (tradition, lump sum, guaranteed -max price, measure and value, cost reimbursement)
  • Design and construct (design-build)
  • Project manager agent (CMA)
  • Alternate delivery methods. (PPP, alliances, early contractor involvement)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Design bid build communication and contract relation with owner, architects/ engineers and contractor?

A

Communication between A/E - Owner - Contractor.

Contract between A/E - Owner and Owner - Contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Characteristics of DBB?

A

3 linear phases
3 primary players (a/e, owner, gc)
2 contract (as in other question)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Selection process of DBB?

A
Designer = qualification based
GC = lowest responsible bid
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Advantages and disadvantages of design bid build?

A

in notes lol

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Project Manager Agent characteristics?

A

3 linear phases
4 primary players (owner, PM, a/e, gc)
3 contracts (owner - pm, owner - a/e, and owner - gc)
Communication between all.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Selection process of Project Manger Agent?

A
PM = Qualification based
A/E = Qualification based
GC = Lowest responsible bid
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Advantages to Project Manager Agent?

A

All for the owner.

Increased representation,independent evaluation, increased constructibility, increased value engineering.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Disadvantages to Project Manager Agent?

A

All for the owner.
PM assumes no risk (owner hold contract), PM agency doesn’t guarantee costs, PM licensing is not available, high owner/PM involvement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Characteristics of Design and Construct (Design-Build)?

A

2 continuous phases (design and build).
2 primary players (owner and DB)
1 contract (owner-DB)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Selection process of DB?

A

DB = Qualification based/ low bid.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Design build advantages and disadvantages?

A

Check notes - too many lol.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What delivery method is currently more popular in the states?

A
Design build (50%)
Design bid build (40%)
Construction management (10%)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which costs less, DB or CMR?

A

DB by 4.5%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which cost more, DB or DBB?

A

DBB by 6%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which cost less, DBB or CMR?

A

CMR by 1.5%

17
Q

Which is faster, DB or CMR?

A

DB by 7%

18
Q

Which is slower, DB or DBB?

A

DBB by 12%

19
Q

Which is slower, DBB or CMR?

A

DBB by 12%

20
Q

Out of the three main delivery methods, which is done at a higher quality?

A

DB is equal or better than DBB or CMR.

21
Q

Alliance?

A

Check notes, too much.

22
Q

What does PPP stand for?

A

Public Private Partnerships.

23
Q

What are the characteristics for PPP?

A

Large scale ($50Mil and upwards)
25 - 35 years to amortise the capital costs.
Large complex projects, require close coordination.
Service or output focus.
Private sector expertise required.
and so much more in notes, look at later…