Why s curve is called the s curve?

A

At beginning of project work is catching up
At the middle work is running smoothly
At the end work is slowing down

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How do you find maximum working capital from the two graphs?

A

By measuring the differences between the two graphs (cost and revenue)